MahaRERA Application

General Information

Other Than Individual

Organization

Bramhacorp Limited
Company
NA
Do you have any Past Experience ?
Yes

Address Details

3 Queen's Garden
Residency Club
Generl A. Vaidya Marg
Camp
Wadia college bridge
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411001

Organization Contact Details

02041423333

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Bramha Suncity PlatinumOthersResidential & Commercial9609.33S No 7 Hissa No 1 to 5 S No 8 Hissa No 1 1 2 S No 38A Hissa No 1B 1 S No 38A Hissa No 1A S No 38B Village Wadgaon Sheri PuneS No 7 Hissa No 1 to 5 S No 8 Hissa No 1 1 2 S No 38A Hissa No 1B 1 S No 38A Hissa No 1A S No 38B Vi41342014-09-292014-09-29
2Bramha BaugResidentialNA11315.7Survey No 55B Hissa No 1A 2B at Village Ghorpadi Taluka Haveli District PuneSurvey No 55B Hissa No 1A 2B at Village Ghorpadi Taluka Haveli District Pune182017-01-312017-02-01
3Bramha Vantage A / BOthersResidential & Commercial2329.8Survey No 6 Hissa No 10 1B Bavdhan Khurd Taluka Mulshi District PuneSurvey No 6 Hissa No 10 1B Bavdhan Khurd Taluka Mulshi District Pune2512017-08-312017-04-29

Member Information

Member Name Designation Photo
ALKA REGE Authorized Signatory View Photo

Project

F Residences T8
On-Going Project
31/12/2018
30/06/2022
No
Residential
No
SURVEY NO. 7/1,7/2,7/3,7/4,7/5, 8/1/1/2,38A/1B/1,38A/1A,38B,3/2
AMENITY AREA AND FURTHER T4 BUILDING
FURTHER PROPOSED DEVELOPMENT OF THE LAYOUT
T1 BUILDING FURTHER 18M DP ROAD
T7 BUILDING FURTHER OPEN SPACE OF ENTIRE LAYOUT
MAHARASHTRA
Pune
Pune
Haveli
VADGAONSHERI
Vadgaonsheri Street
Vadgaonsheri
411014
532.68
1
1
0
0

FSI Details

7657.05
0
7657.05

Bank Details

ICICI BANK
ICIC0006488

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) NA NA 0
Covered Parking ( In Numbers) NA NA 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Concrete roads granite paving tiles pavers
Water Conservation, Rain water Harvesting : YES 100 Rain water harvesting
Energy management : YES 90 Solar for heating water
Fire Protection And Fire Safety Requirements : YES 100 FF FA & PA system
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Power from MSEDCL - Sub station works complete
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 90 Potable drinking water from statutory authority
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 STP 600 KLD
Storm Water Drains : YES 100 RCC pipes connected with chambers
Landscaping & Tree Planting : YES 75 Trees plants lawn
Street Lighting : YES 100 street lights
Community Buildings : YES 100 Club house
Treatment And Disposal Of Sewage And Sullage Water : YES 100 STP - 600 KLD
Solid Waste Management And Disposal : YES 100 OWC equipment

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 F Residences T8 F RESIDENCES TOWER 8 30/06/2021 1 1 1 22 1 0 86
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 88.34 3 1
2 3.5 BHK 64.85 1 1
3 3.5BHK 66.36 1 0
4 3.5BHK 72.24 7 3
5 3.5BHK 77.70 7 4
6 3.5BHK 78.15 3 2
7 3.5BHK 78.17 11 5
8 3.5BHK 78.25 1 0
9 3.5BHK 80.28 7 4
10 3.5BHK 82.86 7 2
11 3.5BHK 83.62 3 1
12 3.5BHK 84.00 11 6
13 3.5BHK 84.08 1 0
14 3.5BHK 85.76 14 6
15 3.5BHK 88.33 11 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 97
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 78
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

90
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 95
11 Overall Percentage of Completion of the work done For the entire Building /Wing 96

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SUNIL VARTAK & ASSOCIATES NA Architect
HM Raje Structural consultants Pvt Ltd NA Engineer
Arpee Infra corporation NA Contractor
UMESH RAMESH PAWAR A52100000006 Real Estate Agent
A K Properties A52100000622 Real Estate Agent
Premlata Estate Solutions Pvt. Ltd. A52100000033 Real Estate Agent
NIKHIL JAIN A52100000055 Real Estate Agent
PROPBUYING REALTORS PVT LTD A52100000476 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
3 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
2 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement