MahaRERA Application

General Information

Other Than Individual

Organization

Sukhwani Chawla Developers
Partnership
NA
Do you have any Past Experience ?
No

Address Details

S No 208/2a
Sukhwani House
Station Road
Pimpri
Opp Swaminathan Hospital
MAHARASHTRA
Pune
Pune
Mulshi
Pimpri
411018

Organization Contact Details

02027425484

Past Experience Details

Member Information

Member Name Designation Photo
Sunil Nandlal Chawla Authorized Signatory View Photo
Gurmukh Jangaldas Sukhwani Partner View Photo
Prakash Nandlal Chawla Partner View Photo
Basant Totaram Sukhwani Partner View Photo

Project

Sukhwani Skylines
New Project
30/12/2027
Yes
Others
No
S No 113/1/2 113/2/1 113/2/2
18 Mtrs wide main road
S No 97 Part S No 102 Part S No 103 Part
S No 112 S No 113 Part
S No 114 Part S No 95 Part S No 96 Part
MAHARASHTRA
Pune
Pune
Mulshi
Wakad
New Wakad Hinjewadi Link Road
Vinode Nagar
411057
25000.00
9
3
6
2389.84

FSI Details

44532.65
0
44532.65

Bank Details

HDFC Bank
HDFC0000437

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 733 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 44 As per Architect Plans
Water Conservation, Rain water Harvesting : YES 55 As per Consultants Details
Energy management : YES 0 As per Electrical Consultant Details
Fire Protection And Fire Safety Requirements : YES 44 As per CFO Norms
Electrical Meter Room, Sub-Station, Receiving Station : YES 60 As per Electrical Consultant Details
Aggregate area of recreational Open Space : YES 0 As per Sanction Plans
Open Parking : YES 0 As per Architect Plans
Water Supply : YES 81 As per PCMC Norms
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 44 As per Consultants Plans
Storm Water Drains : YES 55 As per Consultant Details
Landscaping & Tree Planting : YES 0 As per Landscape Consultant Plans
Street Lighting : YES 0 As per Electrical Consultant Details
Community Buildings : YES 33 As per Sanction Plans
Treatment And Disposal Of Sewage And Sullage Water : YES 50 As per Consultants Details
Solid Waste Management And Disposal : YES 0 As per Consultant Details

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Sukhwani Skylines A - Sanctioned 31/12/2022 0 1 1 14 1 0 114
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 51.45 30 29
2 2BHK 51.69 10 10
3 2BHK 56.65 2 1
4 2BHK 51.85 10 10
5 2BHK 56.43 4 3
6 2BHK 51.41 8 8
7 2BHK 57.15 2 2
8 2BHK 51.16 10 10
9 2BHK 56.95 6 6
10 2BHK 57.37 3 1
11 2BHK 52.19 36 32
12 2BHK 56.72 12 7
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 50
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 87
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 92
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

98
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 33
11 Overall Percentage of Completion of the work done For the entire Building /Wing 81
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Sukhwani Skylines B - Sanctioned 31/12/2022 0 1 1 14 1 0 92
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 51.48 29 29
2 2BHK 51.86 10 10
3 2BHK 56.67 2 2
4 2BHK 56.72 12 8
5 2BHK 52.22 36 34
6 2BHK 56.95 6 6
7 2BHK 56.43 3 2
8 2BHK 51.13 5 4
9 2BHK 51.16 4 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 90
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 93
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

98
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 36
11 Overall Percentage of Completion of the work done For the entire Building /Wing 85.7
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Sukhwani Skylines C-Sanctioned 31/12/2022 0 1 1 14 1 94 94
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 51.11 29 28
2 2BHK 52.70 4 4
3 2BHK 52.77 5 5
4 2BHK 56.68 1 1
5 2BHK 56.72 12 7
6 2BHK 52.68 1 1
7 2BHK 56.89 1 1
8 2BHK 56.95 6 6
9 2BHK 56.96 3 2
10 2BHK 52.74 6 5
11 2BHK 56.74 1 1
12 2BHK 51.83 36 35
13 2BHK 52.74 6 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 90
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 88
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

98
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 26
11 Overall Percentage of Completion of the work done For the entire Building /Wing 84.2
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 Sukhwani Skylines D-Sanctioned 31/07/2024 0 1 1 14 1 0 94
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 59.95 60 13
2 2BHK 45.72 4 0
3 3BHK 56.93 57 7
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 75
4 Stilt Floor 100
5 X number of Slabs of Super Structure 31
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 7
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 2
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 5
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

4
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 14
11 Overall Percentage of Completion of the work done For the entire Building /Wing 43.8
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
5 Sukhwani Skylines E 31/12/2026 0 1 1 14 1 0 92
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 59.85 34 0
2 2 BHK 59.13 36 0
3 2 BHK 58.84 12 0
4 2 BHK 59.56 10 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 5
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 14
11 Overall Percentage of Completion of the work done For the entire Building /Wing 21.9
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
6 Sukhwani Skylines F 31/12/2026 0 1 1 14 1 0 92
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 59.85 36 0
2 2 BHK 59.13 36 0
3 2 BHK 58.84 12 0
4 2 BHK 59.56 8 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 95
2 X number of Basement(s) and Plinth 50
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 14
11 Overall Percentage of Completion of the work done For the entire Building /Wing 15.9
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
7 Sukhwani Skylines G 31/12/2026 0 1 1 14 1 0 115
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 58.07 12 0
2 2 BHK 59.85 32 0
3 2 BHK 59.56 11 0
4 2 BHK 57.85 12 0
5 2 BHK 59.13 36 0
6 2 BHK 58.84 12 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 95
2 X number of Basement(s) and Plinth 23
3 X number of Podiums 13
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 5
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 14
11 Overall Percentage of Completion of the work done For the entire Building /Wing 15
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
8 Sukhwani Skylines H - MHADA and Commercial 31/12/2022 0 1 0 15 1 61 64
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 45.92 33 0
2 2 BHK 45.73 10 0
3 2 BHK 45.10 10 0
4 2 BHK 45.83 11 0
5 Shop 13.60 1 0
6 Shop 14.37 1 0
7 Shop 16.30 2 0
8 Shop 14.64 1 0
9 Shop 13.63 1 0
10 Shop 16.27 1 0
11 Shop 14.66 2 0
12 Shop 14.49 1 0
13 Shop 16.56 4 0
14 Shop 14.67 2 0
15 Shop 14.94 2 0
16 Shop 13.60 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 87
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 97
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 22
11 Overall Percentage of Completion of the work done For the entire Building /Wing 75.6
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
9 Sukhwani Skylines I Commercial Hall 31/12/2026 0 1 0 3 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Commercial Hall 252.44 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 53
4 Stilt Floor 100
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 5
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 14
11 Overall Percentage of Completion of the work done For the entire Building /Wing 37.2

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Laxman Thite Architect Milind R Patil NA Architect
Ravi Nevatia NA Chartered Accountant
Urjal Consultant NA Other Professional
Zopate Electricals Consultants PVT NA Other Professional
G A Bhilare Consultant Pvt Ltd NA Other Professional
Arpee Construction NA Contractor
Krishna Construction NA Contractor
Sharma Construction NA Contractor
Gurudatta Enterprises NA Contractor

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Sukhwani Skylines Civil Judge Senior Division Pune Special Civil Suit No 1086/2018 Civil No Suit NA 2018 Pending
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
4 Other
5 Other
1 Other – Finance
1 Other – Technical
2 Other – Technical
3 Other – Technical
4 Other – Technical
5 Other – Technical
6 Other – Technical
7 Other – Technical
8 Other – Technical
9 Other – Technical
10 Other – Technical
11 Other – Technical
12 Other – Technical
13 Other – Technical
14 Other – Technical
15 Other – Technical
16 Other – Technical
17 Other – Technical
18 Other – Technical
19 Other – Technical
20 Other – Technical
21 Other – Technical
22 Other – Technical
23 Other – Technical
24 Other – Technical
25 Other – Technical
26 Other – Technical
27 Other – Technical
28 Other – Technical
29 Other – Technical
30 Other – Technical
31 Other – Technical
32 Other – Technical
33 Other – Technical
34 Other – Technical
35 Other – Technical
36 Other – Technical
1 Foreclosure of the Project
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement