MahaRERA Application

General Information

Other Than Individual

Organization

AMAR ASSOCIATES
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

101
A-63
SECTOR-1
SHANTI NAGAR , MIRA ROAD (e)
NEAR RLY STATION
MAHARASHTRA
Konkan
Thane
Thane
Mira-Bhayandar (M Corp.)
401107

Organization Contact Details

02228118338

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1SAHJEEVAN CHSLResidentialNA1389.70ROKADIA CROSS LANE OPP S E INTERNATIONAL SCHOOL BEHIND GOKUL HOTEL BORIVALI WEST MUMBAI 922474/B 1 TO 81162017-03-012017-02-27

Member Information

Member Name Designation Photo
JAYESH VINAYCHAND DOSHI Authorized Signatory View Photo
SHAILESH VINAYCHAND DOSHI Partner View Photo

Project

VINAY HERITAGE
New Project
30/12/2024
No
Residential
No
67, 68
POOJA PARK SOCIETY
JHANKAR FACTORY
18 MTS WIDE DP ROAD
S NO 15 PART
MAHARASHTRA
Konkan
Thane
Thane
Mira-Bhayandar (M Corp.)
NEAR VINAY NAGAR PLESENT PALACE NEXT TO JHANKAR FACTORY OFF MIRA BHAYANDAR ROAD MIRA ROAD EAST
MIRA ROAD EAST
401107
7598.31
1
1
0
608.23

FSI Details

14819.24
9447.92
24267.16

Bank Details

INDUSIND BANK
INDB0000600

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 00 00 00
Covered Parking ( In Numbers) 118 00 5

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 00 WORK IN PROGRESS
Energy management : YES 00 SOLAR WATER HEATER
Fire Protection And Fire Safety Requirements : YES 00 WORK IN PROGRESS
Electrical Meter Room, Sub-Station, Receiving Station : YES 00 WORK IN PROGRESS
Aggregate area of recreational Open Space : YES 00 WORK IN PROGRESS
Open Parking : YES 00 WORK IN PROGRESS
Water Supply : YES 00 WORK IN PROGRESS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 00 WORK IN PROGRESS
Storm Water Drains : YES 00 WORK IN PROGRESS
Landscaping & Tree Planting : YES 00 WORK IN PROGRESS
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 VINAY HERITAGE VINAY HERITAGE 31/12/2023 00 1 1 22 118 16 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 29.64 4 0
2 SHOP 41.99 4 0
3 SHOP 35.86 2 0
4 SHOP 22.11 2 0
5 SHOP 31.03 2 0
6 SHOP 40.41 2 0
7 SHOP 34 1 0
8 SHOP 5.76 1 0
9 SHOP 37.81 4 2
10 SHOP 27.96 2 1
11 SHOP 49.33 2 1
12 SHOP 33.44 2 1
13 SHOP 27.68 2 1
14 SHOP 28.06 2 1
15 SHOP 32.24 2 1
16 SHOP 31.68 6 1
17 SHOP 68.38 2 1
18 SHOP 56.58 2 1
19 SHOP 37.90 2 1
20 1BHK 42.74 20 3
21 1BHK 44.50 20 5
22 1BHK 48.31 38 2
23 2BHK 66.43 40 3
24 2BHK 64.57 74 4
25 2BHK 60.39 20 0
26 2BHK 65.40 2 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 00
4 Stilt Floor 00
5 X number of Slabs of Super Structure 00
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 00
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 00
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 00
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

00
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00
11 Overall Percentage of Completion of the work done For the entire Building /Wing 20

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
KHODIYAR CONSTRUCTION NA Contractor
ANISH & ASSOCIATES NA Architect
HIREN M TANNA NA Engineer
R D LUKAD & CO NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
2 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 CERSAI details
1 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement