MahaRERA Application

General Information

Other Than Individual

Organization

Jaikul Associates
Others
Association of Person
Do you have any Past Experience ?
No

Address Details

5th Floor
Pride House
Ganesh Khind Road
Shivaji Nagar
University Circle
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411016

Organization Contact Details

02067091000

Past Experience Details

Other Organization Type Member Information

Name Member Type
Vikas Kulkarni Individual
Sandeep Kulkarni Individual
RISHABH JAIN Individual

Project

KINGSBURY PHASE I
On-Going Project
31/12/2019
30/12/2022
Yes
Residential
No
129P, 135/1, 138, 139
ADJ PLOT OF NOTTINH HILL
ADJ BUILDING F1 F2 OF KINGSBURY
ADJ BUILDING B1 B2 OF KINGSBURY
ADJ S NO 135P
MAHARASHTRA
Pune
Pune
Haveli
CHARHOLI
DY PATIL ROAD
CHARHOLI
412105
11483.48
6
6
0
00

FSI Details

50958.94
1400
52358.94

Bank Details

KOTAK MAHINDRA BANK
KKBK0001759

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 00 00 00
Covered Parking ( In Numbers) 420 285 00

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 80 applicable
Water Conservation, Rain water Harvesting : YES 100 applicable
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 applicable
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 applicable
BASEMENT : YES 2 applicable
Aggregate area of recreational Open Space : YES 0 applicable
Open Parking : YES 80 applicable
Water Supply : YES 100 applicable
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 applicable
Storm Water Drains : YES 100 applicable
Landscaping & Tree Planting : YES 60 applicable
Street Lighting : YES 60 applicable
Community Buildings : YES 0 applicable
Treatment And Disposal Of Sewage And Sullage Water : YES 100 applicable
Solid Waste Management And Disposal : YES 100 applicable

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 KINGSBURY PHASE I C1 31/12/2021 0 1 1 16 1 3 70
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3RLK 83.66 8 7
2 3RLK 85.44 8 7
3 2RLK 65.76 1 0
4 2RLK 60.85 1 0
5 2RLK 60.89 7 0
6 2RLK 61.99 1 0
7 2RLK 62 1 0
8 2RLK 64.74 7 1
9 3RLK 85.02 8 5
10 3RLK 85.16 1 1
11 2RLK 60.01 8 1
12 2RLK 60.46 7 5
13 2RLK 61.36 7 1
14 2RLK 65.16 8 4
15 3RLK 83.21 7 7
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 88
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 95
11 Overall Percentage of Completion of the work done For the entire Building /Wing 89.3
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 KINGSBURY PHASE I C2 31/12/2021 0 1 1 16 1 3 71
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2RLK 60.85 1 0
2 2RLK 61.99 1 0
3 2RLK 65.76 1 0
4 3RLK 85.16 1 0
5 2RLK 62 1 1
6 2RLK 61.36 7 3
7 2RLK 60.46 7 7
8 3RLK 83.21 7 7
9 3RLK 83.66 8 8
10 3RLK 85.02 8 7
11 2RLK 60.01 8 5
12 2RLK 60.89 7 2
13 2RLK 64.74 7 3
14 2RLK 65.16 8 5
15 3RLK 85.44 8 7
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 88
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 95
11 Overall Percentage of Completion of the work done For the entire Building /Wing 89.3
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 KINGSBURY PHASE I D1 31/12/2021 0 1 1 16 1 3 63
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2RLK 63.24 1 1
2 2RLK 66.62 1 1
3 2RLK 63.26 1 0
4 2RLK 62.33 1 0
5 2RLK 65.14 8 8
6 2RLK 62.44 7 7
7 2RLK 63.11 1 1
8 2RLK 62.07 8 6
9 3RLK 83.56 8 8
10 3RLK 83.11 7 7
11 2RLK 61.94 7 7
12 2RLK 64.72 7 7
13 3RLK 86.15 1 0
14 2RLK 62.49 7 7
15 2RLK 61.25 8 7
16 2RLK 61.76 7 7
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 KINGSBURY PHASE I D2 31/12/2021 0 1 1 16 1 3 73
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2RLK 62.44 7 7
2 2RLK 61.25 8 0
3 2RLK 63.11 1 0
4 2RLK 64.72 7 7
5 2RLK 65.78 1 0
6 2RLK 63.24 1 1
7 3RLK 85.64 1 1
8 2RLK 63.26 1 0
9 3RLK 83.11 7 7
10 2RLK 61.94 7 7
11 3RLK 83.56 8 8
12 2RLK 61.76 7 5
13 2RLK 62.07 8 6
14 2RLK 65.14 8 7
15 2RLK 62.33 2 2
16 2RLK 62.49 7 7
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
5 KINGSBURY PHASE I E1 31/12/2021 0 1 1 16 1 3 70
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2RLK 63.24 1 1
2 2RLK 65.14 8 8
3 3RLK 83.11 7 7
4 3RLK 83.56 8 8
5 2RLK 62.44 7 7
6 2RLK 61.94 7 6
7 3RLK 85.64 1 1
8 2RLK 62.07 8 7
9 2RLK 62.33 2 1
10 2RLK 64.72 7 7
11 2RLK 61.76 7 6
12 2RLK 65.78 1 1
13 2RLK 61.25 8 7
14 2RLK 63.26 1 1
15 2RLK 63.11 1 1
16 2RLK 62.49 7 7
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
6 KINGSBURY PHASE I E2 31/12/2021 0 1 1 16 1 3 71
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2RLK 63.24 1 1
2 3RLK 85.64 1 0
3 2RLK 65.78 1 0
4 2RLK 63.26 1 0
5 2RLK 62.33 1 0
6 2RLK 62.44 7 7
7 3RLK 83.11 7 7
8 2RLK 65.14 8 7
9 3RLK 83.56 8 8
10 2RLK 63.11 1 1
11 2RLK 61.94 7 6
12 2RLK 64.72 7 7
13 2RLK 61.25 8 1
14 2RLK 61.76 7 6
15 2RLK 62.07 8 6
16 2RLK 62.49 7 7
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
PARAMAOUNT PEST CONSULTANTS PVT LTD NA Contractor
OMSAI ENTERPRISES NA Contractor
SHRI MAHALAXMI ENTERPRISES NA Contractor
SNEHAL ENTERPRISES NA Contractor
MILLENIUM ENGINEERS & CONTRACTORS PVT LTD NA Contractor
SHUBHANKAR ASSOCIATES NA Contractor
YOGESHWARI ELECTRICALS NA Contractor
VERTEX ENGINEERING & CONTRACTOR NA Contractor
EXPERT SALES & CONTRACT SERVICES PVT LTD NA Contractor
WAGESHWAR FABRICATORS NA Contractor
MOON FABRICATIONS NA Contractor
MONA FABRICATIONS NA Contractor
SAISHRADHA FABRICATIONS & ENGINEERING WORKS NA Contractor
SAIPRASAD ENTERPRISES NA Contractor
AP ENTERPRISES NA Contractor
KP ASSOCIATES NA Contractor
AAKASH ENTERPRISES NA Contractor
AVINASH ANNASAHEB PATIL NA Architect
STURDCOM CONSULTANTS PVT LTD NA Engineer
ABHIKALPAN ARCHITECTS & PLANNERS NA Other Professional
ACE CONSULTANTS NA Other Professional
CONSOLIDATED CONSULTANTS & ENGINEERS PVT LTD NA Other Professional
ABHIKALPAN ARCHITECTS & PLANNERS NA Other Professional
HDFC Realty Limited A51900000107 Real Estate Agent
RAHUL ANAND GAIKWAD A52100000661 Real Estate Agent
SANTOSH KUMAR A52100000143 Real Estate Agent
360 REALTORS LLP A51900000246 Real Estate Agent
Pankaj Kumar Chaurasia A52100000283 Real Estate Agent
PROPERTY CHEF CONSULTING SERVICES A52100000044 Real Estate Agent
JONES LANG LASALLE RESIDENTIAL PRIVATE LIMITED A51900000108 Real Estate Agent
Nitesh Roop Narayan Khare A52100000106 Real Estate Agent
Nishant Madhukar Bhoinallu A52100007451 Real Estate Agent
CBRE South Asia Private Limited A51600003050 Real Estate Agent
PROPINN PROPERTIES PRIVATE LIMITED A52100011114 Real Estate Agent
SQUARE YARDS CONSULTING PRIVATE LIMITED A51800000454 Real Estate Agent
BAJAJ FINANCE LTD A52100003465 Real Estate Agent
NITIN SHANKAR KADDE A52100000577 Real Estate Agent
SUNIL SHARMA A52100008473 Real Estate Agent
VIJAY RAMCHANDRA JAGDALE A52100003858 Real Estate Agent
Big Deal Properties (India) Pvt. Ltd A52100000579 Real Estate Agent
ELARA MARKETING SERVICES PRIVATE LIMITED A51700000030 Real Estate Agent
Parag Madhukar Kamble A52100008547 Real Estate Agent
Pride Facility Managment Services A52100015230 Real Estate Agent
Park Facility Management Services A52100020109 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
KINGSBURY PHASE I CIVIL JUDGE JUNIOR DIVISION 29 Civil No Suit NA 2009 AT EVIDENCE STAGE
NA
KINGSBURY PHASE I DISTRICT COURT PUNE 127 Civil No Appeal NA 2017 APPEAL REJECTED
NA
KINGSBURY PHASE I DISTRICT COURT PUNE 862 Civil No Appeal NA 2016 APPEAL REJECTED
NA
KINGSBURY PHASE I MUMBAI HIGH COURT 225 Civil No Appeal NA 2009 ADMITTED BUT NO PREVENTIVE ORDER IN THE SECOND APPEAL
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Form 2A
2 Form 2A
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 CERSAI details
1 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
4 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Certificates of Architect (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
2 Status of Formation of Legal Entity (Society/Co Op etc.)
3 Status of Formation of Legal Entity (Society/Co Op etc.)
4 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement