MahaRERA Application

General Information

Other Than Individual

Organization

Provident Housing Limited
Company
NA
Do you have any Past Experience ?
Yes

Address Details

130/1
-
Ulsoor Road
Bangalore
HDFC Bank Limited
KARNATAKA
Bangalore
560042

Organization Contact Details

08043439793

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1The Tree by ProvidentResidentialNA25100Ward No 72 2nd Main Road Syndicate Bank Layout Village Herohalli Gollarapalya Hosahalli Bengaluru Karnataka 56009106/153/2A75602017-06-302016-12-31

Member Information

Member Name Designation Photo
Ashish Puravankara Managing Director View Photo
Nani Choksey Managing Director View Photo

Project

Provident Palmvista D4
New Project
30/06/2028
No
Residential
Yes
884, 89, 901, 9024, 9025, 9042, 1011B, 1012, 1013
Other phases of larger project
Private Property
Other phases of larger project
Private Property
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
Kalyan-Shilphata Road
-
421204
567.14
1
1
0
3063

FSI Details

6631.46
0
6631.46

Bank Details

Indusind Bank
INDB0000008

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Provident Palmvista D4 Glory Township LLP Partnership Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Upload Agreement / MoU Copy
6 Upload Agreement / MoU Copy
7 Upload Agreement / MoU Copy
8 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 114 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 As per site & plan requirements
Water Conservation, Rain water Harvesting : YES 0 As per sanction plan
Energy management : YES 0 As per sanction plan & NOC's
Fire Protection And Fire Safety Requirements : YES 0 As per sanction plan & NOC's
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 As per sanction plan & NOC's
Aggregate area of recreational Open Space : YES 0 As per sanction plan & NOC's
Open Parking : NO 0 NA
Water Supply : YES 0 MCGM requirements & NOC's
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 As per sanction plan
Storm Water Drains : NO 0 As per sanction plan
Landscaping & Tree Planting : YES 0 As per design plan
Street Lighting : YES 0 MCGM requirements & NOC's
Community Buildings : YES 0 As per sanction plan & NOC's
Treatment And Disposal Of Sewage And Sullage Water : YES 0 NA
Solid Waste Management And Disposal : YES 0 MCGM requirements & NOC's

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Provident Palmvista D4 Palmvista D4 31/12/2027 1 1 1 33 1 17 97
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 52.87 114 51
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Anil Hassanand Jagwani NA Architect
Ten Folds NA Engineer
M Padmanabha Bhat NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
2 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement