MahaRERA Application

General Information

Other Than Individual

Organization

AMIT ENTERPRISES HOUSING LIMITED
Company
NA
Do you have any Past Experience ?
Yes

Address Details

1902
Amit House
Bajirao Road
Sadashiv Peth
Opp. saraswati Vidyalaya
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411030

Organization Contact Details

02024489494

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Amits Colori A to F BuildingResidentialNA13256.37Village Undri Taluka Haveli District Pune60/2/2 part and 60/362882012-12-312012-03-30
2Astonia Classic A1 to A4 BuildingResidentialNA5954.77Village Undri Taluka Haveli Dist. Pune5443842015-12-312016-11-02
3Astonia Royale A to J, Q and R BuildingResidentialNA31258.12Village Ambegaon Budruk Taluka Haveli Dist Pune62 parts, 63 parts, 56 parts125762012-08-202013-11-27

Member Information

Member Name Designation Photo
KISHOR GOVIND PATE Chairperson View Photo
ROHAN KISHOR PATE Authorized Signatory View Photo
SANJEEV GOVIND PATE Authorized Signatory View Photo

Project

AMITs COLORI Phase-II H and I Building
On-Going Project
30/04/2018
30/06/2019
Yes
Residential
No
S.N. 60/2/2 Part and 60/3, Undri, Pune
By 24 Mtr wide RP Road
AMITs COLORI Phase-I Buildings
By Adj S N 60-2-1
By Adj S N 60-2-2 Part
MAHARASHTRA
Pune
Pune
Haveli
UNDRI
Undri Road
Undri
411060
9074.53
2
2
0
3054.00

FSI Details

13325.39
0
13325.39

Bank Details

HDFC Bank Ltd
HDFC0000060

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 160 0 80

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 80 Driveways will be provided
Water Conservation, Rain water Harvesting : YES 0 Recharge pit
Energy management : YES 0 Solar Water & low energy consuming light fittings
Fire Protection And Fire Safety Requirements : YES 80 As per Fire and Safety Norms
Electrical Meter Room, Sub-Station, Receiving Station : YES 80 Substation Provided in previous Phase
Billiard Room : YES 100 common for residential tenements of all phases
Children play area : YES 100 common for residential tenements of all phases
Entrance Gate : YES 0 common for residential tenements of all phases
Gym : YES 100 common for residential tenements of all phases
Study Room : YES 100 common for residential tenements of all phases
Swimming Pool : YES 100 common for residential tenements of all phases
Table Tenis Room : YES 100 common for residential tenements of all phases
Toddler Pool : YES 100 common for residential tenements of all phases
Toddlers Play Area : YES 100 common for residential tenements of all phases
Aggregate area of recreational Open Space : YES 100 common for residential tenements of all phases
Open Parking : YES 0 -
Water Supply : YES 80 Water supply by Grampanchayat & Infra by promoter
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 85 STP Provided
Storm Water Drains : YES 80 -
Landscaping & Tree Planting : YES 80 -
Street Lighting : YES 80 -
Community Buildings : YES 100 Multipurpose Hall for all residential tetements
Treatment And Disposal Of Sewage And Sullage Water : YES 85 -
Solid Waste Management And Disposal : YES 0 OWC will be provided

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 AMITs COLORI Phase-II H and I Building Building H 0 1 1 13 1 66 80
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK Type IV 44.95 5 5
2 1.5 BHK Type I 38.90 24 24
3 1.5 BHK Type II 36.35 24 24
4 1 BHK Type I 28.57 26 26
5 1 BHK Type II 28.97 12 12
6 1 BHK Type III 31.24 10 10
7 1 BHK Type IV 34.98 1 1
8 2 BHK Type I 43.58 11 11
9 2 BHK Type II 45.96 13 13
10 2 BHK Type III 43.30 18 18
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 95
4 Stilt Floor 95
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 90
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

90
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
11 Overall Percentage of Completion of the work done For the entire Building /Wing 95
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 AMITs COLORI Phase-II H and I Building Building I 30/06/2019 0 1 1 13 1 62 80
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK Type IV 29.29 1 1
2 1 BHK Type I 28.57 34 34
3 1 BHK Type II 28.97 10 10
4 1 BHK Type III 28.95 1 1
5 1 BHK Type V 35.35 1 1
6 1.5 BHK Type I 38.86 22 22
7 1.5 BHK Type II 36.36 22 22
8 1.5 BHK Type III 38.86 1 1
9 1.5 BHK Type IV 37.09 1 1
10 2 BHK Type I 43.58 10 10
11 2 BHK Type II 45.96 11 11
12 2 BHK Type III 43.30 24 24
13 2 BHK Type IV 44.30 1 1
14 SHOP 1 18.15 1 1
15 SHOP 2 18.36 1 1
16 SHOP 3 18.36 1 1
17 SHOP 4 18.65 1 1
18 SHOP 5 16.60 1 1
19 SHOP 6 19.08 1 1
20 SHOP 7 19.08 1 1
21 SHOP 8 19.08 1 1
22 SHOP 9 9.85 1 1
23 SHOP 10 19.08 1 1
24 SHOP 11 31.30 1 1
25 SHOP 12 13.53 1 1
26 SHOP 13 23.04 1 1
27 SHOP 14 25.82 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 95
4 Stilt Floor 95
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 90
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

90
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
11 Overall Percentage of Completion of the work done For the entire Building /Wing 95

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Mr Prafulla R Nadkarni NA Architect
Mr Reza Kabul NA Architect
Mr Umesh Joshi NA Engineer
Saikhushi construction NA Contractor
Avinash Enterprises NA Contractor
Sanket Electroline NA Contractor
ICICI Home Finance Company Limited A51800000727 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
AMITs COLORI Phase-II H and I Building Divisional Jt Registrar Pune Division Pune 49 Others No Appeal NA 2017 Hearing
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Certificates of Architect (Form 4)
1 Status of Formation of Legal Entity
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC005000000023203 Jitendra Sankpal View Orders
2 CC005000000023203 Varsha Sankpal View Orders