MahaRERA Application

General Information

Other Than Individual

Organization

S R Development Corportaion
Partnership
NA
Do you have any Past Experience ?
No

Address Details

Flat No. 6
Shweta Corner
Prabhat Road Lane No. 7
Prabhat Road
Gawaksha Boutique
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411004

Organization Contact Details

02025652222

Past Experience Details

Member Information

Member Name Designation Photo
Amol Kashinath Bhondve Partner View Photo
Dhanesh Vasantrao Mali Authorized Signatory View Photo

Project

Baner Business Bay
New Project
30/03/2022
30/06/2023
Yes
Commercial
Yes
Sr No 52 Hissa No 5/2/3 5/2/5 5/2/6
6 Metre Wide Road
9 Metre Wide Road
Plot
30 Metre Wide Road
MAHARASHTRA
Pune
Pune
Haveli
Baner
Pashan Sus Road
Pune
411045
2096
1
1
0
2096

FSI Details

1852.05
3172.2
5024.25

Bank Details

State Bank of India
SBIN0004523

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Baner Business Bay Sachin Suresh Patil Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Baner Business Bay ABP Group Others Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 105 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 UG WT Completed
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 Work Completed
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Work Completed
Aggregate area of recreational Open Space : NO 0 Work about to start
Open Parking : NO 0 NA
Water Supply : YES 100 Work Completed
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Work Completed
Storm Water Drains : YES 100 Work Completed
Landscaping & Tree Planting : YES 100 Work Completed
Street Lighting : NO 0 Tree Planting completed at site
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Baner Business Bay 1 30/03/2022 4 1 0 14 1 0 105
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Office space 55.80 5 2
2 Office space 49.41 6 2
3 Office space 95.50 2 1
4 Office space 126.58 1 1
5 Office space 53.48 6 2
6 Office space 205.74 1 1
7 Office space 586.08 1 0
8 Office space 585.04 2 1
9 Office space 96.66 3 1
10 Office space 318.12 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Bhushan Kulkarni NA Architect
Knight Frank (India) Private Limited A51900000099 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Baner Business Bay THE HONBLE CIVIL JUDGE SENIOR DIVISION PUNE 562/2017 Civil No Suit NA 2017 Pending Before Honble Civil Judge Pune
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
5 Copy of Layout Approval (in case of layout)
6 Copy of Layout Approval (in case of layout)
7 Copy of Layout Approval (in case of layout)
8 Copy of Layout Approval (in case of layout)
9 Copy of Layout Approval (in case of layout)
10 Copy of Layout Approval (in case of layout)
11 Copy of Layout Approval (in case of layout)
12 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC005000000023357 Mr. Santosh Mukunda Tapkir View Orders