MahaRERA Application

General Information

Other Than Individual

Organization

M/S Chintamani Land and Housing LLP
Partnership
NA
Do you have any Past Experience ?
No

Address Details

60/62
60/62
Mirza Street
Mirza Street
Mumbai
MAHARASHTRA
Konkan
Mumbai City
Mumbai City
Mumbai City
400003

Organization Contact Details

02223445348
www.chintamaniestates.com

Past Experience Details

Member Information

Member Name Designation Photo
Rajiv Anant Shah Partner View Photo
Kumar Girdharlal Shah Partner View Photo
Kumar Girdharlal Shah Authorized Signatory View Photo
Anant Girdharlal Shah Partner View Photo

Project

ARYAVRAT PROJECT
New Project
30/12/2023
31/12/2024
Yes
Residential
No
FP NO 240 TPS IV MAHIM DIVISION
FP NO 239 TPS IV MAHIM DIVISION
FP NO 242 TPS IV MAHIM DIVISION
FP NO 227 TPS IV MAHIM DIVISION
SK BOLE ROAD
MAHARASHTRA
Konkan
Mumbai City
Ward GNorth
GNorth-400028
SK Bole road
DADAR WEST
400028
3145.51
2
2
0
255.61

FSI Details

0
14188.4
14188.40

Bank Details

STATE BANK OF INDIA
SBIN0063846

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 122 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 Building Work to Start
Water Conservation, Rain water Harvesting : YES 0 Building Work to Start
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 Building Work to Start
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Building Work to Start
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 0 Building Work to Start
Water Supply : YES 0 Building Work to Start
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 Building Work to Start
Storm Water Drains : YES 0 Building Work to Start
Landscaping & Tree Planting : YES 0 Building Work to Start
Street Lighting : YES 0 Building Work to Start
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : YES 0 Building Work to Start

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 ARYAVRAT PROJECT Wing B 31/12/2022 2 0 0 22 0 04 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 60.2 2 0
2 1BHK 20.25 1 0
3 1BHK 34.37 1 0
4 1BHK 43.99 1 0
5 1BHK 43.77 1 0
6 1BHK 34.51 2 1
7 1BHK 42.66 3 0
8 1BHK 41.81 7 7
9 2BHK 51.1 4 4
10 2BHK 46.45 12 12
11 2BHK 56.67 18 18
12 2BHK 64.38 1 1
13 2BHK 60.39 1 1
14 1BHK 37.16 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 ARYAVRAT PROJECT Wing A 31/12/2022 2 0 0 15 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 70.14 1 0
2 3BHK 71.53 1 0
3 3BHK 108.5 10 0
4 3BHK 109.47 7 0
5 4BHK 149.35 9 0
6 2BHK 59.23 1 0
7 2BHK 85.88 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 70
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 65
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 43.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
IRANI ARCHIRECTS NA Architect
Chandrakant Pandeshwar NA Engineer
D J Shah and Associates NA Chartered Accountant
ENCOM INFRASTRUCTURE NA Contractor
ENCOM CONSTEC NA Contractor
A K CONSTRUCTION NA Contractor
MATRIX RECON PRIVATE LIMITED A51900004184 Real Estate Agent
ECO MEP CONSULTANTS NA Other Professional

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
ARYAVRAT PROJECT Bombay High Court 2562 Civil No Suit NA 2019 on board
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
5 Building Plan Approval / NA Order for plotted development
6 Building Plan Approval / NA Order for plotted development
7 Building Plan Approval / NA Order for plotted development
8 Building Plan Approval / NA Order for plotted development
9 Building Plan Approval / NA Order for plotted development
10 Building Plan Approval / NA Order for plotted development
11 Building Plan Approval / NA Order for plotted development
12 Building Plan Approval / NA Order for plotted development
13 Building Plan Approval / NA Order for plotted development
14 Building Plan Approval / NA Order for plotted development
15 Building Plan Approval / NA Order for plotted development
16 Building Plan Approval / NA Order for plotted development
17 Building Plan Approval / NA Order for plotted development
18 Building Plan Approval / NA Order for plotted development
19 Building Plan Approval / NA Order for plotted development
20 Building Plan Approval / NA Order for plotted development
21 Building Plan Approval / NA Order for plotted development
22 Building Plan Approval / NA Order for plotted development
23 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
10 Architect’s Certificate of Percentage of Completion of Work (Form 1)
11 Architect’s Certificate of Percentage of Completion of Work (Form 1)
12 Architect’s Certificate of Percentage of Completion of Work (Form 1)
13 Architect’s Certificate of Percentage of Completion of Work (Form 1)
14 Architect’s Certificate of Percentage of Completion of Work (Form 1)
15 Architect’s Certificate of Percentage of Completion of Work (Form 1)
16 Architect’s Certificate of Percentage of Completion of Work (Form 1)
17 Architect’s Certificate of Percentage of Completion of Work (Form 1)
18 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
8 Engineer’s Certificate on Cost Incurred on Project (Form 2)
9 Engineer’s Certificate on Cost Incurred on Project (Form 2)
10 Engineer’s Certificate on Cost Incurred on Project (Form 2)
11 Engineer’s Certificate on Cost Incurred on Project (Form 2)
12 Engineer’s Certificate on Cost Incurred on Project (Form 2)
13 Engineer’s Certificate on Cost Incurred on Project (Form 2)
14 Engineer’s Certificate on Cost Incurred on Project (Form 2)
15 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
5 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
3 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
2 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement