MahaRERA Application

General Information

Other Than Individual

Organization

ANUSHKA DEVELOPERS
Partnership
NA
Do you have any Past Experience ?
No

Address Details

SHOP NO.05
RANDHIR VIHAR SOCIETY
LALASHET COMPOUND
NEAR SYNDICATE BANK
BHANDUP WEST
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
400078

Organization Contact Details

02512486222

Past Experience Details

Member Information

Member Name Designation Photo
NITIN BHIVA KSHIRSAGAR Authorized Signatory View Photo
ROMIL JAYESH DOSHI Partner View Photo
JAYESH ANANTRAI DOSHI Partner View Photo

Project

ARYA GREENS
New Project
30/12/2023
29/12/2024
No
Residential
No
78,78 1 TO 6
CTS NO 79 ADJOINING SLUM
37 M WIDE PROPOSED DP ROAD
CTS NO 80 ADJOINING SLUM
CTS NO 77 AND ROAD
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
NISARG CHS VILLAGE
BHANDUP WEST
400078
1463.50
1
1
0
0

FSI Details

6519
0
6519.00

Bank Details

AXIS BANK
UTIB0002933

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 24 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 DEVELOPER
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 DEVELOPER
Electrical Meter Room, Sub-Station, Receiving Station : YES 10 DEVELOPER
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 0 NA
Water Supply : YES 0 MCGM
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 MCGM
Storm Water Drains : YES 0 DEVELOPER
Landscaping & Tree Planting : NO 0 NA
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 ARYA GREENS ARYA GREENS 31/12/2022 0 1 0 23 1 2 24
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1RK 16.54 16 7
2 1RK 19.23 16 14
3 1RK 17.47 16 11
4 1RK 19.51 16 9
5 1BHK 23.97 16 14
6 1BHK 30.56 16 9
7 1BHK 33.07 16 10
8 Shop 5.71 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 70
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

30
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
11 Overall Percentage of Completion of the work done For the entire Building /Wing 62

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
S S ASSOCIATES NA Architect
NEXUS PROJECT SOLUTIONS PVT LTD NA Engineer
GPATS & CO NA Chartered Accountant
Sandeep Sirsat NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
5 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
3 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement