MahaRERA Application

General Information

Other Than Individual

Organization

Alder Residency Private Limited
Company
NA
Do you have any Past Experience ?
No

Address Details

101
Kalpataru Synergy
Vakola
Santacruz East
Opp Grand Hyatt
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400055

Organization Contact Details

02230645000

Past Experience Details

Member Information

Member Name Designation Photo
Amit Shah Authorized Signatory View Photo
Saugato Dey Authorized Signatory View Photo

Project

Kalpataru Vivant - South Wing B
New Project
31/03/2028
No
Residential
No
CTS No 33A,62, 76 of village Majas
CTS No 33A PT of village Majas
CTS No 33A PT of village Majas
CTS No33A PT vill Majas and touching to wing A
CTS No 33A PT of village Majas
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
Station Road
JVLR
400060
371.86
1
1
0
0

FSI Details

4807.22
196.01
5003.23

Bank Details

HDFC Bank Ltd
HDCF0000060

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 36 50 21

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 To be done before completion of Whole Project
Water Conservation, Rain water Harvesting : YES 0 To be done before completion of Whole Project
Energy management : YES 0 To be done before completion of Whole Project
Fire Protection And Fire Safety Requirements : YES 0 To be done before completion of Whole Project
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Electric Meter Room only
2 No. of Common Basement : YES 0 To be done before completion of Whole Project
3 Nos of Common Podium : YES 0 To be done before completion of Whole Project
Club house, swimming pool & other recreation areas : YES 0 Common Amenities as per AFS
Aggregate area of recreational Open Space : YES 0 5748.618 Sq. Mts. Common RG as per AFS
Open Parking : NO 0 NA
Water Supply : YES 0 Water Supply from Local Authority
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 To be done before completion of Whole Project
Storm Water Drains : YES 0 To be done before completion of Whole Project
Landscaping & Tree Planting : YES 0 To be done before completion of Whole Project
Street Lighting : YES 0 To be done before completion of Whole Project
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 To be done before completion of Whole Project
Solid Waste Management And Disposal : YES 0 To be done before completion of Whole Project

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Kalpataru Vivant - South Wing B South Ridge B 31/12/2026 3 1 1 22 1 0 36
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 1692.91 43 23
2 2BHK 2243.31 43 31
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 98
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 48
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 2
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 13
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 1
11 Overall Percentage of Completion of the work done For the entire Building /Wing 36.2

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SAINATH ESTATE A51800012047 Real Estate Agent
Mystic India Realtors LLP A51900006152 Real Estate Agent
KEY MANSIONS PRIVATE LIMITED A51900001761 Real Estate Agent
PYRAMID PROPERTY CONSULTANTS PVT LTD A51800007429 Real Estate Agent
Addressofchoice Realty Pvt Ltd A52100000116 Real Estate Agent
PROPTIGER MARKETING SERVICES PRIVATE LIMITED A51700000030 Real Estate Agent
Manisha Lifespaces Consulting Pvt. Ltd. A51800008040 Real Estate Agent
360 REALTORS LLP A51900000246 Real Estate Agent
CRAFT FINANCIAL ADVISORS PVT LTD A51900000136 Real Estate Agent
Home Bazaar Services Pvt Ltd A52000000045 Real Estate Agent
AVS LIFESTYLES PVT. LTD A51800003363 Real Estate Agent
Nandkumar V Jethe ( Form 1 and Form 4) NA Architect
Ganesh Lad (Form 2) NA Engineer
C R Mohnot & Co ( CA Certificate-Form 3) NA Chartered Accountant
Kapadia Associates Design Llp (Design Architects) NA Other Professional
Whitby Wood Pritamdasani Consulting Engineers Pvt Ltd. (Structural Consultant) NA Other Professional
Maple Engg Design Services(India) Private Limited (MEP Consultant) NA Other Professional

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
2 Declaration about Commencement Certificate
3 Declaration about Commencement Certificate
4 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
1 CERSAI details
2 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement