MahaRERA Application

General Information

Other Than Individual

Organization

Eversmile Properties Private Limited
Company
NA
Do you have any Past Experience ?
No

Address Details

75
Srishti Complex
Penkarpada Road
Mira Road
Shrushti Chowk
MAHARASHTRA
Konkan
Thane
Thane
Mira-Bhayandar (M Corp.)
401104

Organization Contact Details

02230645000

Past Experience Details

Member Information

Member Name Designation Photo
Amit Shah Authorized Signatory View Photo

Project

Sector 2A - Wing B
New Project
30/12/2027
Yes
Residential
No
New Survey No 66Pt and 68Pt of Village Penkarpada
Partly by S No 66Pt and 68Pt of village Penkarpada
Partlyt S No 66Pt and 68Pt of Village Penkarpada
S No 66Pt of villae Penkarpada
Partly touching to Wing A and Partly S No 66Pt
MAHARASHTRA
Konkan
Thane
Thane
Mira-Bhayandar (M Corp.)
Bhaktivedanta Swami Marg
Shrushti Chowk, Mira Road
401107
833.08
1
1
0
0

FSI Details

20496.58
1725.48
22222.06

Bank Details

HDFC Bank Ltd
HDFC0000060

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 231 119 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 To be done before completion of Whole Project
Water Conservation, Rain water Harvesting : YES 0 To be done before completion of Whole Project
Energy management : YES 0 To be done before completion of Whole Project
Fire Protection And Fire Safety Requirements : YES 0 To be done before completion of Whole Project
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Electrical Meter Room and Sub station only
2 Nos of Common Basement : YES 0 Common development as per AFS
2 Nos of Common Podium : YES 0 Common development as per AFS
Club House, Swimming Pool and other Recreational Areas : YES 0 Common Amenities as per AFS
Aggregate area of recreational Open Space : YES 0 3788.04 Sq Mt Common RG as per AFS
Open Parking : NO 0 NA
Water Supply : YES 0 Water Supply from Local Authority
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 STP only
Storm Water Drains : YES 0 To be done before completion of Whole Project
Landscaping & Tree Planting : YES 0 To be done before completion of Whole Project
Street Lighting : YES 0 To be done before completion of Whole Project
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 To be done before completion of Whole Project
Solid Waste Management And Disposal : YES 0 To be done before completion of Whole Project

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Sector 2A - Wing B Wing - B 31/12/2025 2 1 2 34 1 0 231
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 58.36 67 61
2 3BHK 79.09 60 55
3 2BHK 53.21 34 22
4 2BHK 53.45 60 20
5 3BHK 80.21 6 5
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 73
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 5
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

1
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 13
11 Overall Percentage of Completion of the work done For the entire Building /Wing 49.2

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Vinod Champalal Gadri A51700000639 Real Estate Agent
LOCALITY MASTER A51700002449 Real Estate Agent
Nitin Ajabrao Sonawane A51700003026 Real Estate Agent
Vijay Bahadur Singh A51700005760 Real Estate Agent
Propvilla Realty Pvt Ltd A51700007597 Real Estate Agent
KISHORE JAIPRAKASH VYAS A51700008031 Real Estate Agent
KAN INDIA REALTORS PRIVATE LIMITED A51700008693 Real Estate Agent
Manisha Lifespaces Consulting Pvt. Ltd. A51800008040 Real Estate Agent
JM Financial Products Limited A51900000277 Real Estate Agent
SUDHIR GHANSHYAM PANDEY A52000011171 Real Estate Agent
Jethe And Associates (Form - 1) NA Architect
Hillel Divekar (Form -2) NA Engineer
C R Mohnot & Co ( CA Certificate-Form 3) NA Chartered Accountant
Mandviwala Qutub & Associates (Design Architect) NA Other Professional
Dr.Kelkar Designs Pvt.Ltd. (Structural Consultant) NA Other Professional
Integrated Technical Services(MEP Consultant) NA Other Professional

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Sector 2A - Wing B Thane Court 651 Criminal No Other Case filed by Promoter for relevant S No 2009 Pending
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
2 Declaration about Commencement Certificate
3 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement