MahaRERA Application

General Information

Other Than Individual

Organization

GAGAN HORIZON VENTURES
Others
ASSOCIATION OF PERSON
Do you have any Past Experience ?
No

Address Details

2ND FLOOR
WELLSELY COURT
WELLSELY ROAD
CAMP
ABOVE BMW SHOWROOM
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411001

Organization Contact Details

02026133111

Past Experience Details

Other Organization Type Member Information

Name Member Type
PUNE URBAN PROJECTS Partnership
GAGAN HORIZON DEVELOPERS Partnership

Project

GAGAN AKANKSHA PHASE 1
On-Going Project
31/03/2015
31/12/2018
31/12/2019
No
Residential
Yes
GAT NO 524
GAT NO 525
GAT NO 523
PROPOESD 24M DP ROAD
GAT NO 526
MAHARASHTRA
Pune
Pune
Haveli
Koregaon Mul
Koregaon Mul
Koregaon mul
411202
10443.07
5
5
0
0

FSI Details

15464.01
0
15464.01

Bank Details

AXIS BANK
UTIB0000871

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
GAGAN AKANKSHA PHASE 1 PUNE URBAN PROJECTS Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 80 77 75

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 RECHARE PITS PROPOSED
Energy management : YES 50 LED LIGHTS IN PARKING & SOLAR WATER HEATER
Fire Protection And Fire Safety Requirements : YES 100 FF OVERHEAD TANK WITH WET RISER & FIRE ALARAM
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 TRANSFORMAR YARD PROPOSED
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 100 GROUND WATER WITH WTP WITHOUT RO
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 STP PROPOSED
Storm Water Drains : YES 100 RCC PIPES WITH WEEP HOLE CHAMBER
Landscaping & Tree Planting : YES 10 NATIVE SPECIES PROPOSED
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 REUSE FOR GARDENING & FLUSHING
Solid Waste Management And Disposal : YES 0 ORGANIC WASTE COMPOSTER PROPOSED

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 GAGAN AKANKSHA PHASE 1 BUILDING A1 31/12/2018 0 1 0 8 1 0 16
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 34.65 2 0
2 1 BHK 37.96 2 0
3 1.5 BHK 39.14 2 2
4 2 BHK 43.20 2 0
5 2 BHK 45.68 1 0
6 2 BHK 45.90 2 2
7 2 BHK 46.02 1 1
8 2 BHK 46.21 1 0
9 2 BHK 48.47 2 2
10 2 BHK 49.32 2 2
11 2 BHK 49.58 1 0
12 2 BHK 51.11 1 1
13 2 BHK 52.32 1 1
14 2 BHK 52.72 1 0
15 1 BHK 35.80 4 3
16 2 BHK 48.66 1 1
17 2 BHK 50.21 2 2
18 2 BHK 50.78 1 1
19 2 BHK 48.60 5 5
20 2 BHK 45.96 4 4
21 1 BHK 34.19 14 12
22 1 BHK 31.28 2 2
23 1 BHK 31.45 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 GAGAN AKANKSHA PHASE 1 BUILDING A2 31/12/2018 0 1 0 8 1 0 16
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 45.68 1 0
2 2 BHK 45.90 2 2
3 2 BHK 45.96 2 2
4 2 BHK 46.02 1 1
5 2 BHK 48.19 1 1
6 2 BHK 48.47 4 3
7 2 BHK 48.66 1 1
8 2 BHK 49.01 2 2
9 2 BHK 50.21 2 2
10 2 BHK 52.30 1 1
11 2 BHK 54.83 1 1
12 2 BHK 48.60 5 4
13 1 BHK 31.28 2 2
14 1 BHK 31.45 2 2
15 1 BHK 35.80 2 2
16 1 BHK 37.96 2 2
17 1 BHK 38.09 2 2
18 1.5 BHK 41.43 2 2
19 2 BHK 43.20 2 2
20 2 BHK 51.11 1 1
21 2 BHK 52.72 2 2
22 1 BHK 36.48 4 4
23 1 BHK 34.65 2 2
24 1 BHK 34.19 10 10
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 GAGAN AKANKSHA PHASE 1 BUILDING A3 31/12/2018 0 1 0 8 1 0 16
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 34.19 10 10
2 1 BHK 34.65 2 1
3 1 BHK 36.48 4 4
4 1.5 BHK 39.14 2 2
5 2 BHK 43.20 1 0
6 2 BHK 45.72 1 0
7 2 BHK 45.90 2 2
8 2 BHK 46.02 1 1
9 2 BHK 48.19 2 1
10 2 BHK 48.60 3 1
11 2 BHK 48.66 1 1
12 2 BHK 49.01 1 1
13 1 BHK 31.28 2 2
14 1 BHK 31.45 2 2
15 2 BHK 51.11 3 3
16 2 BHK 51.52 1 1
17 2 BHK 52.72 1 0
18 2 BHK 52.75 1 1
19 1 BHK 37.96 2 2
20 1 BHK 38.09 4 4
21 2 BHK 50.21 2 2
22 2 BHK 54.83 2 1
23 2 BHK 48.47 6 6
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 GAGAN AKANKSHA PHASE 1 BUILDING A4 31/12/2018 0 1 0 8 1 0 16
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 43.20 1 1
2 1 BHK 31.28 2 2
3 1 BHK 31.45 2 1
4 1 BHK 34.65 2 1
5 1 BHK 37.96 2 1
6 2 BHK 45.96 3 2
7 2 BHK 46.02 1 1
8 2 BHK 45.72 1 1
9 2 BHK 48.19 2 0
10 2 BHK 48.60 1 1
11 2 BHK 48.66 1 1
12 2 BHK 49.01 1 1
13 2 BHK 51.52 1 1
14 2 BHK 52.72 1 0
15 2 BHK 52.75 1 1
16 2 BHK 54.83 2 2
17 1 BHK 34.19 10 7
18 1 BHK 38.09 4 4
19 1.5 BHK 39.14 2 2
20 2 BHK 48.47 3 2
21 2 BHK 51.11 5 4
22 2 BHK 50.21 2 2
23 1 BHK 36.48 4 2
24 2 BHK 45.90 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
5 GAGAN AKANKSHA PHASE 1 BUILDING A5 31/12/2018 0 1 0 8 1 0 16
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 31.28 2 2
2 1 BHK 31.45 2 2
3 1 BHK 34.65 2 1
4 1 BHK 35.80 2 2
5 2 BHK 48.60 3 1
6 1 BHK 36.48 4 3
7 2 BHK 50.21 1 1
8 2 BHK 46.02 1 1
9 2 BHK 48.19 2 1
10 2 BHK 48.66 1 0
11 2 BHK 49.01 2 1
12 2 BHK 51.11 3 3
13 2 BHK 52.32 1 1
14 2 BHK 52.72 3 3
15 2 BHK 54.83 1 1
16 2 BHK 48.47 4 3
17 1 BHK 37.96 2 1
18 1.5 BHK 41.43 2 2
19 2 BHK 43.20 2 0
20 2 BHK 45.90 2 2
21 2 BHK 45.96 2 2
22 1 BHK 38.09 2 1
23 1 BHK 34.19 10 10
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 90
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
11 Overall Percentage of Completion of the work done For the entire Building /Wing 86.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
PARVEJ JAMADAR & ASSOCIATES NA Architect
HANSAL PARIKH & ASSOCIATES NA Engineer
ARUN ZAMBARE NA Contractor
JAYPRAKASH YADAV NA Contractor
AMIT GORAKHANATH MAGAR NA Contractor
MAHESH KUMAR NA Contractor
VINAY PHADNIS NA Other Professional
MAHESH CHINCHALKAR NA Other Professional
V K JAIN NA Other Professional
MOHAN JADHAV NA Other Professional
Pankaj Kumar Chaurasia A52100000283 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Form 2A
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 CERSAI details
1 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Certificates of Architect (Form 4)
2 Certificates of Architect (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC005000000011128 PALLAVI YOGESH GAVATE View Orders
2 CC005000000010933 Jyoti Vidyadhar Pinjarkar View Orders
3 CC005000000010933 Pallavi Rajesh Band View Orders
4 CC005000000010933 Jyoti Vidyadhar Pinjarkar View Orders
5 CC005000000010933 Pallavi Rajesh Band View Orders
6 CC005000000022107 Yojana Vinod Deokar View Orders
7 CC005000000022028 Sushant Suhas Gaikwad and Manasi Sushant Gaikwad View Orders
8 CC005000000022028 Krishna Sakharam Dhanorkar View Orders
9 CC005000000022028 Rajesh Ulhas Zirpe View Orders
10 CC005000000022134 Sandesh Janardhan Kale View Orders
11 CC005000000022106 VINOD PRAKASH DEOKAR View Orders
12 CC005000000022077 PRAKASH PATEL View Orders
13 CC005000000022134 Sandesh Janardhan Kale View Orders
14 CC005000000022760 hemant Martandrao kulkarni and 1 other View Orders
15 CC005000000022760 Mrs.Rajashree hemant kulkarni View Orders
16 CC005000000022960 Ketan Dilip Shah View Orders
17 CC005000000023097 JAYASHRI RAJANIKANT SIKACHI View Orders
18 CC005000000022990 NITIN SADASHIV TEKAWADE & SEEMA NITIN TEKAWADE View Orders
19 CC005000000010933 Jyoti Vidyadhar Pinjarkar View Orders
20 CC005000000010933 Pallavi Rajesh Band View Orders
21 CC005000000000091 SUNIL NATHURAM UTTEKAR View Orders
22 CC005000000011128 PALLAVI YOGESH GAVATE View Orders
23 CC005000000022028 Sushant Suhas Gaikwad and Manasi Sushant Gaikwad View Orders
24 CC005000000022028 Krishna Sakharam Dhanorkar View Orders
25 CC005000000022028 Rajesh Ulhas Zirpe View Orders
26 CC005000000023407 Mrs.Kalpana Ankush Pomane View Orders
27 CC005000000033591 Ajinkya Vijay Ghare View Orders
28 CC005000000023215 Benjamin Samul Gadkar and Saurabh Benjamin Gadkar View Orders
29 CC005000000023097 JAYASHRI RAJANIKANT SIKACHI View Orders
30 CC005000000043662 NASIR IBRAHIM PENDHARI View Orders