MahaRERA Application

General Information

Other Than Individual

Organization

Keystone Properties
Partnership
NA
Do you have any Past Experience ?
No

Address Details

1205/3/3
Business Embassy
JM Road
Shivajinagar
Opp Balgandharv Rang Mandir
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411004

Organization Contact Details

02025532090
www.goyalproperties.in

Past Experience Details

Member Information

Member Name Designation Photo
Mohit Goyal Authorized Signatory View Photo
Rohit Goyal Partner View Photo
Subhash Gupta Partner View Photo
Sunny Gupta Partner View Photo

Project

MY HOME PUNAWALE
On-Going Project
31/12/2016
30/06/2021
30/12/2022
No
Residential
Yes
16/3, Near Lotus Business School Pune Banglore Highway pune-411033
Part of S No 17
3 Mtr DP Road
Part of S No 16
Part of S No 16
MAHARASHTRA
Pune
Pune
Mulshi
Punawale
PUNAWALE
PUNAWALE
411033
16955
2
2
0
1643.26

FSI Details

14673.76
6554.89
21228.65

Bank Details

ICICI Bank Ltd
ICIC0000039

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
MY HOME PUNAWALE Royal Developers Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 144 144 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 As per Consultant Drawing
Water Conservation, Rain water Harvesting : YES 100 As per Consultant Drawing
Energy management : YES 100 As per Consultant Drawing
Fire Protection And Fire Safety Requirements : YES 100 As per Consultant Drawing
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 As per Consultant Drawing
Amphitheatre : YES 100 As per Consultant Drawing
CCTV Surveillance System : YES 100 As per Consultant Drawing
Childrens Play Area : YES 100 As per Consultant Drawing
Compound Wall : YES 100 As per Consultant Drawing
Gymnasium : YES 100 As per Consultant Drawing
Intercom DTH Broadband : YES 100 As per Consultant Drawing
Jogging Track : YES 100 As per Consultant Drawing
Multipurpose Court : YES 100 As per Consultant Drawing
Swimming Pool : YES 100 As per Consultant Drawing
Aggregate area of recreational Open Space : YES 100 As per Consultant Drawing
Open Parking : YES 100 As per Consultant Drawing
Water Supply : YES 100 As per Consultant Drawing
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 As per Consultant Drawing
Storm Water Drains : YES 100 As per Consultant Drawing
Landscaping & Tree Planting : YES 100 As per Consultant Drawing
Street Lighting : YES 100 As per Consultant Drawing
Community Buildings : YES 100 As per Consultant Drawing
Treatment And Disposal Of Sewage And Sullage Water : YES 100 As per Consultant Drawing
Solid Waste Management And Disposal : YES 100 As per Consultant Drawing

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 MY HOME PUNAWALE My Home Punawale Wing C 31/12/2020 0 1 0 13 1 43 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK TYPE 1 38.15 4 4
2 2 BHK TYPE 1 52.08 24 23
3 2 BHK TYPE 2 51.60 20 20
4 2 BHK TYPE 3 52.51 12 12
5 2 BHK TYPE 4 52.37 9 9
6 2 BHK TYPE 5 52.62 9 9
7 2 BHK TYPE 6 52.76 12 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 MY HOME PUNAWALE My Home Punawale Wing D 1 1 1 14 1 16 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK TYPE 1 38.15 2 2
2 2 BHK TYPE 1 52.08 24 24
3 2 BHK TYPE 2 51.60 22 22
4 2 BHK TYPE 3 52.51 12 12
5 2 BHK TYPE 4 52.37 9 9
6 2 BHK TYPE 5 52.62 9 9
7 2 BHK TYPE 6 52.76 12 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
R-Constellation Pvt. Ltd. A52100000304 Real Estate Agent
D N Infra NA Contractor
Akash Construction NA Contractor
Shahbuddin Shaikh NA Contractor
Pratik Engineers & Contractors NA Contractor
M D Construction NA Contractor
Amruta Enterprises NA Contractor
Rohan Power NA Contractor
Sitaram Pandit NA Contractor
AVINASH NAWATHE NA Architect
Spectrum Consultnat NA Engineer
Envicon Consultant NA Other Professional
McLIN Consultant NA Other Professional
Mahesh Chinchalikar NA Other Professional
Prasanna Darade NA Other Professional
Star Fire Systems NA Other Professional
Sprout Consultant NA Other Professional
Planedge Consultant Pvt Ltd NA Other Professional

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
2 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement