MahaRERA Application

General Information

Other Than Individual

Organization

SHREE BALAJI ASSOCIATES PUNE LLP
Partnership
NA
Do you have any Past Experience ?
No

Address Details

PLOT NO 5
SAN MAHU COMMERCIAL COMPLEX
BUND GARDEN ROAD
CAMP
OPP POONA CLUB
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411001

Organization Contact Details

02024113702

Past Experience Details

Member Information

Member Name Designation Photo
GANGA HOUSING PVT LTD NA Partner View Photo
ANURAG SUBHASH GOEL Partner View Photo
SUBHASH SITARAM GOEL Authorized Signatory View Photo

Project

GANGA NEWTOWN PHASE I
On-Going Project
31/12/2019
31/12/2019
No
Others
No
SNO 12/1 12/2 12/3 12/4/29
SNO12 PART
SNO 12 PART
DP ROAD
SNO 12 PART
MAHARASHTRA
Pune
Pune
Haveli
DHANORI
DHANORI
DHANORI
411015
6741.41
3
3
0
542

FSI Details

12698.19
0
12698.19

Bank Details

AXIS BANK
UTIB0000110

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 87 87 75

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 80 AS PER ARCT CERTIFICATE
Water Conservation, Rain water Harvesting : YES 100 AS PER ARCT CERTIFICATE
Energy management : YES 0 AS PER ARCT CERTIFICATE
Fire Protection And Fire Safety Requirements : YES 95 AS PER ARCT CERTIFICATE
Electrical Meter Room, Sub-Station, Receiving Station : YES 95 AS PER ARCT CERTIFICATE
Aggregate area of recreational Open Space : YES 0 AS PER ARCT CERTIFICATE
Open Parking : NO 0 NA
Water Supply : YES 70 AS PER ARCT CERTIFICATE
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 80 AS PER ARCT CERTIFICATE
Storm Water Drains : YES 100 AS PER ARCT CERTIFICATE
Landscaping & Tree Planting : YES 20 WORK STARTED
Street Lighting : YES 0 AS PER ARCT CERTIFICATE
Community Buildings : YES 0 AS PER ARCT CERTIFICATE
Treatment And Disposal Of Sewage And Sullage Water : YES 0 AS PER ARCT CERTIFICATE
Solid Waste Management And Disposal : YES 0 AS PER ARCT CERTIFICATE

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 GANGA NEWTOWN PHASE I A1 31/12/2019 0 1 1 13 1 0 22
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 65.69 4 4
2 2 BHK 65.90 5 2
3 2 BHK 66.11 1 0
4 2.5 BHK 74.49 5 5
5 2.5 BHK 77.81 1 1
6 2.5 BHK 74.74 6 6
7 SHOP 32.61 1 0
8 SHOP 35.93 1 0
9 SHOP 42.62 1 0
10 SHOP 44.70 1 0
11 2.5 BHK 67.83 5 5
12 2.5 BHK 68.13 5 4
13 2.5 BHK 68.33 1 1
14 2 BHK 65.19 5 5
15 2 BHK 65.20 5 3
16 2 BHK 65.21 1 1
17 2 BHK 65.27 6 5
18 2 BHK 65.26 10 6
19 2 BHK 65.33 5 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
11 Overall Percentage of Completion of the work done For the entire Building /Wing 86
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 GANGA NEWTOWN PHASE I A2 31/12/2019 0 1 1 13 1 0 28
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 38.12 5 5
2 1 BHK 38.52 1 1
3 1 BHK 38.53 1 1
4 1 BHK 34.75 10 10
5 1 BHK 35.15 11 11
6 1 BHK 37.72 5 5
7 1 BHK 37.74 5 5
8 2 BHK 53.89 5 5
9 2 BHK 53.91 5 5
10 2 BHK 54.09 10 10
11 2 BHK 54.27 2 2
12 2 BHK 56.54 12 12
13 2 BHK 56.67 10 10
14 1 BHK 38.10 5 5
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
11 Overall Percentage of Completion of the work done For the entire Building /Wing 85.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 GANGA NEWTOWN PHASE I A3 31/12/2019 0 1 1 13 1 0 37
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 65.90 5 2
2 2 BHK 66.11 1 0
3 2.5 BHK 74.42 12 12
4 2.5 BHK 74.52 10 8
5 2.5 BHK 77.80 1 1
6 2 BHK 65.19 11 9
7 2 BHK 65.26 10 10
8 2 BHK 65.27 6 4
9 2 BHK 65.33 5 4
10 2 BHK 65.69 4 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 90
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
11 Overall Percentage of Completion of the work done For the entire Building /Wing 87

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
MS PARVEZ JAMADAR AND ASSOCIATES NA Architect
MS G A BHILARE CONSULTANTS NA Engineer
MQA ASSOCIATES NA Architect
RAVINDRA PISAL NA Other Professional
PROPERTY CHEF CONSULTING SERVICES A52100000044 Real Estate Agent
Paresh Lachman Hardwani A52100000163 Real Estate Agent
Nitesh Roop Narayan Khare A52100000106 Real Estate Agent
R-Constellation Pvt. Ltd. A52100000304 Real Estate Agent
NITIN SHANKAR KADDE A52100000577 Real Estate Agent
Big Deal Properties (India) Pvt. Ltd A52100000579 Real Estate Agent
VIKAS SATISH GUPTA A52100002607 Real Estate Agent
CBRE South Asia Private Limited A51600003050 Real Estate Agent
SQUARE YARDS CONSULTING PRIVATE LIMITED A51800000454 Real Estate Agent
ICICI Home Finance Company Limited A51800000727 Real Estate Agent
HDFC Realty Limited A51900000107 Real Estate Agent
JONES LANG LASALLE RESIDENTIAL PRIVATE LIMITED A51900000108 Real Estate Agent
Amit Satpal Gogia A52100000021 Real Estate Agent
360 REALTORS LLP A51900000246 Real Estate Agent
SANTOSH KUMAR A52100000143 Real Estate Agent
UMANG JITENDER SONI A52100000520 Real Estate Agent
SAGAR MOHAN NANAWARE A52100001558 Real Estate Agent
VARUN DEVENDRA MATHURAWALA A52100001699 Real Estate Agent
Valency Realty Pvt. ltd. A51900003909 Real Estate Agent
OM SAI CONSTRUCTION NA Contractor
ANUP CONSTRUCTION NA Contractor
S S C CONSTRUCTION NA Contractor
DEVENDRA ELECTRICAL NA Contractor
RUKMANA CHAVAN NA Contractor
A G ELECTRICALS NA Contractor
BALAJI DECORATION NA Contractor
TAMANA CHAVAN NA Contractor
VIKAS AND NILIMA BHOSEKAR NA Architect
SURYAKANT BHOSALE NA Other Professional
Dhruba Prasad Gupta A52100010221 Real Estate Agent
Nimbleland Infracon LLP A52100004080 Real Estate Agent
RANJEET SINGH YADAV A52100000402 Real Estate Agent
SAGAR MOHAN NANAWARE A52100001558 Real Estate Agent
Haresh Girdharlal Dodeja A52100007293 Real Estate Agent
Signet Space Realty Private Limited A52100007915 Real Estate Agent
Rakesh Kumar Maurya A52100000605 Real Estate Agent
PRASHANT SHASHIKANT ZAREKAR A52100006251 Real Estate Agent
SANJIV KUMAR PRASAD A52100002106 Real Estate Agent
AMIT HANJARIMAL OSWAL A52100007065 Real Estate Agent
Nishant Madhukar Bhoinallu A52100007451 Real Estate Agent
WISTERIA REAL VISION PVT LTD A52100003089 Real Estate Agent
My Dream Flat LLP A52100009090 Real Estate Agent
Preeti Tiwari A52100000400 Real Estate Agent
Rajendra Kashiram Chavan A52100001915 Real Estate Agent
RAHUL ANAND GAIKWAD A52100000661 Real Estate Agent
ROHIT SATPATHY A52100007862 Real Estate Agent
RAKESH KUMAR DHIRAJ A52100012014 Real Estate Agent
CORAZON HOMES AND SECURITIES A52100000096 Real Estate Agent
Ashwani Ramlal Kapoor A51800013920 Real Estate Agent
PROPTIGER MARKETING SERVICES PRIVATE LIMITED A51700000030 Real Estate Agent
Abhishek Indrapal Singh Parmar A52100011870 Real Estate Agent
Ravi Ranjan Kumar Gautam A52100007332 Real Estate Agent
KPRBSK REALTORS PRIVATE LIMITED A52100012415 Real Estate Agent
Udit Methi A52100007675 Real Estate Agent
Relaint infraspace Realty A52100008910 Real Estate Agent
Saideep Satish Patil A52100013984 Real Estate Agent
SHARAD BABAN KHALSE A52100019642 Real Estate Agent
Parvej Saipan Mulla A52100019889 Real Estate Agent
PROPBUYING REALTORS PVT LTD A52100000476 Real Estate Agent
Utkarsh Sharma a52100013128 Real Estate Agent
RAHUL YASHWANT KARANDIKAR a52100019454 Real Estate Agent
Vivek G Pungaliya a52100000690 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement