MahaRERA Application

General Information

Other Than Individual

Organization

PRAJAPATI CONSTRUCTIONS LIMITED
Company
NA
Do you have any Past Experience ?
Yes

Address Details

146-147
PRAJAPATI CONSTRUCTIONS LTD
LAKRI BUNDER ROAD
DARUKHANA
BEHIND KARAN STEEL
MAHARASHTRA
Konkan
Mumbai City
Mumbai City
Mumbai City
400010

Organization Contact Details

02227456291
www.prajapatigroup.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1PRAJAPATI VIHARResidentialNA1850PLOT NO.84 SECTOR NO 55PLOT NO 84 SECTOR NO 551922018-06-302018-06-30
2PRAJAPATI VIHAROthersRESIDENTIAL + COMMERCIAL1850PLOT NO 84 SECTOR 55 DRONAGIRI URAN 400702PLOT NO 842922017-12-312017-12-11

Member Information

Member Name Designation Photo
RAAJESH ROHITASHWA PRAJAPATI Managing Director View Photo
RAKESH ROHITASHWA PRAJAPATI Authorized Signatory View Photo

Project

PRAJAPATI OPAL
New Project
30/12/2025
No
Others
No
PLOT NO 172 TO 174 PLOT NO 186 TO 190
20 MTRS WIDE ROAD
PLOT NO 207 AND 8 MTRS WIDE ROAD
PLOT NO 185 AND PLOT NO 175
PLOT NO 191 AND PLOT NO 207
MAHARASHTRA
Konkan
Raigarh
Panvel
Panvel
SECTOR 10
NAVI MUMBAI
410206
2074.07
1
1
0
404.35

FSI Details

3578.24
151.28
3729.52

Bank Details

ICICI Bank
ICIC0000334

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 66 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 IN LATER SCOPE OF WORK
Water Conservation, Rain water Harvesting : YES 100 Rain water harvesting tank in later scope of work
Energy management : YES 100 IN LATER SCOPE OF WORK
Fire Protection And Fire Safety Requirements : YES 100 IN LATER SCOPE OF WORK
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 IN LATER SCOPE OF WORK
Aggregate area of recreational Open Space : YES 100 IN LATER SCOPE OF WORK
Open Parking : NO 0 NA
Water Supply : YES 100 IN LATER SCOPE OF WORK
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Chambers and lines upto Municipal Drain
Storm Water Drains : YES 100 Terrace & open area storm water to RWH tank overfl
Landscaping & Tree Planting : YES 100 IN LATER SCOPE OF WORK
Street Lighting : YES 100 IN LATER SCOPE OF WORK
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : YES 100 IN LATER SCOPE OF WORK

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 PRAJAPATI OPAL PRAJAPATI OPAL 30/12/2025 0 1 2 17 1 0 57
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP GROUND FLOOR 78.45 1 0
2 SHOP GROUND FLOOR 81.62 1 0
3 SHOP GROUND FLOOR 59.43 1 0
4 SHOP GRAUND ANDFIRST 94.11 1 0
5 SHOP FIRST FLOOR 456.44 1 0
6 SHOP GROUND ANDFIRST 147.80 1 0
7 SHOP ON GROUND FLOOR 46.77 1 0
8 SHOP GROUND FLOOR 80.74 1 0
9 1BHK 34.10 30 28
10 2BHK 52.44 30 24
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SOYUZ TALIB NA Architect
CHIRAG PUTHRAN NA Engineer
NEHAL M FARIA NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
3 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
11 Building Plan Approval (IOD)
12 Building Plan Approval (IOD)
13 Building Plan Approval (IOD)
14 Building Plan Approval (IOD)
15 Building Plan Approval (IOD)
16 Building Plan Approval (IOD)
17 Building Plan Approval (IOD)
18 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Form 2A
2 Form 2A
3 Form 2A
4 Form 2A
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
3 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
4 Proforma of Allotment letter
5 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
4 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
5 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
4 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement