MahaRERA Application

General Information

Other Than Individual

Organization

Mahalunge Township Developers LLP
Others
Limited Liability Partnership
Do you have any Past Experience ?
No

Address Details

5
GODREJ ONE
EASTERN EXPRESS HIGHWAY
VIKHROLI EAST
PIROJSHANAGAR
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
400079

Organization Contact Details

http://www.godrejproperties.com

Past Experience Details

Other Organization Type Member Information

Name Member Type
Godrej Properties Limited Company
Mahalunge Land Developers Private Limited Company

Project

Godrej Hill Retreat
New Project
31/12/2025
Yes
Others
No
Sector R7- Survey No 41/4, 42/1 part, 42/5, 42/6, 42/7, 42/8 part
Proposed 12m wide pedestrian street
Proposed 30m wide RP road
Part of Survey No 42
Adjoining Project Godrej Green Cove
MAHARASHTRA
Pune
Pune
Mulshi
Mahalunge
MDR Road
Mahalunge
411045
17034.77
3
3
0
1490.51

FSI Details

60420.88
60
60480.88

Bank Details

ICICI Bank Limited
ICIC0000321

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 5556 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 As per approved plan
Water Conservation, Rain water Harvesting : YES 0 recharge pits provided as per approved drawings
Energy management : YES 0 Solar heated water in master bedroom toilet
Fire Protection And Fire Safety Requirements : YES 0 Fire alarm system
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 wet risers
Parkings : YES 0 meter room as per drawing
Aggregate area of recreational Open Space : YES 0 all parkings include cycle scooters and cars
Open Parking : NO 0 as per amenity annexure
Water Supply : YES 0 NA
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 municipal water tanker water river water
Storm Water Drains : YES 0 stp as per design
Landscaping & Tree Planting : YES 0 as per approved drawings
Street Lighting : YES 0 as per approved drawings
Community Buildings : YES 0 as per design
Treatment And Disposal Of Sewage And Sullage Water : YES 0 as per amenity annexure
Solid Waste Management And Disposal : YES 0 treated water for gardening and toilet flushing

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Godrej Hill Retreat Tower- B1 31/12/2025 0 1 4 33 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 35.43 3 3
2 3BHK 79.08 16 16
3 2BHK 55.71 1 1
4 4BHK 94.28 1 1
5 2BHK 59.72 1 0
6 2BHK 57.53 1 0
7 2BHK 55.49 13 13
8 1BHK 35.28 2 2
9 Shop 44.95 1 1
10 Shop 65.96 1 1
11 Shop 71.05 1 1
12 2BHK 56.27 1 1
13 2BHK 55.02 28 28
14 2BHK 55.25 28 28
15 2BHK 55.74 15 15
16 Shop 82.77 1 1
17 2BHK 55.59 15 15
18 2BHK 55.81 16 16
19 2BHK 55.93 16 16
20 3BHK 79.56 1 1
21 1BHK 38.81 2 2
22 2BHK 55.51 13 13
23 3BHK 76.57 15 15
24 3BHK 77.17 15 15
25 1BHK 38.96 3 3
26 Studio 20.28 1 1
27 Shop 57.15 1 1
28 Shop 89.33 1 0
29 Shop 27.54 1 1
30 Shop 32.92 1 1
31 3BHK 78.47 15 15
32 2BHK 57.11 15 15
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 60
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 13
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 6
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 16
11 Overall Percentage of Completion of the work done For the entire Building /Wing 29.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Godrej Hill Retreat Tower- B2 31/12/2025 0 1 4 33 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 145.80 1 0
2 Studio 20.28 1 1
3 2BHK 55.02 27 27
4 2BHK 55.49 12 11
5 3BHK 77.17 15 15
6 3BHK 79.08 16 16
7 1BHK 35.28 2 2
8 2BHK 55.51 13 13
9 3BHK 76.57 14 14
10 2BHK 56.27 1 1
11 3BHK 79.14 1 1
12 4BHK 94.28 1 1
13 Shop 49.30 1 1
14 Shop 54.38 1 1
15 Shop 84.57 1 1
16 1BHK 38.81 2 2
17 1BHK 38.96 3 3
18 2BHK 57.53 1 0
19 2BHK 55.71 1 1
20 2BHK 55.81 15 15
21 2BHK 55.93 15 14
22 2BHK 57.11 15 15
23 Shop 39.34 1 1
24 Shop 40.18 1 1
25 Shop 67.17 1 1
26 1BHK 35.43 3 3
27 2BHK 55.59 15 15
28 Shop 45.93 1 1
29 2BHK 55.25 27 27
30 2BHK 55.74 15 15
31 2BHK 57.14 16 16
32 3BHK 78.47 15 15
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 35
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 8
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 24
11 Overall Percentage of Completion of the work done For the entire Building /Wing 36.7
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Godrej Hill Retreat Tower- B3 31/12/2025 0 1 4 33 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 53.92 1 1
2 Studio 20.28 1 1
3 Shop 39.94 1 1
4 2BHK 55.74 15 15
5 2BHK 57.14 16 16
6 3BHK 77.17 15 15
7 2BHK 55.71 1 0
8 2BHK 56.27 1 0
9 3BHK 76.57 14 14
10 Shop 57.64 1 1
11 2BHK 57.11 15 15
12 4BHK 94.28 1 1
13 3BHK 79.08 16 16
14 Shop 89.23 1 1
15 2BHK 55.02 27 27
16 Shop 44.98 1 1
17 2BHK 57.53 1 0
18 3BHK 79.62 1 1
19 2BHK 55.81 16 16
20 2BHK 55.49 12 11
21 2BHK 55.93 15 15
22 Shop 45.67 1 1
23 Shop 49.00 1 1
24 Shop 27.54 1 1
25 2BHK 55.25 28 26
26 2BHK 55.51 13 13
27 2BHK 55.59 15 15
28 3BHK 78.47 15 15
29 1BHK 35.28 2 2
30 1BHK 35.43 3 3
31 1BHK 38.81 2 2
32 1BHK 38.96 3 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 35
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 24
11 Overall Percentage of Completion of the work done For the entire Building /Wing 36.8

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
360 REALTORS LLP A51900000246 Real Estate Agent
3B CONSULTING PRIVATE LIMITED A51700004497 Real Estate Agent
A K Properties A52100000622 Real Estate Agent
Addressofchoice Realty Pvt Ltd A52100000116 Real Estate Agent
AMIT VINODKUMAR GUPTA A52100000529 Real Estate Agent
Sarika Infratech NA Contractor
Anil Powar NA Engineer
MD Deshpande and Co NA Chartered Accountant
Vka NA Architect
ESKAYEM Consultants Pvt. Ltd. NA Other Professional
Strudcom Consultants Pvt.Ltd. NA Other Professional

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Godrej Hill Retreat District Judge and Addl Sessions Judge Pune RCA 601 Civil No Appeal NA 2014 Pending
NA
Godrej Hill Retreat Civil Judge Junior DIvision RCS 1233 Civil Yes Suit NA 2014 Pending
Godrej Hill Retreat Civil Judge Junior DIvision RCS 822 Civil No Suit NA 2008 Case Disposed
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
3 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
10 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
8 Engineer’s Certificate on Cost Incurred on Project (Form 2)
9 Engineer’s Certificate on Cost Incurred on Project (Form 2)
10 Engineer’s Certificate on Cost Incurred on Project (Form 2)
11 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
6 Disclosure of sold/ booked inventory
7 Disclosure of sold/ booked inventory
8 Disclosure of sold/ booked inventory
9 Disclosure of sold/ booked inventory
10 Disclosure of sold/ booked inventory
11 Disclosure of sold/ booked inventory
12 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement