MahaRERA Application

General Information

Other Than Individual

Organization

REGENCY NIRMAN LTD
Company
NA
Do you have any Past Experience ?
Yes

Address Details

1ST FLOOR
REGENCY HOUSE
OPP. VISHNU DARSHAN
NEAR AMAN TALKIES ROAD
NEAR AMAN TALKIES ROAD
MAHARASHTRA
Konkan
Thane
Ulhasnagar
Ulhasnagar (M Corp.)
421002

Organization Contact Details

02512560003

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Regency CrestOthersResidential Cum Commercial7000Regency Crest Plot no 40 Sector 19 Kharghar Navi Mumbai - 410 210Plot no 4021422014-06-302014-12-10
2Regency HeightsOthersResidential & Commercial27335.9Nr Brahmand Phase-1 AzadNagar Kolshet Road Thane W - 400607Survey No 73, Hissa No 1,2,3,4,5, Survey No 74, Hissa No 1,2,3,5, Survey No 75, Hissa No 10P, Survey43202015-03-152015-03-31
3Regency ClassicOthersResidential & Commercial12400Survey NO 54 Hissa no 4 Mumbai Bangalore Highway Near Mahindra Showroom Baner Pune-411045Survey No 54/431322015-10-312016-03-28
4Regency WillowsOthersResidential & Commercial19858Plot no 61 Green Valley Behind Fariyas Hotel Tungari LonavalaPlot no 61 survery no 28 Tungari Lonavala, Maral, Pune24242014-02-032014-02-03
5Regency Sarvam Phase 1OthersResidential & Commercial23488.32Gupta Estates Near Titwala Railway Station Ganpati Mandir Road Titwala E - 421605.S no 42/1, 42/2, 42/3, 42/4/1/2, 42/5, 42/6, 47/1, 50/1/B, 50/2, 220/1, 251/1, 261/1, 223/1, 224/153502013-10-312014-03-21
6Regency Sarvam Phase 2OthersResidential & Commercial26247.81Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 421605S no 42/1, 42/2, 42/3, 42/4/1/2, 42/5, 42/6, 47/1, 50/1/B, 50/2, 220/1, 251/1, 261/1, 223/1, 224/164242015-03-312015-08-20
7Regency Sarvam Phase 3OthersResidential & Commercial30909.13Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 421605S no 42/1, 42/2, 42/3, 42/4/1/2, 42/5, 42/6, 47/1, 50/1/B, 50/2, 220/1, 251/1, 261/1, 223/1, 224/165522015-03-312015-12-16
8Regency Sarvam Phase 4OthersResidential & Commercial13676.03Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 421605S no 42/1, 42/2, 42/3, 42/4/1/2, 42/5, 42/6, 47/1, 50/1/B, 50/2, 220/1, 251/1, 261/1, 223/1, 224/132342016-04-302016-06-09
9Regency Sarvam Phase 5OthersResidential & Commercial10079.23Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 421605S no 42/1, 42/2, 42/3, 42/4/1/2, 42/5, 42/6, 47/1, 50/1/B, 50/2, 220/1, 251/1, 261/1, 223/1, 224/121342016-12-312017-02-10
10Regency Sarvam Phase 6OthersResidential & Commercial16890.79Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 421605S no 42/1, 42/2, 42/3, 42/4/1/2, 42/5, 42/6, 47/1, 50/1/B, 50/2, 220/1, 251/1, 261/1, 223/1, 224/132712017-05-032017-05-03
11Regency Sarvam Phase 7OthersResidential & Commercial16890.90Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 421605S no 42/1, 42/2, 42/3, 42/4/1/2, 42/5, 42/6, 47/1, 50/1/B, 50/2, 220/1, 251/1, 261/1, 223/1, 224/132712017-05-312017-07-18

Member Information

Member Name Designation Photo
ANIL JESSARAM BATHIJA Authorized Signatory View Photo
MAHESH SATYANARAYAN KHAIRARI Managing Director View Photo

Project

Regency Anantam Phase III
New Project
30/09/2023
No
Residential
No
S.NO. 101/3A, 3B, 3C, 3D, 47/1, 48, 44/2, 49/1, 49/2, 50/1, 50/2,50/4,50/5,51/2A, 54/1,97,52/2, 51/4
OPEN LAND AREA
30 MTR WIDE DP ROAD
OPEN LAND AREA
OPEN LAND AREA
MAHARASHTRA
Konkan
Thane
Kalyan
Dawadi
Dombivli
Dombivli
421306
38498.94
7
7
0
26455.68

FSI Details

62033.27
10926.66
72959.93

Bank Details

The Saraswat Co Operative Bank Ltd
SRCB0000345

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 10 -
Water Conservation, Rain water Harvesting : YES 10 -
Energy management : YES 0 -
Fire Protection And Fire Safety Requirements : YES 0 -
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 -
Aggregate area of recreational Open Space : YES 0 -
Open Parking : YES 0 -
Water Supply : YES 0 -
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 -
Storm Water Drains : YES 5 -
Landscaping & Tree Planting : YES 10 -
Street Lighting : YES 0 -
Community Buildings : YES 0 Club House
Treatment And Disposal Of Sewage And Sullage Water : YES 0 -
Solid Waste Management And Disposal : YES 0 -

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 Regency Anantam Phase III Alpine 31/03/2023 0 1 1 25 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 59.50 92 0
2 2 BHK 59.10 92 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 5
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 Regency Anantam Phase III Begonia 31/03/2023 1 1 1 26 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 59.50 92 0
2 2 BHK 59.10 92 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 5
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 Regency Anantam Phase III Blossom 31/03/2023 1 1 1 26 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 59.50 92 0
2 2 BHK 59.10 92 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 20
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 22
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 Regency Anantam Phase III Bluebell 31/03/2023 1 1 1 26 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 59.50 92 0
2 2 BHK 59.10 92 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 30
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 Regency Anantam Phase III Primrose 31/03/2023 1 1 1 26 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 40 184 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 5
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
6 Regency Anantam Phase III Rosalyn 31/03/2023 1 1 1 26 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 40 184 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 5
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
7 Regency Anantam Phase III Rosemary 31/03/2023 1 1 1 26 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 40 184 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 5
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SAC CORP NA Contractor
M/s Vitan Consultant NA Architect
JW Consultants LLP NA Engineer
Adv Satish Supal NA Other Professional
Adv Ashok Advani NA Other Professional
Adv Shailendra Jalawar NA Other Professional

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Details of encumbrances
Details of encumbrances
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other