Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
1 |
VISHWAJEET PARADISE
|
BUILDING - 1 MAJESTIC
|
30/09/2019
|
0
|
1
|
0
|
13
|
0 |
10 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1RK |
25.52 |
12 |
12 |
2 |
1BHK |
31.47 |
1 |
1 |
3 |
1BHK |
32.14 |
3 |
3 |
4 |
1RK |
20.92 |
1 |
1 |
5 |
1RK |
21.65 |
12 |
12 |
6 |
1RK |
24.37 |
11 |
11 |
7 |
1BHK |
33.27 |
12 |
12 |
8 |
1BHK |
32.48 |
12 |
12 |
9 |
1BHK |
34.04 |
24 |
24 |
10 |
1BHK |
32.85 |
1 |
1 |
11 |
1RK |
23.63 |
1 |
1 |
12 |
1BHK |
33.05 |
36 |
36 |
13 |
1BHK |
33.20 |
2 |
2 |
14 |
1RK |
25.10 |
1 |
1 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
2 |
VISHWAJEET PARADISE
|
BUILDING - 2 BLISS
|
30/09/2019
|
0
|
1
|
0
|
13
|
0 |
10 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1RK |
23.58 |
1 |
1 |
2 |
1RK |
26.71 |
13 |
13 |
3 |
1BHK |
29.36 |
1 |
1 |
4 |
1BHK |
29.82 |
7 |
7 |
5 |
1BHK |
30.71 |
1 |
1 |
6 |
1BHK |
31.13 |
9 |
9 |
7 |
1BHK |
31.45 |
1 |
1 |
8 |
1BHK |
32.25 |
1 |
1 |
9 |
1BHK |
32.31 |
12 |
12 |
10 |
1BHK |
33.15 |
8 |
8 |
11 |
1BHK |
33.97 |
1 |
1 |
12 |
1BHK |
34.44 |
10 |
10 |
13 |
1BHK |
34.97 |
12 |
12 |
14 |
1BHK |
34.98 |
1 |
1 |
15 |
1BHK |
37.4 |
1 |
1 |
16 |
1BHK |
38.20 |
12 |
12 |
17 |
2BHK |
44.36 |
1 |
1 |
18 |
2BHK |
44.89 |
12 |
12 |
19 |
2BHK |
48.58 |
1 |
1 |
20 |
2BHK |
48.73 |
1 |
1 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
3 |
VISHWAJEET PARADISE
|
BUILDING - 3 SERENE
|
30/09/2019
|
0
|
1
|
0
|
10
|
0 |
10 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
36.61 |
9 |
9 |
2 |
2BHK |
43.8 |
1 |
1 |
3 |
2BHK |
44.18 |
8 |
8 |
4 |
2BHK |
46.63 |
8 |
8 |
5 |
2BHK |
46.27 |
1 |
1 |
6 |
1BHK |
36.75 |
1 |
1 |
7 |
1RK |
24.59 |
1 |
1 |
8 |
1RK |
25.29 |
9 |
9 |
9 |
1BHK |
29.81 |
1 |
1 |
10 |
1BHK |
30.25 |
7 |
7 |
11 |
1BHK |
30.83 |
1 |
1 |
12 |
1BHK |
35.18 |
1 |
1 |
13 |
1BHK |
31.79 |
9 |
9 |
14 |
1BHK |
35.65 |
1 |
1 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
4 |
VISHWAJEET PARADISE
|
BUILDING -4 ORION
|
30/09/2019
|
0
|
1
|
0
|
5
|
0 |
10 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1RK |
19.06 |
15 |
15 |
2 |
1RK |
20.44 |
5 |
5 |
3 |
1RK |
20.69 |
5 |
5 |
4 |
1BHK |
24.89 |
5 |
5 |
5 |
1BHK |
25.84 |
4 |
4 |
6 |
1BHK |
25.88 |
1 |
1 |
7 |
1BHK |
26.27 |
5 |
5 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|