MahaRERA Application

General Information

Other Than Individual

Organization

RAGHVENDRA CONSTRUCTION COMPANY PVT LTD
Company
NA
Do you have any Past Experience ?
No

Address Details

522, 5TH FLOOR,
THE SUMMIT BUSINESS BAY,
ANDHERI KURLA ROAD
ANDHERI (EAST)
OFF WESTERN EXPRESS HIGHWAY
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400069

Organization Contact Details

02226834133

Past Experience Details

Member Information

Member Name Designation Photo
SUDEEP KUMAR SAHA Authorized Signatory View Photo

Project

AVANT HILLWAY
On-Going Project
31/12/2022
30/12/2024
No
Residential
No
CTS NO 610 A/1B/1
CTS NO 610A -1C
CTS NO 610A-1B -2 and 610A-1A-2A
CTS NO 610A-1-A-1-1
CTS NO 610A-1-1-A-1
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
m
m
400063
4969
3
3
0
745.35

FSI Details

2863.31
11031.09
13894.40

Bank Details

HDFC Bank
HDFC0000543

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 86 23 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 SHALL BE DONE PRIOR TO OC
Water Conservation, Rain water Harvesting : YES 0 SHALL BE DONE PRIOR TO OC
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 SHALL BE DONE PRIOR TO OC
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 SHALL BE DONE PRIOR TO OC
Aggregate area of recreational Open Space : YES 0 SHALL BE DONE PRIOR TO OC
Open Parking : YES 0 SHALL BE DONE PRIOR TO OC
Water Supply : YES 0 SHALL BE DONE PRIOR TO OC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 SHALL BE DONE PRIOR TO OC
Storm Water Drains : YES 0 SHALL BE DONE PRIOR TO OC
Landscaping & Tree Planting : YES 0 SHALL BE DONE PRIOR TO OC
Street Lighting : YES 0 SHALL BE DONE PRIOR TO OC
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 SHALL BE DONE PRIOR TO OC
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 AVANT HILLWAY BUILDING - A, ROYAL 30/06/2024 0 1 0 23 1 13 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 120.77 1 0
2 Shop 125.41 1 0
3 2BHK 71.25 22 18
4 2BHK 65.96 44 36
5 2BHK 62.24 22 15
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 90
5 X number of Slabs of Super Structure 30
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 20
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 5
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 37.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 AVANT HILLWAY BUILDING - B, ELITE 30/06/2024 0 1 0 23 0 15 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 26.01 44 39
2 1BHK 32.14 22 21
3 Shop 23.22 2 0
4 Shop 27.87 1 0
5 Shop 37.16 2 0
6 2BHK 53.51 22 13
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 80
5 X number of Slabs of Super Structure 25
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 7
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 20
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 33.2
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 AVANT HILLWAY BUILDING - C, IMPERIAL 30/06/2024 0 1 0 24 1 12 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 68.77 17 0
2 2BHK 70.26 38 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
UNIQ CONSULTANCY A51800004479 Real Estate Agent
Chiraj Interior and Construction NA Contractor
ASC Associated Consultants NA Engineer
M/s Daddy & Associates NA Architect
Sudheendra &Company NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
11 Building Plan Approval (IOD)
12 Building Plan Approval (IOD)
13 Building Plan Approval (IOD)
14 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
5 Commencement Certificates / NA Order for plotted development
6 Commencement Certificates / NA Order for plotted development
7 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
1 Other – Finance
1 Other – Technical
2 Other – Technical
3 Other – Technical
4 Other – Technical
5 Other – Technical
6 Other – Technical
7 Other – Technical
8 Other – Technical
9 Other – Technical
10 Other – Technical
11 Other – Technical
12 Other – Technical
13 Other – Technical
14 Other – Technical
15 Other – Technical
16 Other – Technical
17 Other – Technical
18 Other – Technical
19 Other – Technical
20 Other – Technical
21 Other – Technical
22 Other – Technical
23 Other – Technical
24 Other – Technical
25 Other – Technical
26 Other – Technical
27 Other – Technical
28 Other – Technical
29 Other – Technical
30 Other – Technical
31 Other – Technical
32 Other – Technical
33 Other – Technical
34 Other – Technical
35 Other – Technical
36 Other – Technical
37 Other – Technical
38 Other – Technical
39 Other – Technical
40 Other – Technical
41 Other – Technical
42 Other – Technical
43 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000196403 Janardan Ramlal Yadav View Orders
2 CC006000000196419 DROPADI SURESH PRAJAPATI View Orders
3 CC006000000196657 RAJESHMOHAN HARISHARAN MISRA View Orders
4 CC006000000197684 ANIL UPADHYAY View Orders