MahaRERA Application

General Information

Other Than Individual

Organization

VIHANG ENTERPRISES
Partnership
NA
Do you have any Past Experience ?
No

Address Details

12TH FLOOR
DEV CORPORA
EASTERN EXPRESS HIGHWAY
KHOPAT
OPP. CADBURY COMPANY
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
400601

Organization Contact Details

02221729000

Past Experience Details

Member Information

Member Name Designation Photo
VIHANG PRATAP SARNAIK Partner View Photo
YOGESH KISHORE CHANDEGALA Partner View Photo
PURVESH PRATAP SARNAIK Partner View Photo
YOGESH KISHORE CHANDEGALA Authorized Signatory View Photo

Project

VIHANGS VERMONT
On-Going Project
31/12/2020
30/12/2022
Yes
Residential
No
SURVEY NO.100 HISSA NO.25, SURVEY NO.100 HISSA NO.27, SURVEY NO.100 HISSA NO.28
SURVEY NO 100 HISSA 24
SURVEY NO 100 HISSA 29 31 32
SURVEY NO 100 HISSA 26
SURVEY NO 92 HISSA 6
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
G.B.ROAD
BHAYNDERPADA
400615
8250
2
2
0
763.50

FSI Details

8357.30
2077.43
10434.73

Bank Details

HDFC BANK
HDFC0000488

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 193 152 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 Entry from 20 Mts. Wide D.P. Road
Water Conservation, Rain water Harvesting : YES 100 Provided
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 As Per CFO Norms
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 As per Approved Plan
Aggregate area of recreational Open Space : YES 100 As per Approved Plan
Open Parking : YES 100 28 PARKING
Water Supply : YES 100 By TMC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 As per Approved Plan
Storm Water Drains : YES 100 As per Approved Plan
Landscaping & Tree Planting : YES 100 As per Approved Plan
Street Lighting : YES 100 Internal Lights for Elevated RG and Internal areas
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 Provided
Solid Waste Management And Disposal : YES 100 Provision of OWC

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 VIHANGS VERMONT BLDG NO 1 BOLTON 30/12/2022 0 1 1 23 1 14 92
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 34.93 12 12
2 2BHK 58.92 15 15
3 SHOP NO 6 16.62 1 1
4 SHOP NO 7 24.86 1 1
5 SHOP NO 8 23.56 1 1
6 SHOP NO 1 20.74 1 1
7 SHOP NO 2 37.13 1 1
8 SHOP NO 3 17.08 1 1
9 2BHK 62.82 7 7
10 2BHK 52.67 7 7
11 2BHK 48.81 15 15
12 1BHK 37.25 18 18
13 2BHK 52.07 22 22
14 SHOP NO 4 10.12 1 1
15 SHOP NO 5 18.18 1 1
16 1BHK 34.93 10 0
17 3BHK 76.81 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 1
4 Stilt Floor 100
5 X number of Slabs of Super Structure 23
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 82.4
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 VIHANGS VERMONT BLDG NO 2 STARK 30/12/2022 0 1 1 23 1 13 91
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 23.56 1 1
2 Shop 17.08 1 1
3 Shop 16.62 1 1
4 Shop 18.18 1 1
5 Shop 10.12 1 1
6 Shop 24.86 1 1
7 2BHK 58.92 15 15
8 2BHK 62.82 7 7
9 2BHK 52.67 7 7
10 2BHK 52.07 22 22
11 3BHK 76.81 1 1
12 Shop 37.13 1 1
13 Shop 20.74 1 1
14 1BHK 34.93 10 10
15 1BHK 34.93 12 12
16 1BHK 37.25 18 18
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 1
4 Stilt Floor 100
5 X number of Slabs of Super Structure 23
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 72.4

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
TEN FOLDS NA Architect
SHREEJI CONSTRUCTION CO NA Contractor
ENGINEERING CREATIONS PUBLIC HEALTH CONSULTANCY PVT LTD NA Other Professional
SHOAIB NAZIR KHAN A51700000152 Real Estate Agent
JM Financial Products Limited A51900000277 Real Estate Agent
Abdul Rahim Rehmatullah Shaikh A51700002352 Real Estate Agent
Mohhamed Affan Ansari A51900003336 Real Estate Agent
MAHESH BABAN KHANDALE A51900004377 Real Estate Agent
Sunil Subhash Shelke A51700000840 Real Estate Agent
360 REALTORS LLP A51900000246 Real Estate Agent
PUNIT ARVIND SINGH A51700002776 Real Estate Agent
MALACHI ANGELO CARDOZO A51700002753 Real Estate Agent
MAHAVIR PRASAD TOSHNIWAL A51700003016 Real Estate Agent
SQUARE YARDS CONSULTING PRIVATE LIMITED A51800000454 Real Estate Agent
Joseph Chamling A51700002806 Real Estate Agent
ARCH KAUSTUBH J SATAM NA Architect
RAAHAT IRFAN TAMBOLI A51700007771 Real Estate Agent
ELARA MARKETING SERVICES PRIVATE LIMITED A51700000030 Real Estate Agent
REHAN BEDRE A51700005002 Real Estate Agent
4G INFO SOURCE LLP A51700001533 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
VIHANGS VERMONT THANE CIVIL JUDGE SENIOR DIVISION 636 Civil No Suit NA 2018 Issues
NA
VIHANGS VERMONT CJSD THANE 524 Civil No Suit NA 2007 Exhibit Hearing
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
5 Commencement Certificates / NA Order for plotted development
6 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
4 Other
5 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement