MahaRERA Application

General Information

Other Than Individual

Organization

BAJAJ INTERNATIONAL REALTY PRIVATE LIMITED
Company
NA
Do you have any Past Experience ?
No

Address Details

106-107, 10TH FLOOR
BAJAJ BHAWAN
JAMNALAL BAJAJ MARG
226, NARIMAN POINT
JAMNALAL BAJAJ MARG
MAHARASHTRA
Konkan
Mumbai City
Mumbai City
Mumbai City
400021

Organization Contact Details

07400064212

Past Experience Details

Member Information

Member Name Designation Photo
BALKISHAN GIRIRAJ MUCHHAL Managing Director View Photo
AUSTIN SALDANHA Authorized Signatory View Photo

Project

Nityanand Nagar Vibhag IV Cooperative Housing Society Limited
On-Going Project
31/12/2018
30/06/2021
31/12/2023
No
Residential
No
684 A 684 A 1 to 69
CTS 500 499 488 486
CTS 685 686 687
POLICE HOUSING CTS 681
CTS 689 690
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
Swami Nityanand road
Andheri East
400069
8362
4
4
0
1737.82

FSI Details

27869.93
764.04
28633.97

Bank Details

HDFC BANK LTD
HDFC0000543

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 366 281 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 As per approved plans
Water Conservation, Rain water Harvesting : YES 100 As per policy
Energy management : YES 90 As per policy
Fire Protection And Fire Safety Requirements : YES 100 As per approved plans
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 As per policy
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 100 As per approved plans
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 As per approved plans
Storm Water Drains : YES 100 As per approved plans
Landscaping & Tree Planting : YES 100 As per approved plans
Street Lighting : NO 100 NA
Community Buildings : YES 0 As per approved plans
Treatment And Disposal Of Sewage And Sullage Water : YES 100 As per policy
Solid Waste Management And Disposal : YES 100 As per policy

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Nityanand Nagar Vibhag IV Cooperative Housing Society Limited Wing - A 31/12/2020 2 1 0 15 1 6 77
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 83.52 77 77
2 3BHK 111.25 1 1
3 1RK 31.84 1 0
4 1BHK 41.63 1 1
5 3BHK 68.54 1 1
6 3BHK 72.42 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Nityanand Nagar Vibhag IV Cooperative Housing Society Limited Wing - B 31/12/2020 2 1 0 15 1 8 83
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1RK 35.94 1 1
2 3BHK 83.34 14 14
3 3BHK 83.37 14 14
4 3BHK 83.43 54 54
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Nityanand Nagar Vibhag IV Cooperative Housing Society Limited Wing - C 31/12/2020 2 1 0 15 1 3 114
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 83.49 28 28
2 3BHK 84.58 14 11
3 3BHK 84.54 13 11
4 3BHK 51.68 1 1
5 3BHK 93.93 13 13
6 2BHK 72.07 14 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 Nityanand Nagar Vibhag IV Cooperative Housing Society Limited Wing - D 31/12/2020 2 1 0 13 1 0 75
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 66.87 12 12
2 3BHK 83.73 12 6
3 3BHK 83.34 12 7
4 3BHK 83.71 23 15
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Miti Designers & Planners NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
16 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
17 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
18 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
19 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
17 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
18 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
19 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
20 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
21 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
22 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
6 Disclosure of sold/ booked inventory
7 Disclosure of sold/ booked inventory
8 Disclosure of sold/ booked inventory
9 Disclosure of sold/ booked inventory
10 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000000958 ADHVIK MAHAJAN View Orders
2 CC006000000161393 Santosh Chandra Tandon View Orders