MahaRERA Application

General Information

Other Than Individual

Organization

VAVYA ENTERPRISES
Partnership
NA
Do you have any Past Experience ?
No

Address Details

SHOP NO. 2
DREAM PALACE
NR THUNGA HOSPITAL
MIRA ROAD EAST
N H HIGH SCHOOL RD
MAHARASHTRA
Konkan
Thane
Thane
Mira-Bhayandar (M Corp.)
401107

Organization Contact Details

09892416539

Past Experience Details

Member Information

Member Name Designation Photo
CHANDRAKANT MOHYANNHAI PATEL Partner View Photo
CHANDRAKANT MOHANBHAI PATEL Authorized Signatory View Photo
HAMID MAJID Partner View Photo

Project

SHREE RAM HEIGHTS
New Project
30/12/2026
No
Residential
No
87/2B, 2C
S-NO-486
S-NO-487-11
S-NO-487-2PT
S-NO-492
MAHARASHTRA
Konkan
Thane
Thane
Mira-Bhayandar (M Corp.)
N H HIGHT SCHOOL RD
MIRA ROAD EAST
401107
2490
2
2
0
221

FSI Details

2268.74
2736
5004.74

Bank Details

THE JAMMU AND KASHMIR BANK
JAKA0MIRARD

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 NIL
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 NIL
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 NIL
Electrical Meter Room, Sub-Station, Receiving Station A WING : YES 0 NA
Fire Protection And Fire Safety Requirements A WING : YES 0 NA
Internal Roads & Footpaths A WING : YES 0 NA
Sewerage (Chamber, Lines, Septic Tank , STP) AWING : YES 0 NA
Water Conservation, Rain water Harvesting A WING : YES 0 NA
Water Supply A WING : YES 0 NA
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 100 WATER CONNECTION WILL BE GIVEN BY MBMC AFTER OC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 NIL
Storm Water Drains : YES 100 NIL
Landscaping & Tree Planting : YES 0 NIL
Street Lighting : YES 100 NIL
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 SHREE RAM HEIGHTS SHREE RAM HEIGHTS-B WING 27/11/2019 0 1 0 11 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 35.47 11 11
2 1BHK 37.19 10 10
3 1BHK 37.19 10 10
4 1BHK 39.64 11 11
5 2BHK 60.46 10 10
6 2BHK 61.18 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 SHREE RAM HEIGHTS SHREE RAM HEIGHT- A WING 31/12/2025 0 1 0 12 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 63.55 1 0
2 1BHK 40.79 12 0
3 1BHK 40.82 10 0
4 2BHK 59.43 11 0
5 1BHK 61.13 11 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 8
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 30.8

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
RAKESH MISHRA & ASSOCIATES NA Chartered Accountant
ADARSH CONSULTANTS NA Engineer
TEJS CONSULTANTS NA Architect
AONE ELETRICAL NA Contractor
MAHESH PATEL NA Contractor

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement