MahaRERA Application

General Information

Other Than Individual

Organization

CHARMS GLOBAL
Partnership
NA
Do you have any Past Experience ?
No

Address Details

A/501
GALLERIA SHOPPING CENTER
HIRANANDANI GARDENS
POWAI
POWAI
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
400076

Organization Contact Details

02225797935

Past Experience Details

Member Information

Member Name Designation Photo
RAJESH RAVJIBHAI PATEL Authorized Signatory View Photo
RAMESH RAVJIBHAI PATEL Partner View Photo
DHIRAJ GOVIND PATEL Partner View Photo
JOHN MATHEW Partner View Photo
NAVIN GOVIND PATEL Partner View Photo
MAHENDRA GOVIND PATEL Partner View Photo
BHARAT GOVIND VASANI Partner View Photo
SANJAY DHONDU BORGAONKAR Partner View Photo
DEVRAM DEVSHI PATEL Partner View Photo
RAVJIBHAI RAMJI PATEL Partner View Photo
SUDHEER RANGNATH SULE Partner View Photo
GEETA RATILAL PATEL Partner View Photo

Project

CHARMS GLOBAL CITY - TYPE- B1-MERLION
New Project
30/06/2024
No
Residential
No
GUT NO. 42, 43 PT
PANVELKAR GREEN CITY
JETWAN SOCIETY
PLAY GROUND RESERVATION 149
60 M PIPE LINE ROAD
MAHARASHTRA
Konkan
Thane
Ambarnath
Ambarnath(M Cl)
AMBERNATH
AMBERNATH
421501
5114.9
1
1
0
2341.63

FSI Details

6742.92
0
6742.92

Bank Details

KOTAK MAHINDRA BANK LTD
KKBK0001374

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 4 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 15 -
Water Conservation, Rain water Harvesting : YES 0 WORK NOT YET STARTED
Energy management : YES 0 WORK NOT YET STARTED
Fire Protection And Fire Safety Requirements : YES 0 WORK NOT YET STARTED
Electrical Meter Room, Sub-Station, Receiving Station : YES 8 WORK STARTED
Basement Parking adjoining B1 Bldg : YES 25 WORK STARTED
Aggregate area of recreational Open Space : YES 57 WORK STARTED
Open Parking : YES 0 WORK NOT YET STARTED
Water Supply : YES 0 WORK NOT YET STARTED
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 5 WORK STARTED
Storm Water Drains : YES 20 WORK STARTED
Landscaping & Tree Planting : YES 0 WORK NOT YET STARTED
Street Lighting : YES 0 WORK NOT YET STARTED
Community Buildings : YES 49 WORK STARTED
Treatment And Disposal Of Sewage And Sullage Water : YES 0 WORK NOT YET STARTED
Solid Waste Management And Disposal : YES 0 WORK NOT YET STARTED

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 CHARMS GLOBAL CITY - TYPE- B1-MERLION TYPE B1- MERLION 30/06/2023 0 1 0 13 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 34.15 24 5
2 1BHK 33.97 24 17
3 2BHK 39.79 48 41
4 1BHK 34.11 47 24
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 72
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 28
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

29
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
11 Overall Percentage of Completion of the work done For the entire Building /Wing 49.4

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
RRC VENTURES PRIVATE LIMITED NA Contractor
DMD ARCHITECT NA Architect
PATEL KULKARNI CONSULTANTS NA Engineer
KARTIK JAYANTILAL PATEL NA Chartered Accountant
AMIT MOHANDAS SIDHANI A51700003811 Real Estate Agent
Sunil Subhash Shelke A51700000840 Real Estate Agent
Bijendra Singh Sobran Singh Chouhan A51700021373 Real Estate Agent
GIRISH RAMCHAND VALECHA A51700025361 Real Estate Agent
KIRAN NARAYAN KOTIAN A51600009745 Real Estate Agent
CHANDRASHEKHAR NARSAPPA AVULU A51700021479 Real Estate Agent
MOTILAL DALBAHADUR PUN A51700022132 Real Estate Agent
ARUN KUMAR VEER BAHADUR SINGH A51700000202 Real Estate Agent
Mahesh Vitthal Sabale A51700025661 Real Estate Agent
nitin hotwani A51700010151 Real Estate Agent
PRASAD MOHAN PANICKER A51700026651 Real Estate Agent
Santosh Dagadu Dhivar A51700029402 Real Estate Agent
VELANI & POKAR NA Chartered Accountant
LEELA CONSTRUCTION NA Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement