MahaRERA Application

General Information

Other Than Individual

Organization

VVR INFRACON LLP
Others
LIMITED LIABILITIES PARTNERSHIP
Do you have any Past Experience ?
Yes

Address Details

312 AHURA CENTRE
93 EAST
82 MAHAKALI CAVES ROAD
COMMERCIAL
NEAR MAROL BUS DEPO
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400093

Organization Contact Details

02228202820
WWW.VIJAYLAXMI.IN

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1VIJAYLAXMI BLISSResidentialNA1881VIJAYLAXMI BLISS CTS NO 25 PLOT NO 5 JVLR ROAD JOGESHWARI EAST MUMBAI 400093PLOT NO 5 CTS NO 252822017-12-312017-12-31
2SWAPNAPOORTIOthersCOMMERCIAL & RESIDENTIAL 2300CTS NO 145 MAJAS VILLAGGE JOGESHWARI EAST MUMBAI 400060CTS NO 145 MAJAS VILLAGE 22002019-12-312019-12-31

Other Organization Type Member Information

Name Member Type
VIRENDRA BADRINATH TIWARI Individual
RAGHU MUDDU POOJARI Individual
KETAN NAVINCHANDRA PARIKH Individual
RAKESH RAMKRIPAL MISHRA Individual
MANGESH VIRENDRA TIWARI Individual
HARVINDER KAUR VIG Individual
PRASHANT KAWAR Individual
VIJAYLAXMI DEVELOPERS & SEC PVT LTD Company

Project

93 EAST
New Project
30/06/2025
No
Commercial
Yes
CTS NO 90A PT 90 B AND 89A 3 PT VILLAGE MULGAON ANDHERI EAST MUMBAI 400093
WD DP ROAD
MAHAKALI CAVES ROAD
WD DP ROAD
INGA COMPLEX
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
82 MAHAKALI CAVES ROAD
COMMERCIAL
400093
992.80
1
1
0
0

FSI Details

986.65
4370.49
5357.14

Bank Details

BHARAT CO OPP BANK LTD
BCBM0000069

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
93 EAST VVR INFRACON LLP Others Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) TOWER PARK 0 0
Covered Parking ( In Numbers) 114 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 NA
Water Conservation, Rain water Harvesting : YES 0 NA
Energy management : YES 0 NA
Fire Protection And Fire Safety Requirements : YES 50 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 NA
Aggregate area of recreational Open Space : YES 0 NA
Open Parking : NO 0 NA
Water Supply : YES 50 NA
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 NA
Storm Water Drains : YES 0 NA
Landscaping & Tree Planting : NO 0 NA
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 93 EAST VVR INFRACON LLP 31/12/2024 1 1 0 14 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Office space 4789.15 111 21
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
11 Overall Percentage of Completion of the work done For the entire Building /Wing 69

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
AKAR CONSTRUCTION COMPANY NA Contractor
UDAY V DHAWAN NA Architect
ARHAM CONSTROTECH PVT LIMITED NA Engineer
SHAH & TAPARIA NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
3 Copy of the legal title report
1 Details of encumbrances
2 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 CERSAI details
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement