Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
1 |
HDIL PARADISE CITY SECTOR 1,PALGHAR
|
BUILDING NO 2
|
|
0
|
1
|
0
|
5
|
1 |
0 |
13 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
COMMERCIAL |
17.82 |
3 |
3 |
2 |
COMMERCIAL |
18.17 |
2 |
2 |
3 |
COMMERCIAL |
19.96 |
1 |
1 |
4 |
COMMERCIAL |
25.24 |
1 |
1 |
5 |
RESIDENTIAL |
41.99 |
10 |
9 |
6 |
RESIDENTIAL |
41.26 |
3 |
3 |
7 |
RESIDENTIAL |
41.46 |
3 |
3 |
8 |
RESIDENTIAL |
42.02 |
23 |
22 |
9 |
COMMERCIAL |
14.36 |
1 |
1 |
10 |
COMMERCIAL |
17.20 |
2 |
2 |
11 |
RESIDENTIAL |
29.86 |
1 |
0 |
12 |
COMMERCIAL |
16.46 |
1 |
1 |
13 |
COMMERCIAL |
12.77 |
2 |
2 |
14 |
COMMERCIAL |
14.42 |
1 |
1 |
15 |
COMMERCIAL |
14.51 |
2 |
2 |
16 |
COMMERCIAL |
14.79 |
1 |
1 |
17 |
COMMERCIAL |
15.38 |
2 |
2 |
18 |
COMMERCIAL |
15.95 |
2 |
2 |
19 |
COMMERCIAL |
16.25 |
2 |
2 |
20 |
COMMERCIAL |
16.69 |
1 |
1 |
21 |
RESIDENTIAL |
36.47 |
1 |
1 |
22 |
RESIDENTIAL |
35.46 |
3 |
3 |
23 |
RESIDENTIAL |
39.95 |
13 |
11 |
24 |
RESIDENTIAL |
42.70 |
1 |
1 |
25 |
RESIDENTIAL |
44.25 |
2 |
2 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
2 |
HDIL PARADISE CITY SECTOR 1,PALGHAR
|
BUILDING NO 3
|
|
0
|
1
|
0
|
5
|
1 |
0 |
13 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
COMMERCIAL |
12.79 |
1 |
1 |
2 |
COMMERCIAL |
13.98 |
1 |
1 |
3 |
COMMERCIAL |
14.42 |
1 |
1 |
4 |
COMMERCIAL |
14.51 |
2 |
2 |
5 |
COMMERCIAL |
15.47 |
1 |
1 |
6 |
RESIDENTIAL |
35.46 |
3 |
2 |
7 |
RESIDENTIAL |
39.95 |
13 |
13 |
8 |
RESIDENTIAL |
42.70 |
1 |
1 |
9 |
COMMERCIAL |
17.20 |
2 |
2 |
10 |
COMMERCIAL |
17.35 |
1 |
1 |
11 |
RESIDENTIAL |
44.25 |
2 |
2 |
12 |
RESIDENTIAL |
42.02 |
23 |
19 |
13 |
RESIDENTIAL |
41.99 |
10 |
9 |
14 |
RESIDENTIAL |
41.26 |
3 |
3 |
15 |
RESIDENTIAL |
41.46 |
3 |
3 |
16 |
RESIDENTIAL |
36.47 |
1 |
1 |
17 |
COMMERCIAL |
10.75 |
1 |
1 |
18 |
COMMERCIAL |
17.82 |
2 |
2 |
19 |
COMMERCIAL |
18.17 |
1 |
1 |
20 |
COMMERCIAL |
22.25 |
1 |
1 |
21 |
RESIDENTIAL |
29.86 |
1 |
1 |
22 |
COMMERCIAL |
12.77 |
2 |
2 |
23 |
COMMERCIAL |
14.64 |
1 |
1 |
24 |
COMMERCIAL |
15.38 |
2 |
2 |
25 |
COMMERCIAL |
15.56 |
1 |
1 |
26 |
COMMERCIAL |
15.95 |
2 |
2 |
27 |
COMMERCIAL |
16.25 |
2 |
2 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
3 |
HDIL PARADISE CITY SECTOR 1,PALGHAR
|
BUILDING NO 4
|
|
0
|
1
|
0
|
5
|
1 |
0 |
24 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDENTIAL |
37.52 |
1 |
1 |
2 |
RESIDENTIAL |
45.07 |
1 |
1 |
3 |
RESIDENTIAL |
45.45 |
2 |
2 |
4 |
RESIDENTIAL |
45.47 |
1 |
1 |
5 |
RESIDENTIAL |
30.86 |
4 |
4 |
6 |
RESIDENTIAL |
40.64 |
4 |
4 |
7 |
RESIDENTIAL |
39.36 |
8 |
6 |
8 |
RESIDENTIAL |
39.62 |
8 |
8 |
9 |
RESIDENTIAL |
39.95 |
28 |
26 |
10 |
RESIDENTIAL |
35.46 |
10 |
10 |
11 |
RESIDNETIAL |
41.43 |
10 |
9 |
12 |
RESIDENTIAL |
41.99 |
18 |
17 |
13 |
RESIDENTIAL |
42.02 |
27 |
26 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
4 |
HDIL PARADISE CITY SECTOR 1,PALGHAR
|
BUILDING NO 9
|
|
0
|
1
|
0
|
5
|
1 |
0 |
16 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDENTIAL |
39.95 |
19 |
17 |
2 |
RESIDENTIAL |
42.02 |
27 |
25 |
3 |
RESIDENTIAL |
35.46 |
5 |
5 |
4 |
RESIDENTIAL |
41.43 |
5 |
3 |
5 |
RESIDENTIAL |
41.99 |
9 |
9 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
80
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
80
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
95
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
20
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
67.5
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
5 |
HDIL PARADISE CITY SECTOR 1,PALGHAR
|
BUILDING NO 10
|
|
0
|
1
|
0
|
5
|
1 |
0 |
16 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDNETIAL |
39.95 |
19 |
16 |
2 |
RESIDENTIAL |
42.02 |
27 |
26 |
3 |
RESIDENTIAL |
35.46 |
5 |
4 |
4 |
RESIDENTIAL |
41.43 |
5 |
3 |
5 |
RESIDENTIAL |
41.99 |
9 |
8 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
50
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
80
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
50
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
5
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
58.5
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
6 |
HDIL PARADISE CITY SECTOR 1,PALGHAR
|
BUILDING NO 11
|
|
0
|
1
|
0
|
5
|
1 |
0 |
38 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
COMMERCIAL |
16.46 |
2 |
0 |
2 |
COMMERCIAL |
16.69 |
2 |
0 |
3 |
COMMERCIAL |
17.20 |
1 |
0 |
4 |
COMMERCIAL |
17.82 |
3 |
0 |
5 |
COMMERCIAL |
18.17 |
3 |
0 |
6 |
COMMERCIAL |
19.96 |
2 |
1 |
7 |
COMMERCIAL |
25.24 |
2 |
1 |
8 |
RESIDENTIAL |
29.86 |
2 |
2 |
9 |
RESIDENTIAL |
41.99 |
26 |
23 |
10 |
RESIDENTIAL |
41.26 |
3 |
3 |
11 |
COMMERCIAL |
12.77 |
1 |
1 |
12 |
COMMERCIAL |
14.36 |
2 |
1 |
13 |
COMMERCIAL |
14.51 |
1 |
0 |
14 |
COMMERCIAL |
14.79 |
2 |
1 |
15 |
COMMERCIAL |
15.38 |
1 |
0 |
16 |
COMMERCIAL |
15.95 |
1 |
0 |
17 |
COMMERCIAL |
16.25 |
1 |
1 |
18 |
RESIDENTIAL |
36.47 |
2 |
2 |
19 |
RESIDENTIAL |
35.46 |
11 |
10 |
20 |
RESIDENTIAL |
39.95 |
36 |
32 |
21 |
RESIDENTIAL |
44.25 |
1 |
1 |
22 |
RESIDENTIAL |
42.02 |
38 |
37 |
23 |
RESIDENTIAL |
42.70 |
2 |
1 |
24 |
RESIDENTIAL |
41.43 |
5 |
4 |
25 |
RESIDENTIAL |
41.46 |
6 |
6 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
7 |
HDIL PARADISE CITY SECTOR 1,PALGHAR
|
BUILDING NO 12
|
|
0
|
1
|
0
|
5
|
1 |
0 |
9 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
COMMERCIAL |
10.75 |
2 |
0 |
2 |
COMMERCIAL |
12.77 |
6 |
2 |
3 |
COMMERCIAL |
14.36 |
6 |
3 |
4 |
COMMERCIAL |
14.46 |
4 |
3 |
5 |
COMMERCIAL |
14.95 |
6 |
1 |
6 |
RESIDENTIAL |
33.32 |
26 |
17 |
7 |
RESIDNETIAL |
44.56 |
6 |
6 |
8 |
RESIDENTIAL |
42.60 |
18 |
13 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
8 |
HDIL PARADISE CITY SECTOR 1,PALGHAR
|
BUILDING NO 13
|
|
0
|
1
|
0
|
5
|
1 |
0 |
9 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDENTIAL |
33.32 |
26 |
21 |
2 |
RESIDENTIAL |
42.60 |
30 |
24 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
9 |
HDIL PARADISE CITY SECTOR 1,PALGHAR
|
BUILDING NO 14
|
|
0
|
1
|
0
|
5
|
1 |
0 |
9 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDENTIAL |
33.32 |
26 |
21 |
2 |
RESIDENTIAL |
42.60 |
30 |
24 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
10 |
HDIL PARADISE CITY SECTOR 1,PALGHAR
|
BUILDING NO 15
|
|
0
|
1
|
0
|
5
|
1 |
0 |
9 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDENTIAL |
33.32 |
26 |
21 |
2 |
RESSIDENTIAL |
42.60 |
30 |
25 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
11 |
HDIL PARADISE CITY SECTOR 1,PALGHAR
|
BUILDING NO 16
|
|
0
|
1
|
0
|
5
|
1 |
0 |
9 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDENTIAL |
33.32 |
26 |
12 |
2 |
RESIDENTIAL |
42.60 |
30 |
22 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
95
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
50
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
80
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
82.5
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
12 |
HDIL PARADISE CITY SECTOR 1,PALGHAR
|
BUILDING NO 17
|
|
0
|
1
|
0
|
5
|
1 |
0 |
9 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDENTIAL |
33.32 |
26 |
14 |
2 |
RESIDENTIAL |
42.60 |
30 |
28 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
98
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
50
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
80
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
60
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
78.8
|
|