MahaRERA Application

General Information

Other Than Individual

Organization

SHIV ASSOCIATES
Others
PROPRIETORSHIP
Do you have any Past Experience ?
Yes

Address Details

SHOP NO. 1 & 2
MARUTI COMPLEX
NEAR ASHOK THEATRE
PIMPRI
ASHOK THEATRE
MAHARASHTRA
Pune
Pune
Haveli
Pimpri Chinchawad (M Corp.)
411017

Organization Contact Details

02027410555

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1DIVINE DESIREOthersRESIDENTIAL & COMMERCIAL2625S NO 66 - RAHATANIS NO 66 - RAHATANI2932016-10-242016-10-24
2STONE RIDGE PHASE -IOthersRESIDENTIAL & COMMERCIAL10500S NO 315 - PIMPRIS NO 315 - PIMPRI41442014-02-242014-02-24
3MADHAVResidentialNA2063GAT NO. 59 & 60GAT NO 59 AND 602702017-06-282017-06-28

Other Organization Type Member Information

Name Member Type
SURESH DWARKADAS JUMANI Individual

Project

STONE RIDGE- II
New Project
30/06/2022
No
Residential
No
S NO 315/2/13- CTS NO 6768
S NO 313 AND 314
S NO 315
REMAINING PORTION OF S NO 315
PAVANA RIVER
MAHARASHTRA
Pune
Pune
Haveli
Pimpri Chinchawad (M Corp.)
PIMPRI WAGHERE COLONY
PIMPRI
411017
1654.33
2
2
0
0

FSI Details

4163
0
4163.00

Bank Details

DCB BANK
DCBL0000313

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 10 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 50 WILL BE PROVIDED
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 60 WILL BE PROVIDED
Electrical Meter Room, Sub-Station, Receiving Station : YES 70 WILL BE PROVIDED
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 0 0
Water Supply : YES 50 WILL BE PROVIDED
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 50 WILL BE PROVIDED
Storm Water Drains : YES 25 WILL BE PROVIDED
Landscaping & Tree Planting : YES 25 WILL BE PROVIDED
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 STONE RIDGE- II STONE RIDGE - II - E 30/06/2021 0 1 0 7 0 5 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 61.28 6 6
2 1BHK 44.82 6 6
3 1BHK 44.61 6 6
4 2BHK 61.24 3 3
5 2BHK 59.01 3 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 90
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

90
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 95
11 Overall Percentage of Completion of the work done For the entire Building /Wing 75
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 STONE RIDGE- II STONE RIDGE - II - G 30/06/2021 0 1 0 7 0 5 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 68.63 3 0
2 2BHK 68.12 3 0
3 2BHK 68.42 3 1
4 2BHK 64.27 6 1
5 2BHK 64.38 6 1
6 2BHK 68.71 3 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 80
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 75
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

25
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 10
11 Overall Percentage of Completion of the work done For the entire Building /Wing 45

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SANJEEV BHOSALE NA Architect
M/S G.A Bhilare Consultant Pvt Ltd NA Engineer
R M NESARIKAR & CO NA Chartered Accountant
Prathamesh Khule NA Other Professional

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement