MahaRERA Application

General Information

Other Than Individual

Organization

AMAR BUILDERS AND DEVELOPERS
Partnership
NA
Do you have any Past Experience ?
No

Address Details

CTS NO. 893
AMAR HOUSE
LANE 1, OFF BHANDARKAR ROAD
DECCAN GYMKHANA
NEAR GOODLUCK CHOWK
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411004

Organization Contact Details

02025664411
www.amarbuilders.com

Past Experience Details

Member Information

Member Name Designation Photo
AMAR HARISHCHANDRA MANJREKAR Partner View Photo
HRISHIKESH AMAR MANJREKAR Partner View Photo
HRISHIKESH AMAR MANJREKAR Authorized Signatory View Photo

Project

AMAR SADANAND TECH PARK
New Project
30/12/2020
No
Commercial
Yes
SURVEY NO.105/3, PLOT NO 3
P-7 RESERVATION
SURVEY NO 105 HISSA NO 3 PLOT NO 2
30 MTR ROAD
SURVEY NO 105 HISSA NO 3 PART
MAHARASHTRA
Pune
Pune
Haveli
Baner
BANER ROAD
BANER
411045
4489.38
1
1
0
0

FSI Details

13382.17
85
13467.17

Bank Details

THE SARASWAT CO OP BANK LTD
SRCB0000035

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
AMAR SADANAND TECH PARK INDIRA SADANAND SHETTY Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 252 252 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Drive ways in paver blocks
Water Conservation, Rain water Harvesting : YES 100 No of Recharge Pits = 3
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 As per Fire NOC awarded
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Meter room & transformer room (No sub-station)
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 100 Piping network from PMC supply to storage tank
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Sewage network line through STP
Storm Water Drains : YES 100 Storm Water Line Network till municipal network
Landscaping & Tree Planting : YES 100 As per Consultant drawing
Street Lighting : YES 100 Only on internal drive ways
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 Through STP connected to municipal line
Solid Waste Management And Disposal : YES 100 OWC provided

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 AMAR SADANAND TECH PARK BUILDING A 30/06/2020 2 0 0 15 1 0 252
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP TYPE 1 64.60 2 2
2 SHOP TYPE 2 64.76 2 2
3 SHOP TYPE 3 92.88 4 4
4 OFFICE TYPE 2 1088.37 2 2
5 OFFICE TYPE 3 1111.32 8 8
6 OFFICE TYPE 1 1088.19 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
S J Contracts Pvt Ltd NA Contractor
M. B. Chaudhari & Associates NA Architect
JW Consultants LLP NA Engineer
JONES LANG LASALLE PROPERTY CONSULTANTS (INDIA) PRIVATE LIMITED A51900000251 Real Estate Agent
Elevare Consulting LLP A52100005962 Real Estate Agent
GAURAV SURESH NAHTA A52100003487 Real Estate Agent
GAURAV GADA A52700014401 Real Estate Agent
GAURAVSINGH BALVINDERSINGH OBEROI A52100009641 Real Estate Agent
Suresh Thakchand Ghodekar NA Engineer
P S Athavale & Co NA Chartered Accountant
Apte & Co NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
2 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement