MahaRERA Application

General Information

Other Than Individual

Organization

SHIVAM DEVELOPERS
Partnership
NA
Do you have any Past Experience ?
No

Address Details

218
Prem Baug
Sir Bhalchandra Road
Matunga C.R
Near Colony Nursing Home
MAHARASHTRA
Konkan
Mumbai City
Ward FNorth
Fnorth-400019
400019

Organization Contact Details

02224101336
www.shivamrealty.com

Past Experience Details

Member Information

Member Name Designation Photo
Girish Shamji Chheda Partner View Photo
Kunal Mahendra Chheda Partner View Photo
Rohit Premji Chheda Partner View Photo
Samir Narendra Jani Partner View Photo
Zaverchand Liladhar Shah Partner View Photo

Project

Godrej Bliss
New Project
08/11/2029
No
Others
Yes
C.T.S No- 163- A/2(Pt)
Common Access Road
Rehab Building
Open Plot- Proposed DP Road
Godrej Nest
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Akurli
Akurli Road
Akurli- Kandivali East
400101
3631.49
2
2
0
0

FSI Details

32601.41
0
32601.41

Bank Details

ICICI Bank Ltd
ICIC0006985

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Godrej Bliss Godrej Projects Development Limited Company Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 524 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 will be provided as per the requirement
Energy management : YES 0 As per IGBC requirements
Fire Protection And Fire Safety Requirements : YES 0 Fire Protection and Safety as per CFO requirement
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Electrical Meter Room Substation
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 water connection will be given by BMC after OC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 STP is proposed
Storm Water Drains : YES 0 Storm water drains lines will be provided
Landscaping & Tree Planting : YES 0 will be provided as per the landscape design
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 STP is proposed
Solid Waste Management And Disposal : YES 0 will be provided as per requirement

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Godrej Bliss Wing E 08/11/2029 1 1 7 39 1 0 234
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 27.75 1 0
2 Shop 18.29 1 0
3 Shop 20.45 1 0
4 Shop 27.23 1 0
5 Shop 27.64 1 0
6 Shop 28.08 1 0
7 Shop 28.18 1 0
8 Shop 29.79 1 0
9 Shop 30.18 1 0
10 2BHK 68.63 33 7
11 3BHK 87.68 32 9
12 3BHK 91.53 33 11
13 2BHK 64.6 26 8
14 2BHK 63.83 27 2
15 2BHK 63.73 31 5
16 2BHK 65.02 33 24
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 10
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 1
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Godrej Bliss Wing F 08/11/2029 1 1 7 39 1 0 290
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 63.73 31 2
2 2BHK 64.64 27 2
3 1BHK 37.61 64 18
4 1BHK 38.33 62 26
5 2BHK 60.6 32 7
6 2BHK 60.92 32 3
7 2BHK 63.83 28 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
M/s Innovations NA Architect
Gokani Consultants Pvt Ltd NA Engineer
CA Amit Jayesh Shah NA Chartered Accountant
360 REALTORS LLP A51900000246 Real Estate Agent
ASHISH MADHUKAR RUMDE A51800000821 Real Estate Agent
VASANTHA RAGHURAM SHETTY A51700001854 Real Estate Agent
Blunest Technologies Pvt Ltd A51900004449 Real Estate Agent
GRD REALTY PVT LTD A51900002118 Real Estate Agent
Honeydew Advisory Services Pvt LTD A51800004408 Real Estate Agent
JM Financial Products Limited A51900000277 Real Estate Agent
KAN INDIA REALTORS PRIVATE LIMITED A51700008693 Real Estate Agent
Krithica Sachdev A51900000022 Real Estate Agent
madhusudanan muthodi puthankalam A52000000512 Real Estate Agent
METRO PROPERTIES A51800000740 Real Estate Agent
Mumbai Aaxis Realty LLP A51800005249 Real Estate Agent
SAURABH KISHAN BIRLA A51800008525 Real Estate Agent
prakash shantaram surve A51800002011 Real Estate Agent
Propedge Advisory Private Limited A51800001003 Real Estate Agent
PROPERTYPISTOL REALTY PRIVATE LIMITED A51700000043 Real Estate Agent
Realty Junction A51700017470 Real Estate Agent
RISING HOMES A51700004600 Real Estate Agent
SRK RESIDENCY PRIVATE LIMITED A51800002923 Real Estate Agent
SYNERGY INFRACON A51900000176 Real Estate Agent
ICICI Home Finance Company Limited A51800000727 Real Estate Agent
RAHEJA ESTATE AGENCY A51800003110 Real Estate Agent
Ambrosia Designs Pvt Ltd. NA Other Professional
Godrej Projects Development Limited NA Other Professional

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 a Details of encumbrances concerned to Finance
2 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
2 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
5 Building Plan Approval / NA Order for plotted development
6 Building Plan Approval / NA Order for plotted development
7 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement