Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
1 |
Olympeo Neo City
|
A1
|
|
0
|
1
|
0
|
5
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
NIVO 259 |
22.02 |
8 |
0 |
2 |
NIVO 265 |
22.20 |
30 |
0 |
3 |
VIVO 168 |
15.61 |
10 |
0 |
4 |
VIVO 222 |
18.58 |
2 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
2 |
Olympeo Neo City
|
A2
|
30/12/2022
|
0
|
1
|
0
|
5
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1RK |
18.58 |
2 |
0 |
2 |
1RK |
15.6 |
10 |
4 |
3 |
1BHK |
22.01 |
8 |
3 |
4 |
1BHK |
22.2 |
30 |
15 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
3 |
Olympeo Neo City
|
A3
|
30/12/2022
|
0
|
1
|
0
|
5
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1RK |
15.6 |
10 |
4 |
2 |
1RK |
18.58 |
2 |
1 |
3 |
1BHK |
22.01 |
8 |
3 |
4 |
1BHK |
22.2 |
30 |
24 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
40
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
34
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
4 |
Olympeo Neo City
|
A4
|
30/12/2022
|
0
|
1
|
0
|
5
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1RK |
15.61 |
10 |
10 |
2 |
1BHK |
22.01 |
8 |
6 |
3 |
1RK |
18.58 |
2 |
1 |
4 |
1BHK |
22.2 |
30 |
27 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
75
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
77.5
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
5 |
Olympeo Neo City
|
A5
|
30/12/2022
|
0
|
1
|
0
|
5
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1RK |
15.61 |
10 |
8 |
2 |
1RK |
18.58 |
2 |
2 |
3 |
1BHK |
22.01 |
8 |
8 |
4 |
1BHK |
22.2 |
30 |
29 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
6 |
Olympeo Neo City
|
A6
|
30/12/2022
|
0
|
1
|
0
|
5
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1RK |
18.58 |
2 |
0 |
2 |
1BHK |
22.02 |
8 |
8 |
3 |
1RK |
15.61 |
10 |
2 |
4 |
1BHK |
22.2 |
30 |
26 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
25
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
22.5
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
7 |
Olympeo Neo City
|
A7
|
30/12/2022
|
0
|
1
|
0
|
5
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
22.02 |
8 |
8 |
2 |
1BHK |
22.2 |
30 |
18 |
3 |
1RK |
15.61 |
10 |
0 |
4 |
1RK |
18.58 |
2 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
45
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
24.5
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
8 |
Olympeo Neo City
|
A8
|
30/12/2022
|
0
|
1
|
0
|
5
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1RK |
18.58 |
2 |
2 |
2 |
1BHK |
22.02 |
8 |
8 |
3 |
1RK |
15.61 |
10 |
7 |
4 |
1BHK |
22.2 |
30 |
30 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
9 |
Olympeo Neo City
|
B1
|
|
0
|
1
|
0
|
5
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
VIVO 186 |
14.86 |
30 |
0 |
2 |
VIVO 168 |
15.61 |
25 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
10 |
Olympeo Neo City
|
B2
|
|
0
|
1
|
0
|
5
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
VIVO 186 |
14.86 |
30 |
0 |
2 |
VIVO 168 |
15.61 |
25 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
11 |
Olympeo Neo City
|
B3
|
|
0
|
1
|
0
|
5
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
VIVO 168 |
15.61 |
25 |
0 |
2 |
VIVO 186 |
14.86 |
30 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
12 |
Olympeo Neo City
|
B4
|
|
0
|
1
|
0
|
5
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
VIVO 186 |
14.86 |
30 |
0 |
2 |
VIVO 168 |
15.61 |
25 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
13 |
Olympeo Neo City
|
B5
|
|
0
|
1
|
0
|
5
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
VIVO 186 |
14.86 |
30 |
0 |
2 |
VIVO 168 |
15.61 |
25 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
14 |
Olympeo Neo City
|
B6
|
|
0
|
1
|
0
|
5
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
VIVO 186 |
14.86 |
30 |
0 |
2 |
VIVO 168 |
15.61 |
25 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
15 |
Olympeo Neo City
|
B7
|
30/12/2022
|
0
|
1
|
0
|
5
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1RK |
14.86 |
30 |
17 |
2 |
1RK |
15.61 |
25 |
20 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
20
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
16 |
Olympeo Neo City
|
Commercial Plaza
|
30/12/2022
|
0
|
1
|
0
|
2
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
Shop Type B |
12.6 |
1 |
0 |
2 |
Shop Type C |
15.24 |
2 |
0 |
3 |
Shop Type E |
17.55 |
1 |
0 |
4 |
Shop Type D |
8.1 |
1 |
0 |
5 |
Shop Type D |
9 |
10 |
6 |
6 |
Shop Type A |
13.05 |
12 |
6 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
50
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
35
|
|