MahaRERA Application

General Information

Other Than Individual

Organization

CAPITAL ASSOCIATES
Partnership
NA
Do you have any Past Experience ?
No

Address Details

OFFICE NO.11
TULSI HEIGHTS
PLOT NO.25
SECTOR-22
KAMOTHE
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
410209

Organization Contact Details

02227431889

Past Experience Details

Member Information

Member Name Designation Photo
ASHWIN BABUBHAI PRAJAPATI Authorized Signatory View Photo
BECHARLAL KHETSHI PATEL Partner View Photo
ABRAHAM DAVID Partner View Photo
HITESH RAMJI RAVARIYA Partner View Photo

Project

OM IMPERIA
On-Going Project
26/12/2018
26/12/2018
No
Residential
Yes
PLOT NO. 22
PLOT NO22A
15 MTR WIDE ROAD
PLOT NO20 21
20 MTR WIDE ROAD
MAHARASHTRA
Konkan
Raigarh
Panvel
Karanjade
410206
899.76
1
1
0
0

FSI Details

1349.64
0
1349.64

Bank Details

AXIS BANK LTD
UTIB0000885

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
OM IMPERIA ABRAHAM DAVID Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 17 0 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 IN LATER SCOPE OF WORK
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 IN LATER SCOPE OF WORK
Electrical Meter Room, Sub-Station, Receiving Station : YES 50 IN LATER SCOPE OF WORK
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 IN LATER SCOPE OF WORK
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 IN LATER SCOPE OF WORK
Storm Water Drains : YES 0 IN LATER SCOPE OF WORK
Landscaping & Tree Planting : NO 0 NA
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 OM IMPERIA OM IMPERIA 26/12/2018 0 1 0 8 1 0 17
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 22.33 1 1
2 1BHK 19.62 1 1
3 2BHK 42.5 6 6
4 1BHK 32.30 5 5
5 1BHK 25.71 1 1
6 1BHK 23.86 12 12
7 1BHK 22.16 10 10
8 1BHK 20.20 1 1
9 SHOP 11.14 1 1
10 SHOP 13.48 1 1
11 SHOP 17.35 1 1
12 SHOP 13.80 1 1
13 1BHK 23.93 2 2
14 SHOP 15.61 2 2
15 SHOP 17.36 1 1
16 SHOP 19.43 1 1
17 SHOP 20.80 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

75
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 72.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SOYUZ TOFIQUE TALIB NA Architect
JAYPAL DAYALU MANDAVI NA Contractor
BALU KUNDLIK RATHOD NA Contractor
SAMARTH AGARWAL NA Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
2 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement