Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
1 |
Three Jewels
|
Moonstone-I
|
30/06/2023
|
1
|
1
|
1
|
15
|
1 |
28 |
62 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2 ROOM HALL KITCHEN |
54.18 |
12 |
12 |
2 |
3 ROOM HALL KITCHEN |
66.15 |
14 |
14 |
3 |
2 ROOM HALL KITCHEN |
54.29 |
30 |
30 |
4 |
3 ROOM HALL KITCHEN |
66.17 |
16 |
16 |
5 |
2 ROOM HALL KITCHEN |
53.93 |
18 |
18 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
100
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
2 |
Three Jewels
|
Moonstone-J
|
30/06/2023
|
1
|
1
|
1
|
16
|
1 |
23 |
71 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2 ROOM HALL KITCHEN |
62.36 |
16 |
16 |
2 |
2 ROOM HALL KITCHEN |
59.28 |
15 |
15 |
3 |
2 ROOM HALL KITCHEN |
62.38 |
16 |
16 |
4 |
2 ROOM HALL KITCHEN |
58.71 |
32 |
32 |
5 |
2 ROOM HALL KITCHEN |
59.29 |
15 |
15 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
100
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
3 |
Three Jewels
|
Moonstone-K
|
30/06/2023
|
0
|
1
|
1
|
16
|
1 |
53 |
41 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2 ROOM HALL KITCHEN |
59.29 |
15 |
15 |
2 |
2 ROOM HALL KITCHEN |
62.38 |
16 |
15 |
3 |
2 ROOM HALL KITCHEN |
62.36 |
16 |
16 |
4 |
2 ROOM HALL KITCHEN |
58.71 |
32 |
30 |
5 |
2 ROOM HALL KITCHEN |
59.28 |
15 |
15 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
4 |
Three Jewels
|
Moonstone-L
|
30/06/2023
|
1
|
1
|
1
|
16
|
1 |
19 |
88 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK |
58.71 |
32 |
32 |
2 |
2BHK |
59.28 |
15 |
15 |
3 |
2BHK |
59.29 |
15 |
15 |
4 |
2BHK |
62.36 |
16 |
16 |
5 |
2BHK |
62.38 |
16 |
16 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
100
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
5 |
Three Jewels
|
Moonstone-M
|
30/06/2023
|
0
|
1
|
1
|
16
|
1 |
43 |
51 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2 ROOM HALL KITCHEN |
59.76 |
15 |
15 |
2 |
3 ROOM HALL KITCHEN |
83.95 |
16 |
16 |
3 |
3 ROOM HALL KITCHEN |
84.03 |
16 |
15 |
4 |
2 ROOM HALL KITCHEN |
59.77 |
15 |
15 |
5 |
3 ROOM HALL KITCHEN |
83.38 |
32 |
32 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
6 |
Three Jewels
|
Moonstone-N
|
31/03/2023
|
0
|
1
|
1
|
15
|
1 |
37 |
81 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2 ROOM HALL KITCHEN |
53.14 |
28 |
27 |
2 |
2 ROOM HALL KITCHEN |
53.15 |
32 |
32 |
3 |
2 ROOM HALL KITCHEN |
59.77 |
58 |
58 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
7 |
Three Jewels
|
Moonstone-O
|
30/06/2023
|
0
|
1
|
1
|
15
|
1 |
34 |
142 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1 ROOM HALL KITCHEN |
37.58 |
82 |
82 |
2 |
1 ROOM HALL KITCHEN |
37.37 |
94 |
94 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|