Common areas And Facilities, Amenities |
Available |
Percent |
Details |
Internal Roads & Footpaths :
|
NO
|
0
|
NA
|
Water Conservation, Rain water Harvesting :
|
YES
|
100
|
complete
|
Energy management :
|
NO
|
0
|
NA
|
Fire Protection And Fire Safety
Requirements :
|
YES
|
100
|
complete
|
Electrical Meter Room, Sub-Station, Receiving Station :
|
YES
|
100
|
complete
|
CHILDREN`S PLAY AREA WITH PLAYING EQUIPMENT :
|
YES
|
50
|
Work In Progress
|
CLUB HOUSE :
|
YES
|
0
|
for whole project & to be handed over to apex body
|
E Charging Car Point :
|
YES
|
0
|
Work In Progress
|
GYMNASIUM WITH FITNESS EQUIPMENT TO BE PART OF THE CLUB HOUSE :
|
YES
|
50
|
RCC Complete. Internal finishing in progress
|
INDOOR GAMES ZONE with games like table tennis,chess & it will be a part of CLUB HOUSE. :
|
YES
|
75
|
RCC Complete. Internal finishing in progress
|
JOGGING and WALKING TRACK :
|
YES
|
0
|
for whole project & to be handed over to apex body
|
KIDS POOL of 20 feet x 12 feet :
|
YES
|
75
|
RCC Complete. Internal finishing in progress
|
LAWN :
|
YES
|
75
|
In Progress
|
MEDITATION & TRANQUILITY GARDEN :
|
YES
|
75
|
In progress
|
Mini Open Amphitheatre :
|
YES
|
0
|
To be complete in phase II
|
MULTIPURPOSE COURT :
|
YES
|
0
|
for whole project & to be handed over to apex body
|
OPEN JACUZZI :
|
YES
|
75
|
RCC Complete. Internal finishing in progress
|
OUTDOOR CHESS BOARD :
|
YES
|
0
|
To be complete in phase ii
|
POOL DECK is provided along the swimming pool :
|
YES
|
0
|
for whole project & to be handed over to apex body
|
SEATING AREAS FORMING PART OF THE LANDSCAPE :
|
YES
|
100
|
RCC Complete. Internal finishing in progress
|
SENIOR CITIZEN GARDEN :
|
YES
|
0
|
for whole project & to be handed over to apex body
|
SHADE SHELTER :
|
YES
|
0
|
for whole project & to be handed over to apex body
|
SNOOKER TABLE PART OF THE CLUB HOUSE :
|
YES
|
0
|
for whole project & to be handed over to apex body
|
SQUASH COURT of size 9m x 6m will be in Club House :
|
YES
|
75
|
RCC Complete. Internal finishing in progress
|
SWIMMING POOL of size 25m x 9m :
|
YES
|
75
|
RCC Complete. Internal finishing in progress
|
SWINGING CORNER :
|
YES
|
0
|
for whole project & to be handed over to apex body
|
TRELLIS ON PERGOLAS ABOVE DECK :
|
YES
|
100
|
COMPLETED
|
WATER FEATURE PART OF LANDSCAPE :
|
YES
|
0
|
To be complete in phase II
|
Aggregate area of recreational Open Space :
|
YES
|
50
|
Work In Progress
|
Open Parking :
|
NO
|
0
|
NA
|
Water Supply :
|
YES
|
95
|
External Connection Balance
|
Sewerage (Chamber, Lines, Septic Tank , STP) :
|
YES
|
95
|
STP Complete. Connection pending.
|
Storm Water Drains :
|
YES
|
100
|
complete
|
Landscaping & Tree Planting :
|
YES
|
60
|
Work in progress
|
Street Lighting :
|
NO
|
0
|
NA
|
Community Buildings :
|
NO
|
0
|
NA
|
Treatment And Disposal Of Sewage And Sullage Water :
|
YES
|
95
|
Only Connection Balance.
|
Solid Waste Management And Disposal :
|
YES
|
95
|
Only Connection Balance.
|