Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1T22-23ResidentialNA6859Near Cognizant Tech Rajiv Gandhi Infotech Park phase1 Hinjawadi Pune 411057Survey No119 Part to 125 plus 154 Part to 160 plus 160/2 to 171 plus 173, Plot No1 22402017-12-312016-11-15
2B1,B2,B3OthersResidential and Commercial1939.78Near Cognizant Tech Rajiv Gandhi Infotech Park phase1 Hinjawadi Pune 411057Survey No119 Part to 125 plus 154 Part to 160 plus 160/2 to 171 plus 173, Plot No1 36962014-12-312016-09-21
3B4ResidentialNA645.46Near Cognizant Tech Rajiv Gandhi Infotech Park phase1 Hinjawadi Pune 411057Survey No119 Part to 125 plus 154 Part to 160 plus 160/2 to 171 plus 173, Plot No1 12382016-12-312017-02-13
4B6ResidentialNA630.81Near Cognizant Tech Rajiv Gandhi Infotech Park phase1 Hinjawadi Pune 411057Survey No119 Part to 125 plus 154 Part to 160 plus 160/2 to 171 plus 173, Plot No1 12312017-12-312017-02-13
5B7,B8ResidentialNA1048.6Near Cognizant Tech Rajiv Gandhi Infotech Park phase1 Hinjawadi Pune 411057Survey No119 Part to 125 plus 154 Part to 160 plus 160/2 to 171 plus 173, Plot No122402015-12-312016-09-21
6T1, T2, T3, T4ResidentialNA2347Near Cognizant Tech Rajiv Gandhi Infotech Park phase1 Hinjawadi Pune 411057Survey No119 Part to 125 plus 154 Part to 160 plus 160/2 to 171 plus 173, Plot No1 44082011-12-312015-03-07
7T5, T6, T7 ,T8ResidentialNA2347Near Cognizant Tech Rajiv Gandhi Infotech Park phase1 Hinjawadi Pune 411057Survey No119 Part to 125 plus 154 Part to 160 plus 160/2 to 171 plus 173, Plot No1 44042013-12-312015-03-07
8T9, T10, T11ResidentialNA2536.38Near Cognizant Tech Rajiv Gandhi Infotech Park phase1 Hinjawadi Pune 411057Survey No119 Part to 125 plus 154 Part to 160 plus 160/2 to 171 plus 173, Plot No1 33552014-12-312015-03-07
9T12, T13, T14ResidentialNA2536.44Near Cognizant Tech Rajiv Gandhi Infotech Park phase1 Hinjawadi Pune 411057Survey No119 Part to 125 plus 154 Part to 160 plus 160/2 to 171 plus 173, Plot No1 33612012-12-312015-03-07

Member Information

Member Name Designation Photo
ABHIJIT PRAKASH KADAM Director View Photo
MEGHALI RAVINDRA KATDARE Authorized Signatory View Photo

Project

Orion 15-16-17
New Project
01/08/2025
Yes
Residential
No
Sector No R2 F Blue Ridge S. No. 119 part to 125 plus 154 part to 160 plus 160/2 to 171 plus 173 plot no 1 and survey no 106 111/1, 112/4, 113/1, 113/2/1, 113/2/2 and 114
18 meter wide road
Green space Adj G7
Adj R2B
T 18 19 Adj R2C
MAHARASHTRA
Pune
Pune
Mulshi
Hinjavadi (CT)
Blue Ridge Approach Road
Hinjavadi
411057
16962.69
3
3
0
13312.22

FSI Details

45806.23
291.46
46097.69

Bank Details

HDFC Bank
HDFC0000060

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 558 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 -
Internal Roads & Footpaths : YES 0 -
Internal Roads & Footpaths : YES 0 -
Water Conservation, Rain water Harvesting : YES 0 OWC
Energy management : YES 0 Solar Water Heating System
Fire Protection And Fire Safety Requirements : YES 0 -
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 -
Aggregate area of recreational Open Space : YES 0 -
Open Parking : NO 0 NA
Water Supply : YES 0 -
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 STP
Storm Water Drains : YES 0 -
Landscaping & Tree Planting : YES 0 -
Street Lighting : YES 0 -
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 STP
Solid Waste Management And Disposal : YES 0 OWC

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Orion 15-16-17 Orion - 15 01/08/2025 0 1 2 33 1 0 186
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 59.90 128 124
2 2BHK 59.56 64 61
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 75
3 X number of Podiums 80
4 Stilt Floor 60
5 X number of Slabs of Super Structure 65
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 25
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 25
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

15
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 15
11 Overall Percentage of Completion of the work done For the entire Building /Wing 48.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Orion 15-16-17 Orion - 16 01/08/2025 0 1 2 33 1 0 186
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 59.56 64 60
2 2BHK 59.90 128 121
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 75
3 X number of Podiums 80
4 Stilt Floor 60
5 X number of Slabs of Super Structure 65
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 25
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 25
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

15
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 15
11 Overall Percentage of Completion of the work done For the entire Building /Wing 48.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Orion 15-16-17 Orion - 17 01/08/2025 0 1 2 33 1 0 186
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 59.90 128 118
2 2BHK 59.56 64 59
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 60
3 X number of Podiums 60
4 Stilt Floor 50
5 X number of Slabs of Super Structure 45
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 5
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

5
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 5
11 Overall Percentage of Completion of the work done For the entire Building /Wing 35

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Orion 15-16-17 High Court Mumbai 9028/2017 Civil No Writ Petition NA 2017 Matter is kept for pre admission as per sitting list
NA
Orion 15-16-17 High Court Mumbai 9029/2017 Civil No Writ Petition NA 2017 Matter is kept for pre admission as per sitting list
NA
Orion 15-16-17 High Court Mumbai ST/6443/2016 Civil No Writ Petition NA 2016 Matter is kept for pre admission as per sitting list
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
3 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
3 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
4 Proforma of Allotment letter
5 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement