MahaRERA Application

General Information

Other Than Individual

Organization

Macrotech Developers Limited
Company
NA
Do you have any Past Experience ?
No

Address Details

412, Floor-4 17G
Vardhman Chamber
Cawasji Patel Road
Fort
Hornimon Circle
MAHARASHTRA
Konkan
Mumbai City
Mumbai City
Mumbai City
400011

Organization Contact Details

02261334251

Past Experience Details

Member Information

Member Name Designation Photo
Rajendra Narpatmal Lodha Director View Photo
Bankim Doshi Authorized Signatory View Photo

Project

Lodha Mulund Project Tower 1
New Project
30/09/2027
No
Residential
Yes
669 669/1 - 669/35 670
604 606 607 679
610 665 666 667 657-1
608 609-A 610
672 673 674 Gokhale Road
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
Gokhale Road
Mulund East
400081
950
1
1
0
0

FSI Details

16850
5600
22450.00

Bank Details

ICICI BANK LTD
ICIC0000323

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Lodha Mulund Project Tower 1 Macrotech Developers Limited Company Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Lodha Mulund Project Tower 1 Arihant Construction Company Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 320 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 As per approved layout
Water Conservation, Rain water Harvesting : YES 0 As per norms
Energy management : YES 0 As per norms
Fire Protection And Fire Safety Requirements : YES 0 As per norms
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 As per norms
Aggregate area of recreational Open Space : YES 0 As per norms
Open Parking : NO 0 NA
Water Supply : YES 0 As per norms
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 As per approved layout and norms
Storm Water Drains : YES 0 As per norms
Landscaping & Tree Planting : YES 0 As per approved layout
Street Lighting : YES 0 As per norms
Community Buildings : YES 0 To be shared across all phases of real estate proj
Treatment And Disposal Of Sewage And Sullage Water : YES 0 As per norms
Solid Waste Management And Disposal : YES 0 As per norms

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Lodha Mulund Project Tower 1 Upper Nest - Tower B 30/09/2027 0 1 0 37 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 63.75 103 65
2 2BHK 69.32 37 35
3 3BHK 84.8 32 28
4 3BHK 99.17 69 27
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 71
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 3
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 85
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

69
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 40
11 Overall Percentage of Completion of the work done For the entire Building /Wing 56.8

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Catapult Realty Consultants NA Architect
JW Consultants NA Engineer
Siddharth Bhat NA Chartered Accountant
Chirag Sarvaiya & Co NA Chartered Accountant
Vilas Desai & Associate NA Architect
K C Shah Consultants NA Engineer
SHASHI KUMAR SHARMA A52100034329 Real Estate Agent
Housenotch Private Limited A51700043835 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
5 Building Plan Approval / NA Order for plotted development
6 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement