Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
1 |
Panvel Pride
|
A WING
|
30/06/2024
|
0
|
1
|
0
|
4
|
1 |
0 |
15 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
30.170 |
4 |
0 |
2 |
1BHK |
30.490 |
4 |
0 |
3 |
2BHK |
43.520 |
4 |
0 |
4 |
1BHK |
29.320 |
3 |
0 |
5 |
1BHK |
29.620 |
4 |
0 |
6 |
1BHK |
29.860 |
2 |
0 |
7 |
1BHK |
29.870 |
2 |
0 |
8 |
1RK |
20.70 |
4 |
0 |
9 |
1RK |
21.260 |
4 |
0 |
10 |
1RK |
21.390 |
8 |
0 |
11 |
1BHK |
29.930 |
5 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
50
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
25
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
2 |
Panvel Pride
|
B WING
|
30/06/2024
|
0
|
1
|
0
|
4
|
1 |
0 |
15 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
28.760 |
2 |
0 |
2 |
2BHK |
44.170 |
2 |
0 |
3 |
1BHK |
30.270 |
2 |
0 |
4 |
1RK |
20.630 |
4 |
0 |
5 |
1BHK |
28.920 |
2 |
0 |
6 |
1BHK |
29.870 |
2 |
0 |
7 |
1BHK |
30.783 |
2 |
0 |
8 |
1BHK |
29.360 |
2 |
1 |
9 |
1BHK |
30.182 |
2 |
0 |
10 |
2BHK |
39.760 |
2 |
0 |
11 |
1BHK |
29.140 |
2 |
0 |
12 |
2BHK |
44.140 |
2 |
0 |
13 |
2BHK |
39.120 |
2 |
0 |
14 |
1BHK |
30.950 |
2 |
0 |
15 |
1RK |
21.200 |
4 |
0 |
16 |
1BHK |
29.490 |
2 |
0 |
17 |
1BHK |
30.550 |
2 |
0 |
18 |
1BHK |
28.540 |
2 |
1 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
10
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
33
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
33
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
4
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
48
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
3 |
Panvel Pride
|
C WING
|
30/06/2024
|
0
|
1
|
0
|
4
|
1 |
0 |
15 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK |
44.17 |
2 |
1 |
2 |
1BHK |
28.93 |
2 |
1 |
3 |
1BHK |
29.14 |
2 |
2 |
4 |
1BHK |
29.18 |
2 |
1 |
5 |
1BHK |
29.36 |
2 |
2 |
6 |
1BHK |
29.5 |
2 |
1 |
7 |
1BHK |
29.87 |
2 |
0 |
8 |
1BHK |
30.55 |
2 |
0 |
9 |
1RK |
19.29 |
4 |
2 |
10 |
1RK |
20.63 |
6 |
3 |
11 |
1RK |
21.2 |
6 |
6 |
12 |
1BHK |
28.54 |
2 |
2 |
13 |
1BHK |
28.76 |
2 |
2 |
14 |
1BHK |
29.74 |
2 |
1 |
15 |
1BHK |
30.28 |
2 |
1 |
16 |
1BHK |
30.96 |
2 |
1 |
17 |
2BHK |
44.14 |
2 |
2 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
25
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
33
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
33
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
4
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
49.5
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
4 |
Panvel Pride
|
D WING
|
30/06/2024
|
0
|
1
|
0
|
4
|
1 |
0 |
15 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1RK |
21.02 |
1 |
0 |
2 |
1RK |
20.3 |
1 |
1 |
3 |
1RK |
20.63 |
5 |
3 |
4 |
1RK |
21.2 |
4 |
4 |
5 |
1RK |
21.37 |
9 |
6 |
6 |
1BHK |
28.6 |
4 |
2 |
7 |
1BHK |
29.2 |
4 |
4 |
8 |
1BHK |
29.26 |
6 |
1 |
9 |
1BHK |
29.5 |
4 |
2 |
10 |
1BHK |
29.82 |
4 |
1 |
11 |
2BHK |
43.54 |
4 |
4 |
12 |
1BHK |
28.9 |
4 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
60
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
20
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
10
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
3
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
39.3
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
5 |
Panvel Pride
|
E WING
|
30/06/2024
|
0
|
1
|
0
|
4
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
30.580 |
1 |
0 |
2 |
1BHK |
30.370 |
1 |
0 |
3 |
1BHK |
29.19 |
6 |
1 |
4 |
1BHK |
29.63 |
2 |
1 |
5 |
1BHK |
29.79 |
2 |
1 |
6 |
1BHK |
29.81 |
2 |
2 |
7 |
1BHK |
30.22 |
2 |
1 |
8 |
1BHK |
31.11 |
2 |
1 |
9 |
1BHK |
31.12 |
3 |
1 |
10 |
1BHK |
31.75 |
2 |
2 |
11 |
1BHK |
30.79 |
2 |
2 |
12 |
2BHK |
39.14 |
3 |
2 |
13 |
1BHK |
29.38 |
2 |
0 |
14 |
1BHK |
28.76 |
3 |
1 |
15 |
1BHK |
28.89 |
1 |
1 |
16 |
1BHK |
30.56 |
2 |
0 |
17 |
1BHK |
29.16 |
2 |
0 |
18 |
2BHK |
39.74 |
2 |
0 |
19 |
1BHK |
31.79 |
2 |
0 |
20 |
1BHK |
31.26 |
2 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
80
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
30
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
33
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
33
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
4
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
48
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
6 |
Panvel Pride
|
F WING EWS and Sales
|
30/06/2024
|
0
|
1
|
0
|
4
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK |
39.75 |
1 |
0 |
2 |
2BHK |
40.640 |
2 |
0 |
3 |
2BHK |
41.40 |
4 |
0 |
4 |
1BHK |
36.350 |
5 |
0 |
5 |
1BHK |
39.07 |
15 |
0 |
6 |
2BHK |
43.18 |
5 |
0 |
7 |
2BHK |
46.22 |
5 |
0 |
8 |
1BHK |
28.990 |
1 |
0 |
9 |
1BHK |
29.43 |
1 |
0 |
10 |
1BHK |
29.750 |
1 |
0 |
11 |
1BHK |
30.05 |
3 |
0 |
12 |
1BHK |
30.20 |
5 |
0 |
13 |
1BHK |
30.430 |
2 |
0 |
14 |
2BHK |
42.04 |
4 |
0 |
15 |
1BHK |
33.480 |
5 |
0 |
16 |
1BHK |
33.490 |
10 |
0 |
17 |
1BHK |
35.990 |
10 |
0 |
18 |
1BHK |
30.730 |
2 |
0 |
19 |
1BHK |
30.80 |
4 |
0 |
20 |
1BHK |
37.60 |
4 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
80
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
18
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
7 |
Panvel Pride
|
G WING
|
30/06/2024
|
0
|
1
|
0
|
4
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1RK |
21.600 |
2 |
0 |
2 |
2BHK |
43.540 |
4 |
0 |
3 |
2BHK |
45.200 |
1 |
0 |
4 |
1RK |
20.300 |
2 |
0 |
5 |
1BHK |
29.190 |
4 |
0 |
6 |
1BHK |
29.260 |
4 |
0 |
7 |
1BHK |
29.490 |
2 |
0 |
8 |
1BHK |
29.500 |
2 |
0 |
9 |
1BHK |
29.820 |
4 |
0 |
10 |
1RK |
21.640 |
1 |
0 |
11 |
1RK |
22.360 |
1 |
0 |
12 |
1RK |
22.890 |
1 |
0 |
13 |
1BHK |
28.600 |
4 |
0 |
14 |
1BHK |
28.900 |
4 |
0 |
15 |
1RK |
20.630 |
4 |
0 |
16 |
1RK |
20.860 |
2 |
0 |
17 |
1RK |
21.190 |
4 |
0 |
18 |
1RK |
21.370 |
8 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
80
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
18
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
8 |
Panvel Pride
|
H WING
|
30/06/2024
|
0
|
1
|
0
|
4
|
1 |
0 |
15 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1RK |
20.3 |
2 |
2 |
2 |
1RK |
20.63 |
4 |
2 |
3 |
1RK |
21.02 |
2 |
1 |
4 |
1RK |
21.2 |
4 |
2 |
5 |
1RK |
21.37 |
8 |
4 |
6 |
1BHK |
28.6 |
4 |
1 |
7 |
1BHK |
28.84 |
2 |
1 |
8 |
1BHK |
28.9 |
4 |
2 |
9 |
1BHK |
29.2 |
4 |
3 |
10 |
1BHK |
29.26 |
4 |
1 |
11 |
1BHK |
29.5 |
4 |
3 |
12 |
1BHK |
29.82 |
4 |
2 |
13 |
2BHK |
43.54 |
4 |
3 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
60
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
20
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
33
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
33
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
4
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
45
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
9 |
Panvel Pride
|
I WING
|
30/06/2024
|
0
|
1
|
0
|
4
|
1 |
0 |
15 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1RK |
20.63 |
6 |
4 |
2 |
1RK |
21.2 |
2 |
1 |
3 |
1RK |
21.37 |
8 |
5 |
4 |
1BHK |
26.92 |
2 |
2 |
5 |
1BHK |
26.96 |
2 |
1 |
6 |
1BHK |
28.78 |
2 |
2 |
7 |
1BHK |
28.8 |
2 |
2 |
8 |
1BHK |
29.03 |
4 |
3 |
9 |
1BHK |
29.39 |
2 |
1 |
10 |
1BHK |
29.4 |
2 |
1 |
11 |
2BHK |
44.26 |
2 |
2 |
12 |
2BHK |
44.27 |
2 |
2 |
13 |
1BHK |
29.71 |
2 |
0 |
14 |
1BHK |
29.15 |
2 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
80
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
25
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
33
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
33
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
4
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
47.5
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
10 |
Panvel Pride
|
J WING
|
30/06/2024
|
0
|
1
|
0
|
4
|
1 |
1 |
4 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
27.69 |
2 |
1 |
2 |
1BHK |
27.71 |
2 |
1 |
3 |
1BHK |
27.96 |
4 |
3 |
4 |
1BHK |
28.25 |
2 |
2 |
5 |
1BHK |
28.54 |
4 |
3 |
6 |
1BHK |
28.29 |
2 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
40
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
24
|
|