MahaRERA Application

General Information

Other Than Individual

Organization

KALPANA STRUCT-CON INFRA LLP
Partnership
NA
Do you have any Past Experience ?
No

Address Details

1006-1008
CYBER ONE
PLOT NO 4&6 SECTOR 30A
VASHI
NEAR CIDCO EXHIBITION CENTRE
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400703

Organization Contact Details

02227814848
WWW.KSCPL.COM

Past Experience Details

Member Information

Member Name Designation Photo
CHATURBHAI THUMAR Partner View Photo
PATHIK THUMAR Authorized Signatory View Photo
JAGDISH THUMAR Partner View Photo
HARSHAD THUMAR Partner View Photo
AJIT THUMAR Partner View Photo
RAMESH NAKRANI Partner View Photo
CHIMAN NAKRANI Partner View Photo
JAYANTILAL NAKRANI Partner View Photo

Project

NESTOR
New Project
30/12/2022
31/12/2024
No
Others
No
26
PLOT NO 25
PLOT NO 27
20 MTRS WIDE ROAD
H T CORRIDOR
MAHARASHTRA
Konkan
Raigarh
Uran
Bokadvira
PLOT NO 26 SECTOR 47
DRONAGIRI
400702
3149.93
2
2
0
0

FSI Details

4719.38
0
4719.38

Bank Details

KOTAK MAHINDRA BANK LTD
KKBK0000671

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 105 54 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 LATER SCOPE OF WORK
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 LATER SCOPE OF WORK
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 LATER SCOPE OF WORK
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 95 later scope of work
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 90 LATER STAGE IN WORK
Storm Water Drains : YES 100 LATER STAGE IN WORK
Landscaping & Tree Planting : YES 85 LATER SCOPE OF WORK
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 NESTOR A WING 31/12/2021 0 1 3 17 1 0 52
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 COMMERCIAL 41.34 1 0
2 COMMERCIAL 35.04 1 0
3 1BHK 29.05 13 9
4 2 BHK 40.84 3 3
5 COMMERCIAL 41.61 4 4
6 2BHK 38.32 3 2
7 1BHK 29.21 13 10
8 2BHK 36.46 13 10
9 2BHK 35.69 13 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 85
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 85
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 85
11 Overall Percentage of Completion of the work done For the entire Building /Wing 95.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 NESTOR B WING 31/12/2021 0 1 3 17 1 0 53
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 COMMERCIAL 41.61 4 1
2 2 BHK 36.37 7 3
3 COMMERCIAL 35.04 1 1
4 COMMERCIAL 41.34 1 0
5 2 BHK 40.84 3 2
6 2 BHK 38.32 3 2
7 1 BHK 29.21 13 3
8 1BHK 29.05 13 5
9 2BHK 35.69 13 6
10 2 BHK 36.46 6 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 85
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 85
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 85
11 Overall Percentage of Completion of the work done For the entire Building /Wing 95.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SOYUZ TALIB ARCHITECTS PVT LTD NA Architect
S R CONSULTANTS NA Engineer
H V DESIGN STUDIO NA Other Professional

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
2 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement