MahaRERA Application

General Information

Other Than Individual

Organization

KABRA AND ASSOCIATES
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

1001, 10TH FLOOR,
KAMLA HUB
N.S. ROAD NO.1, OFF GULMOHAR ROAD
JVPD SCHEME, VILE PARLE (WEST)
NEXT TO AROMAS CAFE
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400049

Organization Contact Details

02226210202
www.kabragroup.net

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1NEW VINAYResidentialNA2434.80Sunder Nagar Near Mumbai University Kalina Santacruz East Mumbai 984918/298/131702015-05-312015-12-31
2KABRA ARGENTUM - UNNAT NAGAR - 43/44ResidentialNA1709Plot No. 43 - 44 Unnat Nagar II Off S V Road Goregaon West Mumbai - 62318, 318 / 1 to 161792015-09-302016-01-20
3RAGESHREEOthersResidential cum Commercial2233.40Sodawala Lane Opp. Pandya Hospital Borivali West Mumbai - 92509 509 1/41692016-06-302017-05-09
4ALYA GARNETOthersResidential cum Commercial13935Brahmand Azad Nagar Behind Universal School Brahmand Thane West - 40060787/2/1 2/2 2/3 4A 4B 4C 5A 5B 5C 122/17 122/1811072014-03-292012-12-12
5NATRAJOthersResidential cum Commercial2566Corner of Prem Nagar & Sodawala Lane Opp. Prabhodhan Thackarey Hall Borivali West Mumbai 922433 243 1/10 1161932017-06-302017-05-30
6NANDANWADIResidentialNA501.67Plot No.257 Jawahar Nagar Next to Mount Mary High School Goregaon West Mumbai - 62505 505/ 1 and 21212014-06-302014-05-09
7CHRISTINAResidentialNA1548Shree Nagar Estate Vidyaniketan Marg Off M G Road Goregaon West Mumbai - 62276-B1512015-05-012014-09-16
8VIHANGResidentialNA527Building No. 16 Siddharth Nagar IV Opp. Vivek College Goregaon West Mumbai - 62348 part 348/57 to 611412015-03-312017-06-10

Member Information

Member Name Designation Photo
GAUTAM JAIGOPAL KABRA Authorized Signatory View Photo
DILIP SATYANARAYAN SONI Authorized Signatory View Photo
SHYAMSUNDER ASHARAM KABRA Partner View Photo
RAJESH ASHARAM KABRA Partner View Photo
GAUTAM JAIGOPAL KABRA Partner View Photo
MANISH KAMALKISHORE KABRA Partner View Photo
ABHISHEK KAMALKISHORE KABRA Partner View Photo
GOURAV JAIGOPAL KABRA Partner View Photo
VINIL SHYAMSUNDER KABRA Partner View Photo

Project

KABRA CENTROID A Redevelopment of GOP CHSL
On-Going Project
31/12/2020
30/12/2021
No
Residential
No
6924-A
Plot Bearing CTS No 6933 - 6988 and 6946
Plot Bearing CTS No 6929 and 6930
Plot Bearing CTS No 6923
Plot Bearing CTS No 5579
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400098
3998.90
1
1
0
544.84

FSI Details

8866
4921
13787.00

Bank Details

Kotak Mahindra Bank Ltd
KKBK0000643

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) NONE NA 0
Covered Parking ( In Numbers) 245 132 98

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 Shall be done prior to OC
Energy management : YES 0 Shall be done prior to OC
Fire Protection And Fire Safety Requirements : YES 100 WORK IN PROGRESS
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 WORK IN PROGRESS
Compliance of Green Building Norms High Performance Glass Windows Electric Charge Station for Cars S : YES 80 Shall be done prior to OC
Health Club Gymnasium : YES 100 Work completion
Landscape and Horticulture Work at Terrace Level : YES 100 Shall be done prior to OC
Swimming Pool and Ground floor amenity area : YES 100 Shall be done prior to OC
Aggregate area of recreational Open Space : YES 95 Shall be done prior to OC
Open Parking : NO 0 NA
Water Supply : YES 95 After OC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 WORK IN PROGRESS
Storm Water Drains : YES 100 Shall be done prior to OC
Landscaping & Tree Planting : YES 95 Shall be done prior to OC
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 Shall be done prior to OC
Solid Waste Management And Disposal : YES 0 Shall be done prior to OC

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 KABRA CENTROID A Redevelopment of GOP CHSL 1 31/12/2020 0 1 0 14 1 3 245
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 50.07 9 9
2 2BHK 57.60 4 4
3 2BHK 61.13 9 7
4 2BHK 63.55 9 9
5 2BHK 65.03 4 0
6 2BHK 65.59 9 9
7 2BHK 71.54 4 3
8 2BHK 71.40 23 20
9 2BHK 73.11 4 1
10 2BHK 74.32 3 0
11 3BHK 80.45 10 9
12 3BHK 90.30 30 20
13 3BHK 89.37 3 0
14 3BHK 95.78 9 3
15 4BHK 140.66 10 6
16 4BHK 146.77 3 1
17 3BHK 73.02 13 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Pravati Corporation MR VINOD K MAVANI NA Contractor
Confair Contractor MR HANIF RIDANI NA Contractor
Anil Enterprises MR ANIL VISHWAKARMA NA Contractor
Gloria Mark Electric Pvt Ltd MR GERALD LEWIS NA Contractor
Arjun Arts MR AMEYA ARJUN KADAM NA Contractor
Hari Om Plumber Contractor MR ROHIT MANJI VERAT NA Contractor
ARCH HEMANT TALATY NA Architect
GVS Architects and Associates ARCH JAIMAN SHAH NA Architect
Reza Kabul Architects Pvt Ltd ARCH REZA KABUL NA Architect
MAK MEP Consulatants MRS SANGEETA MANIRAM VARMA NA Other Professional
Taib Landscape Studio Pvt Ltd MS SAIDAH TAIB NA Other Professional
PEC Greening India MALA SINGH NA Other Professional
SURA AND ASSOCIATES MR PIYUSH K SURA NA Engineer
PRASHANTH PANDU SHETTY A51800005741 Real Estate Agent
Madhusudan Navalram Darak Proprietor of Madhusudan N Darak Estate Consultant A51800014269 Real Estate Agent
DAULATSINGH G GADHVI A51900000248 Real Estate Agent
Mumbai Space Realty LLP A51800004371 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Form 2A
2 Form 2A
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 CERSAI details
1 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement