MahaRERA Application

General Information

Other Than Individual

Organization

MEERA ENTERPRISES
Partnership
NA
Do you have any Past Experience ?
No

Address Details

SHOP NO 2
CHINTAMANI BUNGALOW
SECTOR 19-20 BELAPUR VILLAGE
CBD BELAPUR NAVI MUMBAI
OLD BUS STAND BELAPUR VILLAGE
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400615

Organization Contact Details

02221638500

Past Experience Details

Member Information

Member Name Designation Photo
VRUNDAVAN PANDURANG WANI Authorized Signatory View Photo
PANDHARINATH NAGA PATIL Partner View Photo
VRUNDAVAN PANDURANG WANI Partner View Photo

Project

PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT
On-Going Project
31/12/2020
30/03/2022
31/12/2025
Yes
Others
No
PLOT BEARING CTS NO 582A AND 582B AND 587 PART MULUND EAST
BY VB PHADKE ROAD
BY PROPERTY BEARING CTS NO 587
BY PROPERTY BEARING CTS NO 586
BY GV SCHEME ROAD NO 2
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
400081
2192.68
2
2
0
248.76

FSI Details

5340.28
1585.42
6925.70

Bank Details

GP PARSIK BANK
PJSB0000041

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 61 0 65

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 ONLY RAIN WATER HARVESTING
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 AS PER CFO NOC
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 AS PER APPROVAL
Aggregate area of recreational Open Space : YES 100 AS PER PLAN
Open Parking : YES 60 AS PER PLAN
Water Supply : YES 100 WITHIN PLOT ONLY
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 WITHIN PLOT ONLY
Storm Water Drains : YES 100 WITHIN PLOT ONLY
Landscaping & Tree Planting : YES 100 ONLY TREE PLANTING
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT PATIL PRASAD AND SHANTI SADAN BUILDING PHASE 1 WING A 20/03/2023 1 1 0 10 1 2 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 52.95 9 9
2 SHOP 1 23.13 1 1
3 SHOP 2 23.16 1 1
4 SHOP 3 9.15 1 1
5 OFFICE 6 34.85 2 2
6 SHOP 4 16.27 1 1
7 SHOP 5 29.32 1 1
8 SHOP 6 57.47 1 1
9 OFFICE 8 91.98 1 1
10 1BHK 30.79 2 2
11 OFFICE 7 27.82 1 1
12 1BHK 34.83 7 7
13 1BHK 35.14 9 9
14 2BHK 44.23 3 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT PATIL PRASAD AND SHANTI SADAN PHASE 2 WING B 20/03/2023 1 1 0 17 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 75.85 3 3
2 SHOP 7 22.34 1 1
3 SHOP 8 79.20 1 1
4 SHOP 9 33.04 1 1
5 SHOP 10 15.25 1 1
6 SHOP 11 15.97 1 1
7 SHOP 12 21.42 1 1
8 OFFICE 5 64.37 1 1
9 OFFICE 4 86.77 1 1
10 OFFICE 1 AND 2 AND 3 133.60 1 1
11 SHOP 13 17.91 1 1
12 2BHK 62.57 16 14
13 3BHK 77.43 13 10
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SHARDA CONSTRUCTION NA Contractor
VINAYAK CHOPDEKAR AND ASSOCIATES NA Engineer
ASHISH BHATT NA Architect
RAMESH TAMBAT NA Architect
Y S Muzumdar NA Chartered Accountant

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT BOMBAY SMALL CAUSES COURT 25 Civil No Other CONTEMPT PETITION 2015 CROSS EXAMINATION OF EVIDENCE
NA
PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT BOMBAY SMALL CAUSES COURT 114 Civil Yes Appeal NA 2016 DISPOSED OF

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
5 Commencement Certificates / NA Order for plotted development
6 Commencement Certificates / NA Order for plotted development
7 Commencement Certificates / NA Order for plotted development
8 Commencement Certificates / NA Order for plotted development
9 Commencement Certificates / NA Order for plotted development
10 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
16 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
17 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
18 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
17 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
18 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
19 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
20 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
21 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
4 Proforma of Allotment letter
5 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement