MahaRERA Application

General Information

Other Than Individual

Organization

N.ROSE DEVELOPERS PVT LTD
Company
NA
Do you have any Past Experience ?
No

Address Details

1ST FLOOR
NORTHERN HEIGHTS
SHANTI NAGAR DONGRI
DAHISAR EAST
SAMMELAN HOTEL
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
400068

Organization Contact Details

02228973767

Past Experience Details

Member Information

Member Name Designation Photo
HIREN PRATAP ASHAR Managing Director View Photo
NATWARLAL SHANKARLAL PUROHIT Authorized Signatory View Photo
NARAYAN ANAND SHELAR Managing Director View Photo
RAMJI HIRABHAI BHARWAD Managing Director View Photo

Project

NORTHERN HEIGHTS
On-Going Project
31/12/2019
30/06/2021
30/09/2022
No
Others
No
1625 PT 1648 PT 1653 PT 1654 PT 1657 PT 1663 PT
EAST
WEST
NORTH
SOUTH
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
S V ROAD
DAHISAR EAST
400068
8164.09
2
2
0
0

FSI Details

16639
32962.83
49601.83

Bank Details

STATE BANK OF INDIA
SBIN0015781

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 445 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 COMPLETED
Water Conservation, Rain water Harvesting : YES 90 YET TO START
Energy management : YES 50 YET TO START
Fire Protection And Fire Safety Requirements : YES 60 WORK IN PROGRESS
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 SUB STATION RCC WORK COMPLETE
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 0 YET TO START
Water Supply : YES 40 WORK IN PROGRESS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 80 WORK IN PROGRESS
Storm Water Drains : YES 80 WORK IN PROGRESS
Landscaping & Tree Planting : YES 40 YET TO START
Street Lighting : YES 50 YET TO START
Community Buildings : YES 70 WORK IN PROGRESS
Treatment And Disposal Of Sewage And Sullage Water : YES 0 YET TO START
Solid Waste Management And Disposal : YES 0 YET TO START

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 NORTHERN HEIGHTS C WING 31/12/2020 1 1 3 49 1 63 445
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 105.98 4 4
2 3BHK 101.96 4 2
3 3BHK 100.45 2 2
4 STOREROOM 8.93 5 0
5 2BHK 51.92 1 0
6 2BHK 57.97 74 62
7 2BHK 60.61 4 1
8 2BHK 60.87 2 0
9 2BHK 62.28 4 0
10 2BHK 70.61 64 62
11 2BHK 74.53 4 4
12 2BHK 78.55 4 3
13 3BHK 97.55 74 58
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 NORTHERN HEIGHTS D WING 31/12/2020 1 1 3 49 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 70.61 62 61
2 3BHK 97.55 74 70
3 2BHK 78.55 4 2
4 3BHK 101.96 6 5
5 3BHK 105.98 4 2
6 STOREROOM 8.20 5 0
7 4BHK 140.32 1 1
8 COMMERCIAL 43.39 1 1
9 COMMERCIAL 46.36 1 1
10 COMMERCIAL 46.45 10 10
11 COMMERCIAL 48.77 2 2
12 COMMERCIAL 49.42 1 1
13 COMMERCIAL 50.07 2 2
14 COMMERCIAL 72.93 1 1
15 COMMERCIAL 74.60 1 1
16 COMMERCIAL 91.51 1 1
17 COMMERCIAL 99.96 1 1
18 COMMERCIAL 121.79 1 1
19 COMMERCIAL 149.57 2 2
20 2BHK 50.46 1 0
21 2BHK 62.06 78 71
22 2BHK 65.61 4 0
23 2BHK 68.28 4 0
24 2BHK 74.53 4 3
25 COMMERCIAL 23.88 4 4
26 COMMERCIAL 25.08 3 3
27 COMMERCIAL 29.82 1 1
28 COMMERCIAL 36.05 3 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SHANTANOO RANE AND ASSOCIATES NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
16 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
17 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
18 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of the allotment letter and agreement for sale
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical