MahaRERA Application

General Information

Other Than Individual

Organization

BHOSALE BUILDCON
Partnership
NA
Do you have any Past Experience ?
No

Address Details

Office No 207 / 208
V Times Square
Plot No -3
Sector 15
CBD Belapur
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400614

Organization Contact Details

09324298655

Past Experience Details

Member Information

Member Name Designation Photo
Sumeet Dhanraj Garad Partner View Photo
Babasaheb Mahadeo Bhosale Authorized Signatory View Photo
Babasaheb Mahadeo Bhosale Partner View Photo
Prashant Prabhakar Patekar Partner View Photo

Project

BHOSALE BLUESTAR
New Project
28/08/2022
31/03/2024
No
Others
Yes
Plot No -336
9 Mtr Wide Road
Plot No 357A
9 Mtr Wide Road
Plot No -337
MAHARASHTRA
Konkan
Raigarh
Panvel
Wahal
Sector -24
Pushpak New
410206
179.78
1
1
0
0

FSI Details

268.66
0
268.66

Bank Details

Abhyudaya Co -Op Bank Ltd
ABHY0065060

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
BHOSALE BLUESTAR RATNAMALA RAVINDRA SAWANT Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
BHOSALE BLUESTAR RAHUL RAVINDRA SAWANT Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
BHOSALE BLUESTAR LOKESH RAVINDRA SAWANT Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 3 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 Not commenced. Will be provided as per CIDCO norms
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Not commenced. Will be provided as per CIDCO norms
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 Not commenced. Will be provided as per CIDCO norms
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 Not commenced. Will be provided as per CIDCO norms
Storm Water Drains : YES 0 Not commenced. Will be provided as per CIDCO norms
Landscaping & Tree Planting : YES 0 Not commenced. Will be provided as per CIDCO norms
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 BHOSALE BLUESTAR BHOSALE BLUESTAR 31/08/2021 0 1 0 5 1 0 3
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 23.89 4 2
2 1BHK 27.21 4 1
3 Shop 6.76 1 0
4 Shop 6.09 1 0
5 Shop 6.14 1 0
6 Shop 9.14 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 77

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
ORGANIC ARCHITECTS & PLANNERS NA Architect
RUTUJA SAJJAN NARSINGH NA Chartered Accountant
B M CONSTRUCTIONS NA Contractor
ASSOCIATED STRUCTURAL CONSULTANTS LLP NA Engineer
RERA EASY NA Other Professional

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
3 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement