MahaRERA Application

General Information

Other Than Individual

Organization

RajHeramb Properties
Others
Proprietorship
Do you have any Past Experience ?
Yes

Address Details

Row House No - 3
Raj Vimal Terraces
Plot No - 28
Ram Nagar Colony
NDA Road,Bavdhan
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411021

Organization Contact Details

02066521010

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Regalia ResidencyResidentialNA6089.96Plot No 1 14 15 16 out of Survey No 276 277 278 275 Bavdhan BK Tal Mulshi Dist Punesurvey no 276 277 278 27541192014-08-202015-06-23
2Venkatesh Imperia ResidentialNA6677.65Survey No 14 part 4 Punawale Tal Mulshi Dist Punesurvey no 14 part 4 Punawale tal mulshi Dist Pune21282015-12-312016-06-17

Other Organization Type Member Information

Name Member Type
Pravin Vishwanath Patil Others

Project

Venkatesh Imperia Phase I
On-Going Project
31/05/2017
30/06/2018
30/06/2019
No
Residential
No
Survey no 14 Part 4 Tal Mulshi Dist Pune
9 meter road and survey no 14 5
survey no 14 3
9 meter road and Survey no 13
18 meter road
MAHARASHTRA
Pune
Pune
Mulshi
Punawale
Pandhare Wasti
PCMC
411033
604.23
2
2
0
960.93

FSI Details

760.57
0
760.57

Bank Details

INDUSIND BANK
INDB0000006

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 2 2 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Completed
Water Conservation, Rain water Harvesting : YES 100 Completed
Energy management : YES 100 Completed
Fire Protection And Fire Safety Requirements : YES 100 Completed
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Completed
Aggregate area of recreational Open Space : YES 100 Completed
Open Parking : YES 100 Completed
Water Supply : YES 100 Completed
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Completed
Storm Water Drains : YES 100 Completed
Landscaping & Tree Planting : YES 100 Completed
Street Lighting : YES 100 Completed
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 Completed
Solid Waste Management And Disposal : YES 100 Completed

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Venkatesh Imperia Phase I B 30/06/2018 0 1 0 1 1 5 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 53.43 1 1
2 2 BHK 52.89 1 1
3 3 BHK 74.76 1 1
4 2 BHK 57.66 1 1
5 2 BHK 52.91 1 1
6 2 BHK 52.51 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Venkatesh Imperia Phase I C 30/06/2018 0 1 0 1 1 5 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 61.58 1 1
2 2 BHK 52.60 1 1
3 2 BHK 53.79 1 1
4 3 BHK 66.34 1 1
5 2 BHK 55.72 1 1
6 2 BHK 53.20 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Gem Associates Mr Girish Gupte NA Architect
Spectrum Consultants Mr Parag Chopda NA Engineer
Nikunj Investments and Home Solutions A52100002995 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
2 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement