MahaRERA Application

General Information

Other Than Individual

Organization

EV HOMES CONSTRUCTIONS PVT LTD
Company
NA
Do you have any Past Experience ?
Yes

Address Details

A-212
VARDHMAN CHMABERS
PLOT NO 84
SECTOR 17
VASHI
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400703

Organization Contact Details

02227890325

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1SAFFIRE HEIGHTSResidentialNA1800PLOT NO 32A AND 33A SECTOR 12 KALAMBOLI TALUKA PANVEL DISTT RAGIAD 410209PLOT NO A32 AND A33 SECTOR 12 KALAMBOLI1702010-03-312012-05-24
2E V CASTLEResidentialNA848.75PLOT NO 110 SECTOR 9 ULVE TALUKA PANVEL DISTT RAIGAD 410206PLOT NO 110 SECTOR 9 ULVE TALUKA PANVEL DISTT RAIGAD 4102061262016-04-302016-04-27
3SINAI TOWERResidentialNA1514KAKINAD KOCHI KERALA 682017KAKINAD KOCHI KERALA 6820171382017-07-312017-02-03
4ZION I AND IIResidentialNA3178PLOT NO 29 AND 30 SECTOR 25 NERUL EAST NAVI MUMBAI 400706PLOT NO 29 AND 30 SECTOR 25 NERUL EAST NAVI MUMBAI 4007062592016-03-312017-05-26

Member Information

Member Name Designation Photo
ELENJIKAMALIL VARKEY THOMAS Managing Director View Photo
JOISE THOMAS Managing Director View Photo
VICKY THOMAS Managing Director View Photo
VICKY THOMAS Authorized Signatory View Photo
RICKI THOMAS Managing Director View Photo

Project

EV Shradha
New Project
30/06/2028
No
Residential
Yes
Plot No. 10
Proposed 15 Mtrs Wide Road
Proposed 15 Mtrs Wide Road
Proposed 9 Mtr Wide Road
Proposed 15 Mtrs Wide Road
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
Sector 10
Vashi
400703
10390.38
3
3
0
1658.30

FSI Details

49870.49
0
49870.49

Bank Details

State Bank of India
SBIN0011785

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
EV Shradha Shradha Co-Operative Housing Society Limited Societies Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 581 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 NOT YET STARTED
Energy management : YES 0 NOT YET STARTED
Fire Protection And Fire Safety Requirements : YES 0 NOT YET STARTED
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 NOT YET STARTED
Aggregate area of recreational Open Space : YES 0 NOT YET STARTED
Open Parking : NO 0 NA
Water Supply : YES 0 NOT YET STARTED
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 NOT YET STARTED
Storm Water Drains : YES 0 NOT YET STARTED
Landscaping & Tree Planting : YES 0 NOT YET STARTED
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 NOT YET STARTED
Solid Waste Management And Disposal : YES 0 NOT YET STARTED

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 EV Shradha EV 10 Marina Bay 31/12/2027 0 1 4 23 1 0 371
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 65.62 44 28
2 2BHK 52.36 44 22
3 3BHK 82.74 88 32
4 3BHK 119.15 44 14
5 2BHK 63.60 4 2
6 2BHK 64.43 3 3
7 2BHK 61.11 3 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 50
2 X number of Basement(s) and Plinth 50
3 X number of Podiums 50
4 Stilt Floor 50
5 X number of Slabs of Super Structure 95
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 40
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 EV Shradha Ev Shraddha Wing A1 31/12/2027 0 1 2 25 1 0 105
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 44.19 100 0
2 2BHK 54.63 50 0
3 3BHK 63.58 50 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 50
2 X number of Basement(s) and Plinth 50
3 X number of Podiums 50
4 Stilt Floor 50
5 X number of Slabs of Super Structure 33
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 35
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

00
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 26.8
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 EV Shradha EV Shradha Wing A 2 31/12/2027 0 1 2 25 1 0 105
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 52.36 26 4
2 2BHK 61.12 3 1
3 2BHK 63.61 4 2
4 2BHK 64.44 3 1
5 2BHK 65.63 44 11
6 3BHK 82.74 88 13
7 3BHK 119.15 44 5
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 50
2 X number of Basement(s) and Plinth 50
3 X number of Podiums 15
4 Stilt Floor 50
5 X number of Slabs of Super Structure 25
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 20
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 21

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Megha Enterprises NA Contractor
Dessin 2000 NA Architect
Vinit Structural Consultancy Pvt Ltd NA Engineer
C.M Electricals NA Contractor
J. S. Enterprises NA Contractor
Royal Fire Protection Services Pvt. Ltd. NA Contractor
Business Leader NA Contractor
Sadik Ansari NA Contractor
J. S. Enterprises NA Contractor
E. A. Patil & Associates LLP NA Chartered Accountant
Krishna R Moondra & Associates NA Chartered Accountant
Aristo Real Estate Consultants A51700036861 Real Estate Agent
KULWANT KAUR MANJINDER SINGH PANESAR A51700009022 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
5 Copy of Layout Approval (in case of layout)
6 Copy of Layout Approval (in case of layout)
7 Copy of Layout Approval (in case of layout)
8 Copy of Layout Approval (in case of layout)
9 Copy of Layout Approval (in case of layout)
10 Copy of Layout Approval (in case of layout)
11 Copy of Layout Approval (in case of layout)
12 Copy of Layout Approval (in case of layout)
13 Copy of Layout Approval (in case of layout)
14 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement