MahaRERA Application

General Information

Other Than Individual

Organization

Newone Constructions Private Limited
Company
NA
Do you have any Past Experience ?
No

Address Details

7th Floor
S-14, Solitaire Corporate Park
Andheri Ghatkopar Link Road,
Andheri East
Opp Miradoor Hotel
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400093

Organization Contact Details

02261296900

Past Experience Details

Member Information

Member Name Designation Photo
Sarjan Pankaj Shah Director View Photo
Abhishek Jain Authorized Signatory View Photo

Project

Satellite Elegance
New Project
30/12/2024
Yes
Residential
No
620A / 1A / 4A / 2/ 1 /8 of Village Malad East
CTS No 661
CTS No 620A 6
CTS No 620 A 6
13 mt wide Pankaj Shah Marg
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
Pankaj Shah Marg, Opp Film City Road
Goregoan East
400063
4621
2
2
0
369

FSI Details

16510
1953
18463.00

Bank Details

HDFC BANK LIMITED
HDFC0000240

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 289 183 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 As per MCGM requirements
Energy management : YES 0 Power Supply thru Utility Provider
Fire Protection And Fire Safety Requirements : YES 0 As per CFO & NBC Norms
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Meter Room & Sub-station as per utility provider
Children Play Area : YES 0 As per approvals and proposed design
Entrance Foyer : YES 0 As per approvals and proposed design
Gymnasium : YES 0 As per proposed design
Landscape Garden : YES 0 As per proposed design
Multipurpose Hall : YES 0 As per proposed design
Security Cabin : YES 0 As per proposed design
Society Office : YES 0 As per proposed design
Steam and Sauna : YES 0 As per proposed design
Swimming Pool : YES 0 As per proposed design
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 As per statutory requirements
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 As per statutory requirements
Storm Water Drains : YES 0 As per statutory requirements
Landscaping & Tree Planting : YES 0 As per proposed design
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 As per statutory requirements
Solid Waste Management And Disposal : YES 0 As per statutory requirements

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Satellite Elegance Elegance Wing A 31/12/2023 1 1 10 34 1 0 146
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 39.67 55 49
2 2BHK 58.99 87 74
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 35
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 07
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 43
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 48.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Satellite Elegance Elegance Wing B 31/12/2023 1 1 10 34 1 0 143
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 47.38 1 0
2 2BHK 58.99 23 11
3 2BHK 65.96 111 79
4 3BHK 82.68 1 1
5 3BHK 83.43 3 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 73
5 X number of Slabs of Super Structure 35
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 7
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 43
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 45.8

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Sandeep Shikre & Associates NA Architect
Struct Bombay Consultant NA Other Professional
Dnyanesh G.Bhave NA Other Professional
Anil J Saboo Associates NA Chartered Accountant
V C Shah & Co NA Chartered Accountant
Alpesh Gandhi NA Engineer

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Satellite Elegance Bombay High Court PIL Lodging No 63 /2018 Civil No Writ Petition NA 2018 Not admitted No adverse orders passed
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement