MahaRERA Application

General Information

Other Than Individual

Organization

PALAVA DWELLERS PVT LTD
Company
NA
Do you have any Past Experience ?
No

Address Details

10TH FLOOR
LODHA EXCELUS
N M JOSHI MARG
LOWER PAREL
LOWER PAREL
MAHARASHTRA
Konkan
Mumbai City
Mumbai City
Mumbai City
400011

Organization Contact Details

02261334809

Past Experience Details

Member Information

Member Name Designation Photo
HITESH MARTHAK Director View Photo
Kunal Modi Authorized Signatory View Photo

Project

Violet A to C
New Project
31/07/2024
No
Residential
Yes
55/2 part and 55/5 part
55 by 5 part
55 by 2 part
55 by 2 part and 55 by 5 part
55 by 2 part and 55 by 5 part
MAHARASHTRA
Konkan
Thane
Kalyan
Khoni
Kalyan Shil fata road
Taloja
421204
2636
3
3
0
1514.38

FSI Details

14675.74
0
14675.74

Bank Details

IDBI BANK
IBKL0000454

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Violet A to C Macrotech Developers Ltd Company Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 NA
Water Conservation, Rain water Harvesting : NO 0 NA
Energy management : YES 0 NA
Fire Protection And Fire Safety Requirements : YES 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Shared across various phases
Aggregate area of recreational Open Space : YES 0 NA
Open Parking : YES 0 NA
Water Supply : YES 0 NA
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 NA
Storm Water Drains : YES 0 NA
Landscaping & Tree Planting : YES 0 NA
Street Lighting : YES 0 NA
Community Buildings : YES 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 NA
Solid Waste Management And Disposal : YES 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Violet A to C Violet A 31/07/2023 0 1 0 13 0 5 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 29.36 3 1
2 2BHK 40.41 2 2
3 2BHK 43.66 1 1
4 2BHK 39.76 50 50
5 2BHK 36.88 57 57
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 43
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 55
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

26
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 42.4
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Violet A to C Violet B 31/07/2023 0 1 0 13 0 7 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 29.36 2 0
2 2BHK 43.66 5 2
3 1BHK 27.03 12 11
4 2BHK 39.76 112 108
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 29
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 55
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

15
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 39.9
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Violet A to C Violet C 31/07/2023 0 1 0 13 0 5 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 29.36 1 1
2 2BHK 36.88 12 12
3 2BHK 43.66 4 4
4 1BHK 29.91 11 11
5 2BHK 39.76 69 69
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 55
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

13
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 36.8

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
A NA Contractor
VILAS DESAI & ASSOCIATES NA Architect
K C SHAH CONSULTANTS NA Engineer
B B JAIN & ASSOCIATES NA Chartered Accountant
MSKA & ASSOCIATES NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
3 Copy of the legal title report
4 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
5 Commencement Certificates / NA Order for plotted development
6 Commencement Certificates / NA Order for plotted development
7 Commencement Certificates / NA Order for plotted development
8 Commencement Certificates / NA Order for plotted development
9 Commencement Certificates / NA Order for plotted development
10 Commencement Certificates / NA Order for plotted development
11 Commencement Certificates / NA Order for plotted development
12 Commencement Certificates / NA Order for plotted development
13 Commencement Certificates / NA Order for plotted development
14 Commencement Certificates / NA Order for plotted development
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
1 CERSAI details
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of the allotment letter and agreement for sale
2 Proforma of the allotment letter and agreement for sale
3 Proforma of the allotment letter and agreement for sale
4 Proforma of the allotment letter and agreement for sale
5 Proforma of the allotment letter and agreement for sale
6 Proforma of the allotment letter and agreement for sale
7 Proforma of the allotment letter and agreement for sale
8 Proforma of the allotment letter and agreement for sale
9 Proforma of the allotment letter and agreement for sale
10 Proforma of the allotment letter and agreement for sale
11 Proforma of the allotment letter and agreement for sale
12 Proforma of the allotment letter and agreement for sale
13 Proforma of the allotment letter and agreement for sale
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical