MahaRERA Application

General Information

Other Than Individual

Organization

Swaminarayan Life Space LLP
Partnership
NA
Do you have any Past Experience ?
No

Address Details

2/5
Ratna Niwas
Nehru Road
Bhaji Market
Above Kunj Vihar Hotel
MAHARASHTRA
Konkan
Thane
Kalyan
DOMBIVLI
421201

Organization Contact Details

09930836889

Past Experience Details

Member Information

Member Name Designation Photo
Pundalik Balu Mhatre Partner View Photo
Jayesh Pundlik Mhatre Partner View Photo
Dipesh Pundlik Mhatre Partner View Photo
Dharmesh Ashok Joshi Partner View Photo
Vishal Ashok Joshi Partner View Photo
Rasiklal Doongershi Nisar Partner View Photo
Hirji Laxman Patel Partner View Photo
Hemant Mulchand Patel Authorized Signatory View Photo
Sachin Mulchand Vaviya Partner View Photo
Ashish Ramesh Manseta Partner View Photo
Jeram Shamji Patel Partner View Photo

Project

Swaminarayan City Phase 1A
New Project
30/12/2029
No
Others
Yes
S No 61/17, 61/18, 61/19, 61/20, 61/51 PT, 61/52, 61/53, 61/54, 61/55, 61/56 and 61/57
S No 61 H No 13
45 mtrs ring Road
18 Mtrs Road
S No 61 H No 14 and 18
MAHARASHTRA
Konkan
Thane
Kalyan
DOMBIVLI
Reti Bunder Road
Mauje Thakurli
421202
20721.47
5
2
3
2971.04

FSI Details

28936.33
33226.67
62163.00

Bank Details

Kotak Mahindra Bank
KKBK0001416

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Swaminarayan City Phase 1A Bhagwan Waman Gaikwad Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Upload Agreement / MoU Copy
6 Upload Agreement / MoU Copy
7 Upload Agreement / MoU Copy
8 Upload Agreement / MoU Copy
9 Upload Agreement / MoU Copy
10 Upload Agreement / MoU Copy
11 Upload Agreement / MoU Copy
12 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Swaminarayan City Phase 1A Bharat Waman Gaikwad Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Upload Agreement / MoU Copy
6 Upload Agreement / MoU Copy
7 Upload Agreement / MoU Copy
8 Upload Agreement / MoU Copy
9 Upload Agreement / MoU Copy
10 Upload Agreement / MoU Copy
11 Upload Agreement / MoU Copy
12 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Swaminarayan City Phase 1A Sharad Waman Gaikwad Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Upload Agreement / MoU Copy
6 Upload Agreement / MoU Copy
7 Upload Agreement / MoU Copy
8 Upload Agreement / MoU Copy
9 Upload Agreement / MoU Copy
10 Upload Agreement / MoU Copy
11 Upload Agreement / MoU Copy
12 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Swaminarayan City Phase 1A Jaidev Waman Gaikwad Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Upload Agreement / MoU Copy
6 Upload Agreement / MoU Copy
7 Upload Agreement / MoU Copy
8 Upload Agreement / MoU Copy
9 Upload Agreement / MoU Copy
10 Upload Agreement / MoU Copy
11 Upload Agreement / MoU Copy
12 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 144 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 Provide Only Drive Way
Water Conservation, Rain water Harvesting : YES 0 NA
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 As Per Provisional Noc Provided by KDMC
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 electrical Meter room will be provided
Aggregate area of recreational Open Space : YES 0 NA
Open Parking : YES 0 NA
Water Supply : YES 0 Provide Up To Site By KDMC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 NA
Storm Water Drains : NO 0 NA
Landscaping & Tree Planting : YES 0 Nos.
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Swaminarayan City Phase 1A ESTONIA 31/12/2028 0 1 4 27 1 0 75
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 14.22 1 1
2 Shop 14.83 1 0
3 Shop 14.95 2 2
4 Shop 14.98 1 0
5 Shop 15.07 1 0
6 Shop 15.1 1 0
7 Shop 15.18 1 1
8 Shop 16.37 2 0
9 Shop 16.56 1 0
10 Shop 16.69 1 0
11 Shop 16.75 1 0
12 Shop 16.96 2 1
13 Shop 17.69 1 0
14 Shop 12.91 1 1
15 Shop 35.45 1 0
16 Shop 35.72 1 0
17 Shop 37.68 1 0
18 Shop 44.69 1 0
19 3BHK 83.27 25 6
20 3BHK 83.57 50 13
21 3BHK 86.78 25 4
22 3BHK 88.46 1 0
23 Shop 13.96 1 0
24 Shop 14.06 1 0
25 Shop 14.17 1 0
26 Shop 19.24 1 0
27 Shop 19.6 1 0
28 Shop 22.17 2 0
29 Shop 28.54 1 0
30 Shop 12.84 2 2
31 Shop 18.01 2 1
32 Shop 18.06 1 0
33 Shop 12.57 5 0
34 Shop 12.64 1 1
35 3BHK 89.32 1 0
36 Shop 23.11 2 1
37 Shop 23.24 1 0
38 Shop 23.32 3 0
39 Shop 23.38 1 0
40 Shop 23.44 1 0
41 Shop 23.51 2 0
42 Shop 24.35 1 1
43 Shop 7.5 2 1
44 Shop 10.8 1 0
45 Shop 11.6 2 1
46 Shop 11.95 1 1
47 Shop 19.83 2 0
48 3BHK 86.87 21 8
49 Shop 16.21 1 1
50 Shop 216.81 1 0
51 Shop 647.48 1 0
52 Shop 1234.51 1 0
53 Shop 19.02 2 1
54 3BHK 89.56 1 0
55 3BHK 89.77 1 0
56 3BHK 90.51 1 0
57 Shop 158.76 1 0
58 Shop 171.2 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 70
5 X number of Slabs of Super Structure 50
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 9
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 3
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 20
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 35.2
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Swaminarayan City Phase 1A AMADORA 31/12/2028 0 1 3 25 1 0 69
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 52.19 90 24
2 1BHK 33.09 86 73
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 58
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 45
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

40
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 3
11 Overall Percentage of Completion of the work done For the entire Building /Wing 54.6
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Swaminarayan City Phase 1A Wing E 31/12/2028 0 0 0 0 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 0 0 0 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 Swaminarayan City Phase 1A Wing F 31/12/2028 0 0 0 0 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 0 0 0 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
5 Swaminarayan City Phase 1A wing G 31/12/2028 0 0 0 0 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 0 0 0 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Vijay Pathak NA Architect
SR Consultants Subramanya Rao NA Engineer
ANAROCK Property Consultants Pvt. Ltd. A51900000108 Real Estate Agent
Pratik N Pandya and co NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
3 Copy of the legal title report
4 Copy of the legal title report
5 Copy of the legal title report
6 Copy of the legal title report
7 Copy of the legal title report
8 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
5 Copy of Layout Approval (in case of layout)
6 Copy of Layout Approval (in case of layout)
7 Copy of Layout Approval (in case of layout)
8 Copy of Layout Approval (in case of layout)
9 Copy of Layout Approval (in case of layout)
10 Copy of Layout Approval (in case of layout)
11 Copy of Layout Approval (in case of layout)
12 Copy of Layout Approval (in case of layout)
13 Copy of Layout Approval (in case of layout)
14 Copy of Layout Approval (in case of layout)
15 Copy of Layout Approval (in case of layout)
16 Copy of Layout Approval (in case of layout)
17 Copy of Layout Approval (in case of layout)
18 Copy of Layout Approval (in case of layout)
19 Copy of Layout Approval (in case of layout)
20 Copy of Layout Approval (in case of layout)
21 Copy of Layout Approval (in case of layout)
22 Copy of Layout Approval (in case of layout)
23 Copy of Layout Approval (in case of layout)
24 Copy of Layout Approval (in case of layout)
25 Copy of Layout Approval (in case of layout)
26 Copy of Layout Approval (in case of layout)
27 Copy of Layout Approval (in case of layout)
28 Copy of Layout Approval (in case of layout)
29 Copy of Layout Approval (in case of layout)
30 Copy of Layout Approval (in case of layout)
31 Copy of Layout Approval (in case of layout)
32 Copy of Layout Approval (in case of layout)
33 Copy of Layout Approval (in case of layout)
34 Copy of Layout Approval (in case of layout)
35 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
11 Building Plan Approval (IOD)
12 Building Plan Approval (IOD)
13 Building Plan Approval (IOD)
14 Building Plan Approval (IOD)
15 Building Plan Approval (IOD)
16 Building Plan Approval (IOD)
17 Building Plan Approval (IOD)
18 Building Plan Approval (IOD)
19 Building Plan Approval (IOD)
20 Building Plan Approval (IOD)
21 Building Plan Approval (IOD)
22 Building Plan Approval (IOD)
23 Building Plan Approval (IOD)
24 Building Plan Approval (IOD)
25 Building Plan Approval (IOD)
26 Building Plan Approval (IOD)
27 Building Plan Approval (IOD)
28 Building Plan Approval (IOD)
29 Building Plan Approval (IOD)
30 Building Plan Approval (IOD)
31 Building Plan Approval (IOD)
32 Building Plan Approval (IOD)
33 Building Plan Approval (IOD)
34 Building Plan Approval (IOD)
35 Building Plan Approval (IOD)
36 Building Plan Approval (IOD)
37 Building Plan Approval (IOD)
38 Building Plan Approval (IOD)
39 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
6 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
4 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement