MahaRERA Application

General Information

Other Than Individual

Organization

Astrum Developments Private Limited
Company
NA
Do you have any Past Experience ?
No

Address Details

101
Kalpataru Synergy
Vakola
Santacruz East
Opp. Grand Hyatt
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
400055

Organization Contact Details

02230645000
www.kalpataru.com

Past Experience Details

Member Information

Member Name Designation Photo
Amit Shah Authorized Signatory View Photo
Jayant Oswal Authorized Signatory View Photo

Project

Kalpataru Jade Skyline
New Project
31/12/2026
No
Residential
Yes
S No 12 Part Baner Tal Haveli District Pune
Remaining portion of S No 12
Amenity Space
24 meter wide DP road
Remaining portion of S No 12
MAHARASHTRA
Pune
Pune
Haveli
Baner
Off Pan Card Road
Baner
411045
1771.97
1
1
0
0

FSI Details

39337.52
662.48
40000.00

Bank Details

Axis Bank Ltd
UTIB0000004

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Kalpataru Jade Skyline Dr. Babul Rustumkhan Pathan Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 2136 25 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 To be done before completion of Project
Internal Roads & Footpaths : YES 0 To be done before completion of Project
Internal Roads & Footpaths : YES 0 To be done before completion of Project
Water Conservation, Rain water Harvesting : YES 0 To be done before completion of Project
Energy management : YES 0 To be done before completion of Project
Fire Protection And Fire Safety Requirements : YES 0 To be done before completion of Project
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Electrical Meter Room and Sub station only
5 Nos. of Common Podiums : YES 0 Common development as per AFS
Club House, Swimming pool & other Recreational areas : YES 0 Common amenities as per AFS
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 0 To be done before completion of Project
Water Supply : YES 0 To be done before completion of Project
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 STP only
Storm Water Drains : YES 0 To be done before completion of Project
Landscaping & Tree Planting : YES 0 To be done before completion of Project
Street Lighting : YES 0 To be done before completion of Project
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 To be done before completion of Project
Solid Waste Management And Disposal : YES 00 To be done before completion of Project

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Kalpataru Jade Skyline Jade Skyline- Wing A1, A2, A3, A4 and A5 31/03/2026 3 1 5 21 0 591 2136
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 779.95 28 12
2 2BHK 4373.22 63 41
3 3BHK 17824.38 189 62
4 Studio Co Promoter 527.76 18 0
5 Studio 1583.28 54 0
6 4BHKCoPromoter 110.98 1 1
7 4BHK 332.94 3 3
8 3BHKCoPromoter 6881.39 73 10
9 2BHKCoPromoter 1780.6 26 14
10 1 BHK Co Promoter 278.56 10 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 99
2 X number of Basement(s) and Plinth 92
3 X number of Podiums 71
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 26.2

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
GAURAV SURESH NAHTA A52100003487 Real Estate Agent
VIKRAM PRAKASH MULAY A52100028509 Real Estate Agent
LAKEDGE TECHNOLOGIES PRIVATE LIMITED A52100026118 Real Estate Agent
MADAN NARSING JADHAV A52100024737 Real Estate Agent
OMKAR SANTOSH MULE A52100026654 Real Estate Agent
amoya consulting LLP A52100017509 Real Estate Agent
PRIME ASSETS REALTY PRIVATE LIMITED A52100024992 Real Estate Agent
SPACEINDIA NEST PRIVATE LIMITED A52100002248 Real Estate Agent
Trespect India Private Ltd A51900020838 Real Estate Agent
PROPBUYING REALTORS PVT LTD A52100000476 Real Estate Agent
Swapnil Potdar (Architect Certificate-Form 1 and Form 4) NA Architect
Vishwas Kadam ( Engineer Certificate-Form 2) NA Engineer
C R Mohnot & Co ( CA Certificate-Form 3) NA Chartered Accountant
J+W Consultants (Structural Consultant) NA Other Professional
Avinash Nawathe Architects (Liaison Architect) NA Other Professional
S N Joshi (MEP Consultant) NA Other Professional

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
2 Declaration about Commencement Certificate
3 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 CERSAI details
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement