MahaRERA Application

General Information

Individual

Individual

JEETENDRA ALIAS RAVI
AMARNATH
KAPOOR
AMARNATH KAPOOR
No

Address For Official Communication

PLOT 27 JVPD
TUSSHAR HOUSE
N S ROAD NO.7 JUHU
VILE PARLE WEST
N S ROAD NO. 7
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400049

Contact Details

02226707782

Past Experience Details

Project

IRIS MIRA ROAD E
New Project
30/12/2022
No
Others
No
21/1, 24/2
SURVEY NO 21-2
SURVEY NO 27-4
SURVEY NO 20-5 AND 20-7
SURVEY NO 24-3
MAHARASHTRA
Konkan
Thane
Thane
Mira-Bhayandar (M Corp.)
VILLAGE GHODBANDAR
VILLAGE GHODBANDAR TALUKA AND DISTRICT THANE
401107
19363
3
3
0
2644.75

FSI Details

14368.74
00
14368.74

Bank Details

ICICI BANK LTD
ICIC0000366

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 00 00 00
Covered Parking ( In Numbers) 230 00 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 PAVING
Water Conservation, Rain water Harvesting : YES 100 WORK IN PROGRESS
Energy management : YES 100 WORK IN PROGRESS
Fire Protection And Fire Safety Requirements : YES 100 WORK IN PROGRESS
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 WORK IN PROGRESS
Aggregate area of recreational Open Space : YES 100 WORK IN PROGRESS
Open Parking : YES 100 COMPLETE
Water Supply : YES 100 AS PER THE RULES OF THE MBMC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 WORK IN PROGRESS
Storm Water Drains : YES 100 WORK IN PROGRESS
Landscaping & Tree Planting : YES 100 WORK IN PROGRESS
Street Lighting : NO 0 NA
Community Buildings : YES 100 WORK IN PROGRESS
Treatment And Disposal Of Sewage And Sullage Water : YES 100 WORK IN PROGRESS
Solid Waste Management And Disposal : YES 100 WORK IN PROGRESS

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 IRIS MIRA ROAD E BUILDING F 31/12/2021 1 1 0 17 1 33 77
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 42.61 110 00
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 IRIS MIRA ROAD E BUILDING G 31/12/2021 1 1 0 17 1 33 77
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 42.61 110 00
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 IRIS MIRA ROAD E BUILDING H 31/12/2021 1 00 00 17 00 34 76
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 42.61 110 00
2 Shop 33.96 1 00
3 Shop 25.99 01 00
4 Shop 33.74 01 00
5 Shop 11.07 01 00
6 Shop 14.50 01 00
7 Shop 14.41 01 00
8 Shop 11.07 01 00
9 Shop 14.30 01 00
10 Shop 14.18 01 00
11 Shop 26 01 00
12 Shop 33.96 01 00
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
ANISH AND ASSOCIATES NA Architect
MAHIMTURA CONSULTANTS PVT LTD NA Engineer
PRERANA GHAT & ASSOCIATES NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
2 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement