MahaRERA Application

General Information

Other Than Individual

Organization

M.S.PATIL AND ASSOCIATES
Partnership
NA
Do you have any Past Experience ?
No

Address Details

FLAT NO.2 BLDG. NO.50-51
SAMAYADNYA CO-OP. HSG. SOC.
LOKMANYA NAGAR, POST OFFICE LANE
SADASHIV PETH
OPP. S.P.M. ENGLISH MEDIUM SCHOOL
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411030

Organization Contact Details

02024339205

Past Experience Details

Member Information

Member Name Designation Photo
MADHUKAR SHANKAR PATIL Partner View Photo
PARIMAL MADHUKAR PATIL Partner View Photo
RAHUL MADHUKAR PATIL Authorized Signatory View Photo
ANUJ RAMESH SANGHVI Authorized Signatory View Photo
TANUJ RAMESH SANGHVI Partner View Photo

Project

GANADHISH SANKUL B WING
New Project
30/06/2023
No
Residential
No
SURVEY NO. 7A/3/4/5/1, HINGANE KHURD OFF SINHAGAD ROAD PUNE 411051
AMENITY SPACE
SURVEY NO 8 AND SURVEY NO 7A PART
ROAD AND SURVEY NO 7A PART
SURVEY NO 7 PART
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
OFF NARAYANRAO KONDIBA JAGATAP PATH
SAI NAGAR HINGNE KH.
411051
3508.81
1
1
0
471.26

FSI Details

2741.04
0
2741.04

Bank Details

IDBI BANK LTD
IBKL0000490

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
GANADHISH SANKUL B WING M.S.Patil and Associates Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 39 39 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 completed
Water Conservation, Rain water Harvesting : YES 100 completed
Energy management : YES 100 completed
Fire Protection And Fire Safety Requirements : YES 100 completed
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 completed
Intercom security system : YES 100 completed
UGWT : YES 100 completed
Watchmen cabin and entrance gate : YES 100 completed
Aggregate area of recreational Open Space : YES 100 Children's Play Area
Open Parking : YES 100 completed
Water Supply : YES 100 completed
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Common septic Tank For all Buildings
Storm Water Drains : YES 100 completed
Landscaping & Tree Planting : YES 100 completed
Street Lighting : YES 100 completed
Community Buildings : YES 100 completed
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : YES 100 completed

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 GANADHISH SANKUL B WING Ganadhish Sankul B wing 30/06/2022 0 1 0 9 1 5 39
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 67.35 9 9
2 2BHK 73.74 1 1
3 3BHK 85.13 1 1
4 1BHK 48.72 5 5
5 2BHK 65.03 8 8
6 3BHK 89.93 5 2
7 2BHK 65.58 3 3
8 1BHK 44.89 3 3
9 3BHK 82.29 4 4
10 2BHK 70.57 4 4
11 2BHK 74 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Dilip G Kale NA Architect
Nilesh P Kolhe NA Engineer
Nitin B Inamdar NA Chartered Accountant
Rajesh C Ratkalkar NA Other Professional
Pranjali Construction NA Contractor
Pawar Enterprises NA Contractor
Kshitij Tikhe NA Other Professional

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
3 Copy of the legal title report
4 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
11 Building Plan Approval (IOD)
12 Building Plan Approval (IOD)
13 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
2 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement