MahaRERA Application

General Information

Other Than Individual

Organization

Enerrgia Skyi Developers
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

Sr No 77/2/16 plot no 21
Sugat Residency
Bhusari Colony
Kothrud
Behind Ved Vihar
MAHARASHTRA
Pune
Pune
Haveli
Kothrud
411038

Organization Contact Details

02025207279

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Skyi Songbirds Phase IResidentialNA28878.97Sr No 274 and others Village Bhugaon Tal Mulshi Dist Pune274 and others53882015-09-302016-01-11
2Skyi Songbirds Phase IIResidentialNA12490.42Sr No 274 and others Village Bhugaon Tal Mulshi Dist Pune274 and others33572016-10-312017-03-31

Member Information

Member Name Designation Photo
Sushant Mohan Jadhav Partner View Photo
Sushant Mohan Jadhav Authorized Signatory View Photo
Nitin Murlidhar Gaikwad Authorized Signatory View Photo

Project

Skyi Songbirds Phase B
On-Going Project
31/05/2019
30/11/2020
30/05/2022
Yes
Residential
Yes
274/1 and others Bhugaon Mulshi Pune
Road
Survey No 456
Ramnadi
Survey No 275 276 427 431 432 451
MAHARASHTRA
Pune
Pune
Mulshi
Bhugaon
Paud Road
Bhugaon
412115
11340.31
2
2
0
14255.07

FSI Details

12931.05
1439
14370.05

Details of RERA Designated Separate Bank Account

HDFC Bank
HDFC0000007

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Skyi Songbirds Phase B Samruddha Properties Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Skyi Songbirds Phase B Shrikant Shravan Mahale Individual Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Skyi Songbirds Phase B Kamalabai Venkatnarsaiyya Gannu Individual Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 entrance gate included in this
Water Conservation, Rain water Harvesting : YES 95 NA
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 this includes water tank for fire fighting
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 NA
Raw Water Supply Scheme : YES 100 Raw Water Supply Scheme from Lavale Mula River to
Aggregate area of recreational Open Space : YES 0 NA
Open Parking : YES 0 NA
Water Supply : YES 100 NA
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 NA
Storm Water Drains : YES 100 NA
Landscaping & Tree Planting : YES 98 includes nest park river promenade walking track
Street Lighting : YES 95 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 75 Sewage Treatment Plant
Solid Waste Management And Disposal : YES 100 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Skyi Songbirds Phase B Building No 5 31/05/2020 0 1 0 13 1 0 58
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 109.73 10 10
2 2BHK 90.44 1 1
3 2BHK 68.2 22 19
4 3BHK 95.59 24 22
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 95
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 89.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Skyi Songbirds Phase B Building No 6 31/05/2020 0 1 0 13 1 0 59
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 90.44 1 1
2 3BHK 95.59 24 20
3 2BHK 68.2 22 18
4 3BHK 109.64 10 9
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 96
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 79.1

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Salil Ranadive Architects NA Architect
Delcons Consultant India Pvt Ltd NA Engineer
360 REALTORS LLP A51900000246 Real Estate Agent
PROPBUYING REALTORS PVT LTD A52100000476 Real Estate Agent
R-Constellation Pvt. Ltd. A52100000304 Real Estate Agent
WISTERIA REAL VISION PVT LTD A52100003089 Real Estate Agent
Million SqFt Realty Pvt Ltd A52100007986 Real Estate Agent
CORAZON HOMES AND SECURITIES A52100000096 Real Estate Agent
GLOBAL REALTORS A52100000018 Real Estate Agent
Vaibhav Prakash Jathar A52100006148 Real Estate Agent
Ronisun Knowledge Application Center A52100005788 Real Estate Agent
MAISON CHASSE PRIVATE LIMITED A52100000327 Real Estate Agent
PURNENDU PRASAD A52100007668 Real Estate Agent
Amanco Realtors Pvt Ltd A52100006230 Real Estate Agent
Avinash Gajanan Bhangale A52100012039 Real Estate Agent
subodh shukla A52100006838 Real Estate Agent
SUGGESTED PROPERTY PRIVATE LIMITED A52100000184 Real Estate Agent
PROPENGINE REALTECH LLP A52100000628 Real Estate Agent
Vaibhav Shivaji Jadhaw A52100004052 Real Estate Agent
Property Pointer Private Limited A52100000787 Real Estate Agent
Bluenest Properties LLP A52100007204 Real Estate Agent
Rahul Kumar Sharma A52100004246 Real Estate Agent
ELARA MARKETING SERVICES PRIVATE LIMITED A51700000030 Real Estate Agent
HDFC Realty Limited A51900000107 Real Estate Agent
UMESH RAMESH PAWAR A52100000006 Real Estate Agent
ABHIJIT SAHEBRAO SABBARWAR A52100000382 Real Estate Agent
PROPERTY CHEF CONSULTING SERVICES A52100000044 Real Estate Agent
PROPFINDER INDIA PRIVATE LIMITED A52100004005 Real Estate Agent
Kunal Chandrakant Khande A52100012841 Real Estate Agent
Vishwas Pandurang Garud A52100010681 Real Estate Agent
SANDEEP PRAMOD URANKAR A52100011007 Real Estate Agent
SOURABH BELIYA A52100010736 Real Estate Agent
Apna Ghar Lifespaces LLP A52100008848 Real Estate Agent
SQUARE YARDS CONSULTING PRIVATE LIMITED A51800000454 Real Estate Agent
GAURAV SURESH NAHTA A52100003487 Real Estate Agent
Propndeals Realty Pvt Ltd A52100003345 Real Estate Agent
Nesting Dreams Private Limited A52100012998 Real Estate Agent
Aparna Mahesh Kunte A52100014548 Real Estate Agent
Lokesh kumra A52100006340 Real Estate Agent
Realtors Compass A52100001849 Real Estate Agent
Rohan Ashokkumar Jadhav A52100013555 Real Estate Agent
Sagar Ganesh Waichole A52100015101 Real Estate Agent
The Altitude Consultatnt A52100015124 Real Estate Agent
LIFE SPACE PROPERTY SOLUTIONS PVT LTD A52100000993 Real Estate Agent
Vikas Das A52100002200 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Skyi Songbirds Phase B Civil Judge Junior Division 312 Civil No Suit NA 2017 The case is disposed off as settled
NA
Skyi Songbirds Phase B Civil Judge Senior Division 1208 Civil No Suit NA 2016 framing of issues
NA
Skyi Songbirds Phase B Civil Judge Junior Division 852 Civil No Suit NA 2015 steps
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
3 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
2 Architect’s Certificate on Completion of Project (Form 4)
3 Architect’s Certificate on Completion of Project (Form 4)
4 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
2 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement
1 Other
1 Other – Finance
1 Other – Technical

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC005000000177743 Enerrgia Skyi Developers View Orders