MahaRERA Application

General Information

Other Than Individual

Organization

Acme Housing India Private Limited
Company
NA
Do you have any Past Experience ?
Yes

Address Details

5th Floor
10, Solitaire Corporate Park
Guru Hargovindji Road
Chakala, Andheri East
Opposite The Mirador Hotel
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400093

Organization Contact Details

02267570000
www.acmehousing.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Oakwood and AshwoodResidentialNA8096.7Thane MaharashtraSurvey 46, Hissa 2/1, Gat 61/1/1,2,3,4 and Hissa 5, Gat 61/2/1,2,323822013-12-312014-12-12

Member Information

Member Name Designation Photo
Chetankumar Madival Authorized Signatory View Photo
Munish Pravin Doshi Chairperson View Photo
Nitin Bavisi Authorized Signatory View Photo

Project

Lodha Bellavista - Wing B2
New Project
30/12/2025
31/07/2027
Yes
Residential
Yes
Gat No.61/1/1, Gat No.61/1/2,3,4, Gat No. 61/2/1,2,3
19 13 54 44 N 72 58 17 14 E
19 13 54 48 N 72 58 16 01 E
19 13 54 81 N 72 58 16 47 E
19 13 54 14 N 72 58 16 77 E
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
Khewra Circle Marg
Off. Ghodbunder Road, Thane
400607
570.42
1
1
0
0

FSI Details

14136.22
15682.17
29818.39

Bank Details

HDFC BANK
HDFC0000114

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Lodha Bellavista - Wing B2 Acme Housing India Private Limited Company Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 242 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 Common to all users of larger layout
Internal Roads & Footpaths : YES 0 Common to all users of larger layout
Internal Roads & Footpaths : YES 0 Common to all users of larger layout
Water Conservation, Rain water Harvesting : YES 0 Common to all users of larger layout
Energy management : YES 0 Common to all users of larger layout
Fire Protection And Fire Safety Requirements : YES 0 Common to all users of larger layout
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Common to all users of larger layout
2 Level Common Podium : YES 0 Common to all users of larger layout
Amenities : YES 0 Common to all users of larger layout
Common External Podium : YES 0 Common to all users of larger layout
Common Stilt : YES 0 Common to all users of larger layout
Aggregate area of recreational Open Space : YES 0 Common to all users of larger layout
Open Parking : NO 0 NA
Water Supply : YES 0 Common to all users of larger layout
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 Common to all users of larger layout
Storm Water Drains : YES 0 Common to all users of larger layout
Landscaping & Tree Planting : YES 0 Common to all users of larger layout
Street Lighting : YES 0 Common to all users of larger layout
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 Common to all users of larger layout
Solid Waste Management And Disposal : YES 0 Common to all users of larger layout

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Lodha Bellavista - Wing B2 Wing B2 30/12/2025 2 1 2 38 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 64.1 66 1
2 2BHK 65.31 27 1
3 3BHK 127.46 2 0
4 3BHK 130.43 1 0
5 4BHK 135.64 34 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 42
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 14.2

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Lodha Bellavista - Wing B2 High Court Bombay 7949 of 2015 Civil No Writ Petition NA 2015 Pending
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
5 Building Plan Approval / NA Order for plotted development
6 Building Plan Approval / NA Order for plotted development
7 Building Plan Approval / NA Order for plotted development
8 Building Plan Approval / NA Order for plotted development
9 Building Plan Approval / NA Order for plotted development
10 Building Plan Approval / NA Order for plotted development
11 Building Plan Approval / NA Order for plotted development
12 Building Plan Approval / NA Order for plotted development
13 Building Plan Approval / NA Order for plotted development
14 Building Plan Approval / NA Order for plotted development
15 Building Plan Approval / NA Order for plotted development
16 Building Plan Approval / NA Order for plotted development
17 Building Plan Approval / NA Order for plotted development
18 Building Plan Approval / NA Order for plotted development
19 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
4 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
2 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
4 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement